Loading...
Resolution No. 80511 RESOLUTION NO. 8051 2 3 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF VERNON APPROVING AND AUTHORIZING THE EXECUTION OF A 4 CONTRACT FOR DETAILED ENGINEERING, PROCUREMENT, 5 CONSTRUCTION AND STARTUP FOR THE MALBURG GENERATING STATION PROJECT BY AND BETWEEN THE CITY OF VERNON 6 AND SCOTT COMPANY 7 8 WHEREAS, the City of Vernon ("City") is proceeding at this 9 time to develop a 134 MW Combined Cycle Power Plant officially named 1.0 the Malburg Generating Station (the "Malburg Project") for the purpose 11 of installing additional generating capacity that will yield an 12 efficient, cost-effective, and reliable source of electric generation 13 to the City of Vernon's constituents; and 14 WHEREAS, City staff has determined that it needs the services 15 of a consultant to provide detailed engineering, procurement, 16 construction ("EPC") and startup services for the Malburg Project; and 17 WHEREAS, between June 21, 2001 and November 14, 2001, the 18 Utilities Department sent out questionnaires to potential bidders, in ig order to ascertain their interest in the EPC contract,' and to pre- 20 qualify a certain pool of prospective bidders; and 21 WHEREAS, the Utilities Department received nine (9) 22 responses; and 23 WHEREAS, on February 15, 2002, the Utilities Department sent 24 out a Request for Proposals ("RFP") for the EPC contract; and 25 WHEREAS, responses to the RFP were received from the 26 following entities: Scott Co., University Marelich Mechanical, 27 ARB/Black & Veatch, and TIC/BiBB/Kiewitt; and 28 WHEREAS, the City's Project Engineer, Carter -Burgess, had 1 2 3 4 5 6 7 8 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 lestimated the cost of the EPC to be significantly less than any of the Jbids received; and WHEREAS, the Utilities Department rejected all bids and contacted all of the responders to inquire about their willingness to enter into negotiations regarding the EPC contract price; and WHEREAS, thereafter, the Utilities Department was authorized to enter into exclusive negotiations with Scott Co., the lowest responsible bidder, in order to lower the bid price; and WHEREAS, on July 24, 2002, the .City Council of the City of Vernon adopted Resolution No. 8032 approving an interim Letter Agreement with Scott Co. to proceed with the development and completion of the engineering design and drawings for the Malburg Project while the EPC contract was being negotiated, so that there would be as little confusion as possible regarding the interpretation of the contract specifications; and WHEREAS, Scott Co. and Vernon entered into negotiations between July 24, 2002 and August 14, 2002 regarding the EPC contract; and WHEREAS, the Utilities Department has determined that the Scott Company, also known as Scott Co. Industrial Contractors, the Scott Companies, Inc. and Scott Co. of California (collectively "Scott"), a firm specializing in Industrial Construction Services, could provide the lowest overall package price meeting the Department's specifications and requirements; and WHEREAS, the Utilities Department has prepared and submitted on August 14, 2002, a Staff Report detailing the services that will be provided by Scott under the EPC contract and the costs of these services; and - 2 - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 WHEREAS, by letter dated August 14, 2002, Bruce V. Malkenhorst, City Administrator/City Clerk, recommended that the contract with Scott be approved and executed; and WHEREAS, Scott was the lowest responsible bidder who bid on the EPC RFP, and has lowered its original price; and WHEREAS, the City Council of the City of Vernon has determined that, pursuant to the provisions of subsection (a) of Section 2.27 of the Vernon City Code, it is in the public interest and necessity to enter into an EPC contract with Scott setting forth the terms and conditions of the services to be performed for the Malburg project to enhance services provided to the Vernon community. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF VERNON AS FOLLOWS: SECTION 1: The City Council of the City of Vernon hereby finds and determines that the recitals contained hereinabove are true and correct. SECTION 2: The City Council of the City of Vernon hereby approves the EPC Contract with Scott, a copy of which is attached hereto as Exhibit "A" and made a part hereof. SECTION 3: The City Council of the City of Vernon hereby authorizes the Mayor and the City Clerk to execute said Contract for, and on behalf of, the City of Vernon. SECTION 4: The City Council of the City of Vernon hereby directs the City Clerk, or his designee, to send one fully executed Agreement to: Scott Company Attn. Steve Klaus, Project Manager 14920 S. San Pedro St. Gardena, CA 90248 - 3 - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 SECTION 5: The City Clerk of the City of Vernon shall certify to the passage of this resolution, and thereupon and thereafter the same shall be in full force and effect. APPROVED AND ADOPTED this 4th day of September, 2002. ATTEST: BRUCE V. MALKENHORST, City Clerk EONIS C. BUR Mayor - 4 - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 STATE OF CALIFORNIA ) ss COUNTY OF LOS ANGELES ) I, BRUCE V. MALKENHORST, City Clerk of the City of Vernon, do hereby certify that the foregoing Resolution, being Resolution No. 8051, was duly adopted by the City Council of the City of Vernon at a regular meeting of the City Council duly held on Wednesday, September 4, 2002, and thereafter was duly signed by the Mayor of the City of Vernon. (SEAL) BRUCE V. MALKENHORST, City Clerk - 5 - SUPPORTING DOCUMENTS EXHIBIT AM" SEE BINDER FOR COMPLETE CONTRACT WITH APPENDICES CONTRACT FOR DETAILED ENGINEERING, PROCUREMENT, CONSTRUCTION, and STARTUP FOR THE MALBURG GENERATING STATION PROJECT VERNON, CALIFORNIA August 14, 2002 EPCContract 0_8_14.doc CONTRACT Table Of Contents Page 1. GENERAL 2 A Scope of Work 2 B Definitions......................................................... 2 2. RISK OF LOSS ....................................................... 8 3. CONTRACT PRICE AND PAYMENTS ................. 8 A. Contract Price 8 B. Payment Schedule 8 C. Invoices 9 D Form and Content 10 E. Payment 10 F. Failure to Achieve Progress 10 G. Payments Withheld 10 H. Retainage 11 1. Payments Not Acceptance of Work 11 4 NOTICE TO PROCEED 11 5. CHANGE ORDERS ................................ 1 I A. General I B. Change Work Authorization 12 C. Unauthorized Changes 12 D. Effect on Schedule and Warranties and Guarantees 12 E. Payment Procedure 12 6. BONDING REQUIREMENTS 13 7. PRE-EXISTING SITE CONDITIONS ..................... 13 8. LAWS AND REGULATIONS ................... 13 9. INSPECTION....................................................... 14 10. FORCE MAJEURE................................................. 14 it. DELAYS/SUSPENSION.......................................... 14 12. WARRANTIES...................................................... 15 A. General 15 B. Warranty Period 15 C. Remedy of Defects 15 D. Survival of Warranties 16 E. Extent of Warranties and Guarantees 16 F. Prevention 16 G. Assignment of Warranties and Guarantees 16 13. INFORMATION FURNISHED TO AND BY THE CITY 16 14. INFORMATION FURNISHED TO CONTRACTOR 16 A. Access to Confidential Information 16 B. No Disclosure 17 C. Court Ordered Disclosure 17 D. Remedies 17 15. TECHNICAL DATA ................................................ 17 16. PATENTS............................................................. 17 17. CANCELLATION/DEFAULT...................................... 18 A. Termination 18 B. Contractor's Breach 18 C. City's Breach 18 18. ASSIGNMENT....................................................... 18 19. PARTIAL INVALIDITY ............................................ 19 20. CHOICE OF LAW ................................................... 19 21. INSTALLATION/FIELD SERVICES ........................... 19 22. INDEMNIFICATION AND INSURANCE ..................... 19 EPCContract_0_8_ 14.doc it A. Indemnity 19 B. Insurance 19 23. NON -WAIVER ......................... ......... .............--- 20 24- AMENDMENTS..................................................... 20 25. ENTIRE AGREEMENT ............................................. 20 26. BENEFIT OF AGREEMENT ...................................... 20 27. FORUM SELECTION ............................................... 20 28. COUNTERPARTS................................................... 20 29. NOTICES.............................................................. 21 30. INDEPENDENT CONTRACTOR ................................ 21 31. CONTRACTOR NOT AGENT .................................... 21 32. REVIEW OF EXISTING CONDITIONS ...................... 22 A. Premises 22 B. Verification of Existing Conditions 22 C. Statement of Fact 22 33. SUPERVISION BY CONTRACTOR ............................ 22 A Management of Work 22 B. Control of Work 23 34. GOVERNMENTAL REGULATIONS AND TAXES ...... 23 A. Permits and Licenses 23 B. Laws and Regulations 23 35. LIQUIDATED DAMAGES ......................................... 24 A. Delays 24 B. HP Steam Loss 24 C. Liquidated Damage Payment 24 D. Sole Remedy 24 36. MAXIMUM AGGREGATE LIQUIDATED DAMAGES 24 37. PERFORMANCE GUARANTEES ................................ 24 A. Performance Guarantees 24 B. Noise Emissions 25 C. Auxiliary Power Limit 25 D. HP and LP Steam line Pressure Loss 25 E. Obligations of the Contractor 25 F. Corrective Action 25 G. Standards for Plan of Corrective Action 25 38. LIMITATION OF LIABILITY .................................... 25 A. 25 B. 26 39. DISPUTE RESOLUTION .................................... 26 40. ENVIRONMENTAL PROTECTION ............................ 26 A. Qualified Personnel 26 B. Material 26 C. Compliance with Laws 26 D. Hazardous Materials Removal 27 E. Environmental Indemnity 27 F. Material Safety Data Sheets 27 G. Suspension and Notification 27 41. LABOR AND MATERIALS ....................................... 28 A. General 28 B. Employment of Licensed Personnel 28 C. Assignment of Individuals 28 D. Material 28 E. Start up Spare Parts and Special Tools 28 F. Quality Control Program 29 G. Testing 29 H. City's Right to Inspect 29 EPCContract_0_8_ 14.doc i i i APPENDIX Page Appendix 1 Specification for Combined Cycle Power Plant 31 Appendix 2 Project Control Requirements for Contract 32 Appendix 3 Unconditional Waiver & Release Upon Final Payment 36 Appendix 4 Insurance Schedule 40 Appendix S Miscellaneous 42 EPCContract_0_8_ 14.doc iv CONTRACT THIS CONTRACT is made, entered into and executed in duplicate originals, either copy of which may be considered and used as the original hereof for all purposes, as of this , 2002, in the City of Vernon, County of Los Angeles, BY AND BETWEEN THE CITY OF VERNON 4305 Santa Fe Avenue Vernon, CA 90058 AND Contractor SCOTT COMPANY 14290 South Pedro Gardena, CA 90248 RECITALS WHEREAS, the City of Vernon ("City") has completed the development of a Combined Cycle Power Plant (hereinafter, the "Project") for purposes of installing additional generating capacity within the City that is capable of yielding cost effective, efficient and reliable electricity to meet its goals, while meeting Federal, State and local environmental and siting requirements; and . WHEREAS, City has sought proposals for the detailed engineering, procurement, construction and startup of a combined cycle power plant to create the Project; and WHEREAS, Contractor submitted a proposal to City dated April 29, 2002 for the equipment and services defined herein; and WHEREAS, City's Utilities Department has determined that the construction of the Project and the purchase of the equipment and services from the Contractor will assist City in meeting its electricity goals and is in the public interest; and WHEREAS, Contractor has advised City that it is qualified to perform such services under this Contract NOW, THEREFORE, THE PARTIES HERETO DO MUTUALLY AGREE AS SET FORTH HEREIN: EPCContract_0_8_ 14.doc I 1. GENERAL The Contract shall consist of the following: Purchase Order The terms and conditions as set forth in this Contract Appendix "1" Specification for Combined Cycle Power Plant Appendix "2" Project Control Requirements for Contract Appendix "3" Unconditional Waiver & Release Upon Final Payment Appendix "4" Insurance Schedule Appendix "5" Miscellaneous All Appendices are attached hereto and incorporated by reference as though fully set forth herein. To the extent that there are any conflicts between the terms of the Appendices and the teens and conditions set forth below, the terms and conditions set forth herein shall prevail. The above order of precedence shall prevail in the event that there is a conflict or inconsistency among the documents that comprise the Contract. A. Scope of Work The Project shall consist of the detailed design and engineering, balance of plant equipment supply, and installation of a "two on one" natural gas fired combined cycle power plant as defined in Appendix 1. B. Definitions AFC Application for Certification to the California Energy Commission AQMD Shall mean the South Coast Air Quality Management District. Beneficial Use Shall mean that the Contractor has completed the Work (including commissioning requirements) and the plant is ready for the Stability and Performance Testing by the City and the City has provided a Notice of Acceptance. Best Efforts Shall mean those efforts which a skilled, competent, experienced, prudent contractor would use to perform the requirements of the Contract in a timely manner exercising the degree of professional skill, care, competence, and prudence customarily imposed on a contractor performing similar services for similar electric utility projects. For the purposes of the Contract, a timely manner shall mean strict adherence to the milestone schedule dates. Business Day Shall refer to normal business days at the City of Vernon, Monday through Thursday, excluding legal holidays. Bid Shall mean the offer or proposal of the Bidder submitted on the prescribed forms setting forth the price or prices for the Work to be performed. EPCContract_0_8_ 14.doc 2 Bidder Shall mean all Parties approved to bid on the RFQ Package as determined by the City. Change Order Shall mean a design or field Change Order or Amendment to this Contract, signed by City's Representative, authorizing an addition, deletion or revision in the Work or an adjustment in the Schedule or any change to the Contract Price resulting therefrom. City Shall mean the City of Vernon, a California Municipal Corporation. City or Owner's Shall mean that individual designated by City, who shall have the Representative responsibility and authority specifically delegated to such individual by City and made known in writing to Contractor. Combined Cycle Power Shall mean the complete Malburg Generating Station units 1,2 & 3 Plant generating units and the auxiliaries and controls as required to produce a complete and operable power station as defined by the Specification, Appendix 1. Contract Shall mean this Contract and all of the Appendices, as such Contract and Appendices now exist and as they may be hereafter amended from time to time. Contract Price Shall mean that price specified in Section 3 of the Contract that is the total amount payable by City to Contractor for the Work to be performed hereunder. Contractor's Project Shall mean that individual designated by Contractor who shall be Manager responsible for the performance of the Work, be authorized to execute Change Orders and to act on behalf of Contractor and its Subcontractors. Commercial Operation Shall mean the successful completion of all Emissions Tests and Performance Tests and acceptance of the Combined Cycle Power Plant for dispatch by the City. Commissioning Shall mean the services and craft work required to check out all mechanical, electrical and control systems and subsystems and declare the System ready for its Stability Test after Mechanical Completion. Contract Documents Shall mean the Purchase Order, the terms and conditions asset forth in this Contract, Appendix 1 Specification for Combined Cycle Power Plant, Appendix 2 Project Control Requirements for Contract, Appendix 3 Unconditional Wavier & Release Upon Final Payment, Appendix 4 Insurance Schedule, and Appendix 5, the Proposal Farm EPCContract 0 8 14.doc 3 Contract Time Schedule Shall mean the period during which Contractor will be required to deliver, erect, commission, and startup the System under this Contract. Contractor Shall mean Scott Company, (Scott), its legal representatives, successors, and assigns. Contract Drawings Shall mean all drawings, diagrams, illustrations, schedules, and other data which are specifically prepared by or for the Contractor to illustrate some portion of the Work and all illustrations, brochures, standard schedules, prepared by a supplier and submitted by the Contractor to illustrate material or equipment for some portion of the Work. Day Shall mean a calendar day and shall include Saturdays, Sundays and holidays, except that, in the event that an obligation to be performed under this Contract falls due on a Saturday, Sunday or legal holiday in the State of California, the obligation shall be deemed due on the next business day. Defects or Deficiencies Shall mean materials and workmanship that do not conform to Contract Drawings and/or specifications, are of inferior workmanship, or will materially and adversely affect the performance of the Work. Defective Work Shall mean work that is unsatisfactory, damaged, faulty, deficient, does not conform to the Contract, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract. Delaying Event Emissions Test Engineer or City's Engineer Equal Shall mean a delay in the performance of the Work caused by City or an event of Force Majeure. The purpose of the Emissions Tests will be to demonstrate that the unit meets the emissions guarantees for the specified fuel, i.e. natural gas. The Emissions Tests will also serve as a compliance test to demonstrate that the Combined Cycle Power Plant complies with all guaranteed emissions limits as specified in the HRSG Contract between the City of Vernon and Alstom Power. Shall mean Carter & Burgess, Inc. Shall mean equal as determined by the City. EPCContract 0 8 14.doc 4 Environmental Law Shall mean any federal, state, regional or local law, regulation, decision of the courts, ordinance, rule, code, order, directive, guidelines, permit or permit condition, currently existing or as amended, enacted, issued or adopted in the future, which relates in any way to worker or workplace safety, environmental conditions, environmental quality or policy, health and/or safety issues or concerns (including product safety). Environmental Law includes, without limitation, the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended (42 USC, Section 9601 et. seq.), the Resource Conservation and Recovery Act (42 USC, Section 6901 et. seq.), the Carpenter -Presley -Tanner Hazardous Substance Account Act (California Health & Safety Code, -Section 25300 et. seq.), the California Hazardous Waste Control Law (California Health & Safety Code, Section 25100 et. seq.), the Occupational Safety and Health Act (29 USC § 651 et. seq.), the California Occupational Safety and Health Act (California Labor Code § 6300 et. seq.), and any regulations or rules promulgated thereunder. Final Payment Shall mean the last payment of the remaining Retainage after the Contractor has fulfilled all the obligations defined in this Contract. FOB Jobsite Shall mean when the conveyance has stopped next to the off-loading area at the Jobsite. Force Majeure Shall have the meaning set forth in Section 10 herein. Jobsite Shall mean the location of Station A at 2715 East 50th Street, Vernon, CA 90058. Generating Hours Shall mean operating the Combined Cycle Power Planttogenerate electricity electrical grid from minimum to maximum load as defined in Appendix 1, Part 1. Government Agency Shall mean any federal, state or local government agency or other public body having the mandate, authority or power to implement, coordinate, administer or enforce an Environmental Law. Governmental Rules Shall mean all laws, regulations, orders, decrees, conditions of any franchise, license, permit or other authorization issued by a governmental authority, and decisions of courts and governmental agencies. EPCContract 0 8 14.doc Hazardous Materials Shall mean any chemical, substance, material, controlled substance, object, conditions, solid or hazardous waste or combination thereof which is or may be, hazardous to human health or safety or the environment due to its radioactivity, ignitability, corrosivity, reactivity, toxicity, or other harmful or potentially harmful properties or effects. Hazardous Material include, without limitation, oil or petroleum and petroleum products, asbestos and any asbestos containing materials, radon, polychlorinated biphenyls (PCBs), urea formaldehyde insulation, lead paints and coatings, and all of those chemicals, substances, materials, controlled substances, objects, conditions and waste or combinations thereof which are now or become in the future listed, defined or regulated in any manner by any federal, state or local Environmental Law. Laws and Regulations; Shall mean laws, rules, regulations, ordinances, codes, and/or Laws or Regulations orders defined in the AFC. Material Shall mean all materials, machinery, equipment, construction equipment, supplies, and items, as described in the Contract and necessary to successfully complete the Work described in the Contract Documents. Mechanical Completion Shall mean the date defined in Section 3 when the Contractor has completed the installation and the System is ready for Commissioning. Mobilization Shall mean the date defined in the Contract that the Contractor can commence Work on the Jobsite. Notice to Proceed Shall mean the written notice to be issued by City to Contractor, directing the commencement of the Work or portion of the Work. Notice of Acceptance Shall mean written notification provided by the City defining the completion of the Work or portion of the Work Owner Shall mean the City of Vernon.. Parties Shall mean Contractor and City collectively. The Parties may at times herein be referred to individually as Party. Payment Application Shall mean the written explanation of the Contractor's request for monthly payment for reimbursement based on quantities installed multiplied by the unit installation prices plus material quantities and equipment delivered to the Jobsite or adjacent laydown area. Performance Test Shall mean the testing of the Combined Cycle Power Plant to verify that the guaranteed performance values are met as defined in the Specification. EPCContract_0_8_ 14.doc 6 Performance Guarantees Shall mean the Performance Guarantees set forth in Section 37 of this Contract. Purchase Order Shall mean the standard purchase order that is issued by the City. Retainage Shall mean the withholding of payment by City as set forth in Section 3H of this Contract. RFQ Package Shall mean the City furnished bid documents, including applicable specifications, drawings, data sheets, and sample contract. Schedule Shall mean the Construction Execution Plan Schedule of key dates and milestones for the timely completion of the Work. Services Shall mean all related work to be supplied by Contractor, including furnishing of necessary equipment, craft labor, supervision, startup labor, vendor technical support (for Contractor furnished equipment) and required management, as described in the Contract and necessary to successfully complete the Work described in the Contract. Specification Shall mean the scope of work and the documents included and referenced in Appendix 1 to this Contract including Part 1-Technical Specification, Part 2-Erection Requirements and Part 3-Technical Attachments. Stability Test Shall mean a test that is conducted after Commissioning is completed in order to verify that the Combined Cycle Power Plant can operate in a stable condition at various loads within the conditions specified in the operating manuals over a 24 hour period. When the Stability Test has been completed successfully, the plant shall be deemed ready for Performance Testing. Subcontractor Shall mean any person, firm, or corporation that provides under contract with Contractor the design engineering, construction, equipment, labor and materials for some part of Contractor's obligation under the terms of this Contract. System Shall mean the Combined Cycle Power Plant. Underground Facilities Shall mean all pipeline, conduits, ducts, cables, wires, manholes, vaults, tanks, or other such facilities or attachments, and any encasements containing such facilities that have been installed or are existing underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone, cable television, computer or control data, sewage, drainage, traffic, control systems, or water. EPCContract_0_8_ 14.doc 7 Witness Points Shall mean a test or inspection point during manufacturing for which City indicates a desire to witness. Work The Work shall include all of the home -office, on -site related engineering, design, supervision, labor, Contractor equipment, construction equipment, tools, fabrication, materials, startup, Commissioning as required in the Contract and required to provide City with a functioning System. 2. RISK OF LOSS Title and risk of loss or damage shall pass to the City and shall be deemed to be complete upon Beneficial Use. 3. CONTRACT PRICE AND PAYMENTS A. Contract Price City shall pay Contractor the Contract Price of Forty Three Million Nine Hundred Thousand and 00/100 Dollars ($43,900,000.00) for the Work to be performed by Contractor under this - Contract. Contractor shall not be entitled to payment exceeding the Contract Price, except to the extent that the Contract Price may be changed in accordance with the terms of this Contract. Prices shall not include sales, or use taxes, special financing fees or value-added taxes, the City shall either pay any and all such applicable charges or provide Contractor with acceptable exemption certificates. B. Payment Schedule Contractor and City shall mutually agree to an earned installed quantity Payment Application. Payment will be made in accordance with the agreed -upon monthly -earned progress less five percent (5%) retention (the "Retainage") until Commercial Operation and receipt of as -built data. Payments will also be paid in accordance with the Payment Application in Appendix 2 Commencement and Completion of Workset forth below. The Engineer will perform a quantity validation to approve the Pay ApplicationPayment Application. Neither the final certificate nor final payment shall relieve the Contractor from responsibility for defects in design, materials and workmanship. Five percent (5%) retention will be withheld until the progress or the project reaches fifty percent (50%) complete. All subsequent invoices rendered shall be paid net with no retention. EPCContract_0_8_ 14.doc 8 SCHEDULE DATES SUBJECT TO AFC APPROVAL Estimated Award Date August 21, 2002 Mobilization October 15, 2002 Estimated Contractor to Start Onsite Construction December 3, 2002 Estimated Combustion Turbine Unit 1 Mechanical Installation Complete July 20, 2003 Estimated Steam Turbine Unit 3 mechanically Complete August 8, 2003 Estimated Combustion Turbine Unit 2 Mechanical Installation Complete August 15, 2003 Estimated HRSG Unit 1 Hydrostatic test Complete September 8, 2003 *Estimated HRSG Unit 2 Hydrostatic Test Complete October 8, 2003 Mechanical Completion November 30, 2003 Beneficial Use March 26 2004 Completion of the Performance Test Aril 2, 2004 Commercial Operation Aril 12, 2004 Payment Application Date Milestone Description 1. 8/21/02 Contract Award 2. 12/03/02 On Site Mobilization 3. 12/31/02 Engineering, Submittals, Procurement of balance of Plant 4. 08/01/03 Erection of HRSG #1 Modules 5. 09/15/03 Erection of HRSG #2 Modules 6. 07/20/03 Erection of CTG #1 7. 8/15/03 Erection of CTG #2 8. 8/08/03 Erection of ST #3 9. 11/08/03 Hydrotest of Power Train #1 10.11/22/03 Hydrotest of Power Train #2 11. 11/30/03 Completion of Mechanical Work 12.03/26/04 Beneficial Use Contract Percentage 10%* 10%* 10% 15% 15% All payments except those identified with an asterisk will be reviewed and approved by the City based on quantities installed and or deliveries as defined in the Schedule. C. Invoices Contractor shall submit an invoice to City on a monthly basis based on progress agreed to herein. Contractor shall not include progress payments made to Subcontractors of material or equipment during its manufacture thereof. The adjacent laydown area and Contractor's Gardena facility can be. considered part of the project site for partial payments for delivery; however, the risk of loss shall be determined by Section 2 of this Contract. EPCContract 0 8 14.doc 0J 0 D. Form and Content Contractor shall provide adequate documentation to City's Representative to support its invoice for purposes of confirming the accuracy of the invoice. E. Payment Payment will be due net 30 days after City's receipt of Contractor's invoice. F. Failure to Achieve Progress In the event City, in its sole discretion, elects to pay all or any portion of any such payment, notwithstanding Contractor's failure to make progress pursuant to Schedule, such payment shall not be deemed a waiver by City of the requirement for timely completion of said progress, or of City's right to withhold future progress payments pending completion of the progress required. G. Payments Withheld City may withhold payment and shall withhold payment to the extent indicated by the City's Representative to be necessary to protect City from loss because of - (a) any defective Work not remedied whether or not payment has been made therefore; (b) any claim of lien or stop notice has been filed or recorded, or City has received notice that a claim of lien or stop notice may be filed or recorded, regarding; (c) any damage caused by the Contractor, its Subcontractors or agents to the City, its employees, officers or agents while Contractor is performing its duties under this Contract; (d) any claim by a Subcontractor that it has not been paid any amount due and owing from Contractor (e) Contractor fails to pay, when due, any amount of principal or interest or is otherwise in breach of any agreement in respect to any of its indebtedness or guarantee of indebtedness; fails to pay its debts as they come due; becomes insolvent; makes an assignment for the benefit of creditors; files a petition, or becomes the subject of a petition filed against it, in any bankruptcy, insolvency or similar proceeding; or one or more final judgments are entered against it in the aggregate amount in excess of Ten Million Dollars and 00/100 ($10,000,000.00) and the same shall remain un-discharged and un-stayed for sixty (60) days; (f) reasonable evidence that the Work cannot be completed as required by the Contract; (g) failure to carry out the Work in accordance with the Contract; or (h) the amount of any exception taken by the City as a result of a progress quantity audit. EPCContract_0_8_ 14.doc 10 H. Retainage City may apply the Retainage and other amounts withheld against amounts owed to City by Contractor under this Contract, or payable by the City to third Parties by reason of the Contractor's breach of any of its obligations under this Contract, and shall pay the remainder with the Final Payment. Payment shall be made in accordance with the agreed upon progress less five percent (5%) retention of the gross billing each month until the progress or the project reaches fifty percent (50%) completion which amount shall be due and payable to Contractor upon the successful completion of the Performance Test and delivery to City of the as -built data and drawings required by the Contract. All subsequent invoices rendered shall be paid net with no retention. Upon successful completion of the Performance Test, or in the event the Performance Test has not been conducted within the time period set forth herein, or in the event City elects not to run the Performance Test for causes not due to Contractor, Contractor shall submit the following: (1) the as -built drawings and other documents required under Appendix 1, Specification and (ii) data establishing payment or satisfaction of all obligations, including without limitation, releases and waivers of liens and assignment of warranties and consents to assignment of warranties, arising out of this Contract. I. Payments not Acceptance of Work No payment made hereunder shall be considered as approval or acceptance of any Work by City. Payment of Applications for Payment shall be subject to correction or adjustment by City in subsequent payments of invoices submitted by Contractor. 4. NOTICE TO PROCEED The City shall provide written notice to the Contractor, directing the commencement of the engineering and or construction of the Work or portion of the Work as necessary. Contractor shall not perform any portion of the requirements of this Contract without written Notice to Proceed from City. 5. CHANGE ORDERS A. General Only City may issue a request for Change Order under this Contract. Such request shall be by written notification to Contractor. As soon as practicable after receipt of the notice, Contractor shall prepare and forward to City, in writing, the price for the change or extra Work in accordance with the requirements of this Section and any required adjustment to the Schedule. Except for minor modifications to the Work, not involving extra cost and consistent with the purposes of the Work, and except in an emergency endangering life or property, no extra work or change shall be performed unless a written Change Order from the City authorizes the extra work or change. EPCContract_0_8_ 14.doc I 1 } B. Change Work Authorization Should the City authorize a Change Order, Contractor shall furnish the necessary labor with requisite equipment and small tools, and/or materials required for performing such additional work. All authorized changes and the agreed to price shall be confirmed and directed through a Change Order. The price shall include all costs associated with performing the Change Order, including the impact on the Schedule for the original Work, inefficiencies and overhead created by the Change Order. All Change Orders shall be performed under the terms and conditions of this Contract. All Change Orders shall be signed by both City's Representative and Contractor's Representative before Contractor begins work on the Change Order. The total dollar value for any individual Change Order shall not exceed Twenty Thousand Dollars and 00/100 ($20,000.00) under any condition. This dollar limitation shall not be circumvented by the issuance of more than one Change Order for a specified change or extra work. Any changes that may exceed this amount, if any, must be agreed to by an Amendment to this Contract. C. Unauthorized Changes Contractor hereby expressly waives any compensation for any changes to the Work or any extra work that is performed by Contractor if such changes or extra work is unauthorized by an executed Change Order. No compensation for labor or schedule impacts from such unauthorized work shall be considered. D. Effect on Schedule and Warranties and Guarantees Contractor shall have seven (7) days after receipt of a Change Order request to notify City in writing that the change requested will have an adverse effect on Contractor's ability to meet the scheduled date for Beneficial Use, or upon any of Contractor's warranties or guarantees under this Contract. Such notice shall provide a detailed statement of the reasons for and the extent of any such effect. City shall have seven (7) days in which to respond to such notice. If City agrees with the representations in Contractor's notice, the date of Beneficial Use and/ or the warranties or guarantees shall be changed as appropriate. Unless directed otherwise by City, Contractor shall proceed with the Work during the exchange of notices described in this Section. E. Payment Procedure As a condition precedent to the right to receive any compensation for changes or extra work pursuant to a Change Order, Contractor shall famish to the City an itemized bill of the cost of such work and, unless it is so received, the claim for said additional work shall be deemed waived by Contractor. The total of the itemized Change Order shall be entered on Contractor's monthly invoice, properly identified under the designated numbered Change Order, and payment shall be made in accordance with this Contract. EPCContract_0_8_ 14.doc 12 V 6. BONDING REQUIREMENTS Contractor shall, upon execution of the Contract and before beginning Work, furnish an executed Performance Bond and a Labor and Materials Payment Bond each for one hundred percent (100%) of the Contract Price with a corporate surety, guaranteeing the Work will be done according to the Work and Specifications, and further, that Contractor will rebuild, repair, or replace any or all items which have proven defective due to unsatisfactory material and/or workmanship; or due to failure to meet the conditions, requirements and/or specific guarantees noted in the referenced Specifications. Such bonds shall be written with a qualified surety company licensed to do business in California and listed in current U.S. Treasury Form 370 and with Best Rating of "A" or better. Such bonds shall be effective for a period extending to one (1) year from the date of acceptance of the Work by City. Contractor will supply a bond on and subject to the terms and conditions of Standard A 1 A Form 312. Contractors Bond excludes any liability by Surety for Performance Guarantees. 7. PRE-EXISTING JOBSITE CONDITIONS Nothing herein shall be interpreted as placing any responsibility or liability on: (a) Contractor for pre-existing Jobsite conditions related to pollution, contamination, hazardous waste, asbestos or toxic materials or for the generation, emission or disposal of such substances; or (b) City for pollution, contamination, hazardous waste, asbestos or toxic material introduced to the Jobsite by Contractor including the generation, emission, or disposal of such Contractor introduced substances. City shall indemnify, defend and hold harmless Contractor against any and all claims or liabilities based on the conditions identified in paragraph (a) above. Contractor shall indemnify, defend and hold harmless City, its officers, employees and agents against any and all claims or liabilities based on the conditions identified in paragraph b. above. 8. LAWS AND REGULATIONS Contractor agrees to comply with all federal, state and local laws that apply to Contractor as a supplier to City under this Contract. All laws, regulations and design codes expressly incorporated herein shall be those in effect on the effective date of this Contract. In the event of any subsequent revisions or changes thereto, except in connection with the business activities of Contractor or its Subcontractors or agents, Contractor assumes no responsibility for compliance therewith unless an appropriate Change Order is issued. Nothing contained herein shall be construed as imposing responsibility or liability upon Contractor for the obtaining of permits, licenses or approvals from any environmental, siting or public utility authority or other agency required in connection with the supply, erection or operation of the System, except business licenses, building permits, transit waivers, and/or contractor's licenses as may be required in the name of Contractor or its Subcontractors to support its business activities. EPCContract_0_8_ 14.doc 13 9. INSPECTION Contractor shall provide City reasonable escorted access to Contractor's manufacturing facilities, after receipt of reasonable notice, for the purposes of inspecting the Work and witnessing any tests prearranged to be witnessed and required by this Contract. Neither completion of manufacturing nor shipment of any part will be delayed to accommodate such inspection or witnessing. For agreed Witness Points, Contractor will provide at least twenty-one (21) days advance notice. If Contractor does not receive written confirmation that City will attend, or if City fails to appear at the time of the test/inspection mentioned in the notification, Contractor shall proceed with the Work. Contractor shall provide City a schedule of potential Witness Points within thirty days of execution of this Contract. Within two weeks of receipt of the schedule, City will provide Contractor with an initial indication of potential Witness Points it may wish to witness. 10. FORCE MAJEURE Neither Contractor nor City shall be considered to be in default with respect to any of their obligations under this Contract when a failure of performance shall be due to an uncontrollable force. The term "uncontrollable force" shall mean any cause beyond the control of the Party affected, including, but not restricted to, flood, earthquake, storm, fire, lightning, epidemic, war, terrorist action, riot, civil disturbance or disobedience, sabotage, federal, state, or municipal action, statute, ordinance, or regulation, embargoes of the United States Government or any other government, which by exercise of due diligence such Party could not reasonably have been expected to avoid and by exercise of due diligence has been unable to overcome. Either Party rendered unable to fulfill any of its obligations under this Contract by reason of an uncontrollable force, shall give written notice within five Business Days of such fact to the other Party and shall exercise due diligence to remove such inability with all reasonable,dispatch. The City shall pay the Contractor for earned progress up to the force majeure event. 11. DELAYS/SUSPENSION In the event of any delay attributable to City, its subcontractors or agents that negatively affects the Contract Time Schedule, Contractor shall be entitled to an equitable adjustment of the Schedule dates defined in Section 3B and the consequences thereof and reimbursement of all impact costs. EPCContract_0_8_ 14.doc 14 1\�— 12. WARRANTIES A. General Contractor represents and warrants that: (a) Contractor is fully experienced and properly licensed, equipped, organized, financed and qualified to perform the Work pursuant to this Contract. (b) Contractor will design, engineer, construct, install, equip, start-up, and complete the Work in accordance with the requirements of this Contract, including the requirements, codes, standards and regulations specified in the Specification. the Work will be designed, engineered, constructed, installed, equipped, started up, and completed in accordance with sound, generally accepted and the best trade engineering and construction practices and in compliance with all applicable requirements of federal, state or local laws, codes and regulations governing the construction and operation of the Work. The Work will be uniformly new, of good quality and free from fault or defects in material, workmanship or performance, and all Work, including substitutions not so conforming to these standards may, at the option of City be considered defective and the Material and Work shall be fit for its intended purposes as exhibited by the Performance Guarantees and shall conform to the requirements of this Contract. B. Warranty Period The warranty period shall be eighteen (18) months from the date of Beneficial Use by the City or eight thousand (8,000) station Generating Hours which ever comes first. The warranty period for deficiencies under paragraph A above, shall be one (1) year from the date of correction of the deficiency or eighteen (18) months after Beneficial Use by City, whichever occurs first. Contractor procured equipment will carry a one year warranty from date of Beneficial Use by City or eighteen (18) months from date of shipment, documented by formal shipping documents, whichever comes first. C. Remedy of Defects If City or City's Representative notifies Contractor of any deficiencies under this Section discovered in the Work during the warranty period as defined herein, whether such Work has been performed, fabricated, installed, tested, completed or accepted, Contractor shall promptly replace, repair or re -perform the Work to conform to the requirements of this Contract, all at Contractor's expense, including repairs to other parts of the Work, or other property damaged as a result of such deficiencies or corrective actions, and including the costs of City's Representative or any outside consulting services thereby made necessary. Contractor shall also perform such tests as City may reasonably request to verify that such correction, replacement, repair, re -performance or rework complies with the requirements of this Contract. Contractor shall perform its warranty obligations hereunder as expeditiously as possible and shall in every case commence the necessary corrections, repairs, replacements, performance and tests within seven days of written notice to Contractor. In the event Contractor fails to commence such performance within such seven (7) day period, City may perform or cause to be performed the same, all at Contractor's expense. EPCContract_0_8_ 14.doc 15 D. Survival of Warranties All representations, covenants, and warranties in this Section shall: (a) survive any inspection and acceptance of the Work and continue for the warranty period in Section 1213; (b) be extended for one (1) day for each day that Contractor is unable to achieve Beneficial Use in accordance with the Specification due to a breach of Contractor's warranties; and (c) shall continue in respect of any defect notice of which has been given by the City to Contractor prior to the date on which the warranty period in Section 12B would have expired but for this provision for the extension thereof in respect of such defects. E. Extent of Warranties and Guarantees Contractor's warranties and guarantees under this Section do not extend to any repairs, adjustments, alterations, replacements or maintenance which may be required to the Work as a result of normal corrosion, normal erosion or normal wear -and -tear in the operation of the Work. F. Prevention Contractor agrees not to file or otherwise assert, suffer or permit a mechanic's lien to be filed or continued against any property of City for services or Work performed or Material, furnished in connection with the Work by Contractor. G. Assignment of Warranties and Guarantees On the date of the Notice of Acceptance of the Work after Commercial Operation, Contractor shall assign, by executing a document or documents, all warranties and guarantees that it procures from third parties on product incorporated into its Work, which, upon such assignment shall be valid, and Contractor shall obtain from all such third parties consents to such assignment. Contractor shall enforce all such warranties and guarantees on behalf of City during the warranty period and shall provide City with all reasonable assistance in the enforcement of such warranties and guarantees whether or not such enforcement occurs during the warranty period. 13. INFORMATION FURNISHED TO AND BY CITY Not used 14. INFORMATION FURNISHED TO CONTRACTOR A. Access to Confidential Information. City may provide Contractor with, or allow Contractor access to certain information not available to the public concerning City, or businesses located in the City or City's vendors. The information may include company information, taxes, sales, value of assets, or other such information. All such information shall be known as "Confidential Information" and shall be marked clearly as "Confidential Information". EPCContract_0_8_ 14.doc 16 B. No Disclosure. Except as expressly permitted, Contractor shall not disclose, permit the disclosure of, release, disseminate, or transfer, whether orally or by any other means, any part of such confidential information to any other person or entity, whether corporate, governmental, or individual, without the express prior written consent of an authorized representative of City. Contractor shall return any written Confidential Information and all copies made of such items to City upon City's written request, but in any event not later than the date that Contractor has performed all services to be performed pursuant to this Contract. Contractor hereby agrees that such confidential information and any documents provided may be used by Contractor only as authorized by City. Contractor shall take reasonable measures to avoid any disclosure of any such confidential information to any unauthorized person. C. Court Ordered Disclosure. Contractor shall immediately notify City of any court order or subpoena requiring disclosure of confidential information, and shall cooperate with the City's legal counsel in the appeal or challenge of any such order or subpoena. Recipient may only disclose confidential information required to be disclosed pursuant to court order or subpoena after legal counsel has exhausted any lawful and timely appeal or challenge. D. Remedies. In addition to any other remedies that it may have at law or in equity, City shall be entitled to a temporary and permanent injunction by a court of competent jurisdiction against any breach or threatened breach of the confidential information provisions of this Contract. Contractor acknowledges that in case of such breach or threatened breach of said provisions, City would have no adequate remedy at law. 15. TECHNICAL DATA All operating or other performance information and data under this Contract are based on the conditions specified in the attached Appendices. Contractor's sole liability in respect to performance of the Work shall be only as expressly stated in the attached Appendices, or as set forth herein. 16. PATENTS Contractor shall defend, indemnify and hold City and its officers, employees and agents free and harmless from any claim, litigation or other judicial or administrative proceeding the basis of which is that the Work supplied hereunder infringes on a U.S. apparatus patent issued prior to the date of this Contract other than those arising out of (a) Material supplied according to City's detailed design; (b) modifications, alterations, additions or changes made by City to the Work or to Material supplied by Contractor, (c) the use of -the Work or Material supplied hereunder in conjunction with any other process or Material not supplied by Contractor, or (d) claims covering a process performed or a product produced by said Work. City will notify Contractor in writing within a reasonable period of time of such claim. Contractor shall have control over the defense and/or settlement of such claim and reasonably required assistance in said defense. EPCContract_0_8_ 14.doc 17 If the Work is determined to infringe on a patent, or in Contractor's reasonable opinion may infringe on a patent, Contractor will, at its option and expense, either (1) procure for City the right to continue using said Work or part thereof, (ii) modify it so it becomes non -infringing Work, (iii) replace it with substantially equivalent non -infringing Work. 17. CANCELLATION/ DEFAULT A. Termination Any order or contract maybe terminated by City for its convenience upon fifteen (15) days prior written notice and upon payment of reasonable and proper termination charges, including, but not limited to, all costs incurred or committed prior to the effective date of notice of termination and all charges incurred by Contractor in connection with the termination, plus reasonable overhead and profit. B. Contractor's Breach In the event Contractor commits a breach of a material condition of this Contract, City shall notify the Contractor in writing of said breach and if Contractor has not cured or begun reasonable efforts to cure after 15 working days of receipt of said notice, and fails to diligently pursue corrective action, then City shall have the right to cancel this Contract, The City may: 1) proceed against the Contractor's Bond in accordance with the terms and conditions of the Bond or, 2) deviate from the terms and conditions of the Bond, thereby waiving its right to make claim against the Contractor's Bond; the City may then pursue whatever other remedies it may have under the law against Contractor.. Contractor shall be responsible for any direct costs due to City's re -procurement of the equivalent of the Work or services cancelled from Contractor. Among other things, Contractor shall be deemed to be in default under this Contract if Contractor files for bankruptcy or another person or entity institutes against Contractor a bankruptcy, reorganization, moratorium, liquidation or similar insolvency proceeding or other relief under any bankruptcy or insolvency law affecting creditor's rights or a petition is presented or instituted for its winding -up or liquidation. C. City's Breach If City fails to make any contractual payment to Contractor when due under the provisions of this Contract, and such failure is not remedied within fifteen (15) days of City's receipt of written notice of such default, then Contractor will notify City. if such failure is not remedied within "seven (7) days of City's receipt of the second notice then Contractor may terminate this Contract for City's default. 18. ASSIGNMENT Contractor may not directly or indirectly sell, assign, transfer, pledge, mortgage or encumber (each, a "Transfer") any of its interest in any of its rights or obligations under this Contract, without the prior written consent of City. Any Transfer that is made without the prior written consent of City shall be void. EPCContract_0_8_ 14.doc 18 19. PARTIAL INVALIDITY Wherever possible, each provision hereof will be interpreted in such manner as to be effective and valid under applicable law, but in case any one or more of the provisions contained herein will, for any reason, be held to be invalid, illegal or unenforceable in any respect, such provision will be ineffective to the extent, but only to the extent, of such invalidity, illegality or unenforceability without invalidating the remainder of such invalid provision or provisions or any other provisionhereof, unless such a construction would be unreasonable or contrary to the intent of the Parties as expressed in this Contract. 20. CHOICE OF LAW The rights and remedies of the Parties hereunder shall be governed by the laws of the State of California. 21. INSTALLATION/FIELD SERVICES Unless specifically excluded, all field services required by the Work shall be completed by the Contractor. 22. INDEMNIFICATION AND INSURANCE A. Indemnity Contractor shall indemnify, hold harmless and defend City, its officers, employees and agents from and against any claims, demands, suits, proceedings, liabilities, judgments, awards, losses, damages, costs or expenses (including reasonable attorney's) whatsoever arising out of and caused or occasioned by any negligent act or omission of Contractor, or any of its officers, directors, agents or employees, contractors or Subcontractors in connection with the per- formance of the Work under or in connection with this Contract. In the event that any losses arise, directly or indirectly, in whole or in part, out of the joint or concurrent negligence of both Parties and their respective representatives, each Party's liability therefore shall be limited to such Party's proportionate degree of fault. B. Insurance Prior to commencing Work hereunder, Contractor shall provide City with proof of insurance providing and maintaining the coverage's and endorsements set forth in the Insurance Schedule attached hereto as Appendix 4, Insurance Schedule, and made a part hereof by reference. Said proof of insurance shall also provide that said policy or policies shall not be canceled or materially reduced in coverage without giving at least 30 days prior written notice to City. Contractor shall not permit a Subcontractor or vendor to perform work on City premises unless and until proof of insurance is obtained showing that such Subcontractor or vendor has worker's compensation coverage. If Contractor employs Subcontractors as part of the services rendered, Contractor's protective coverage is required. Contractor may include all Subcontractors as insureds under its own EPCContract_0_8_ 14.doc 19 policy or shall furnish separate insurance for each Subcontractor, meeting the requirements set forth herein. 23. NON -WAIVER The failure of either Party to insist upon or enforce, in any instance, strict performance by the other Party of any provision of this Contract or to exercise any right herein conferred shall not be construed as a waiver or relinquishment to any extent of its right to assert or rely upon any such provision or rights on any future occasion. 24. AMENDMENTS This Contract may be modified or amended only by a written document executed by both Contractor and City. 25. ENTIRE AGREEMENT This Contract is the entire agreement of the Parties. Contractor represents that in entering into this Contract, it has not relied on any previous representations or understandings of any kind or nature. 26. BENEFIT OF AGREEMENT This Contract shall bind and benefit the Parties hereto and their heirs, successors, and permitted assigns. 27. FORUM SELECTION Any action brought -relating to this Contract shall be brought and held exclusively in a State Court in the County of Los Angeles, California. 28. COUNTERPARTS This Contract may be executed simultaneously in two or more counterparts, each of which shall be deemed to be an original, but all of which together shall constitute one and the same instrument. EPCContract_0_8_ 14.doc 20 29. NOTICES Notices to the Parties, unless otherwise requested in writing, shall be sent to: City: THE CITY OF VERNON ATTN: BRUCE V. MALKENHORST CITY ADMINISTRATOR 4305 SANTA FE AVENUE VERNON, CA 90058-0805 CONTRACTOR: SCOTTCOMPANY ATTN: STEVE KLAUS 14920 SOUTH PEDRO GARDENA CA, 90248-2036 Notices shall be deemed to have been received by the close of Business Day two days after the date on which it was mailed. 30. INDEPENDENT CONTRACTOR. At all times during the tern of this Contract, Contractor shall be an independent contractor and shall not be an employee of City. City shall have the right to control Contractor only insofar as the results of Contractor's services rendered pursuant to this Contract; however, City shall not have the right to control the means by which Contractor accomplishes services rendered pursuant to the Contract except to the extent that such services involve the use of City property or Confidential Information. 31. CONTRACTOR NOT AGENT Except as City may specify in writing, Contractor shall have no authority, express or implied, to act on behalf of City in any capacity whatsoever as an agent. _ Contractor shall have no authority, expressed or implied, pursuant to this Contract to bind City to any obligation whatsoever. EPCContract_0_8_14.doc 21 32. REVIEW OF EXISTING CONDITIONS A. Premises Contractor represents that (i) it has relied upon its own examination of the area on which the Work is to be performed, the adjacent premises and the site, (ii) it knows the applicable federal, state and local laws, ordinances and regulations in existence as of the effective date of this Contract, and (iii) it assumes responsibility therefore. Contractor knows, or shall be deemed to have known, the facilities or lack thereof for delivering, handling and storing materials, equipment on and near the site and the applicable labor conditions. Contractor represents and warrants that all such matters are acceptable and will not interfere with the timely performance of its Work under this Contract. B. Verification of Existing Conditions Contractor represents that (i) it has reviewed the site survey and site proposal drawings and other data concerning the Work included in the Specification, (ii) Contractor has determined and verified all materials, field measurements and field construction criteria related thereto, and it has checked and coordinated the information contained within such submittals with the requirements of the Work and this Contract. To the extent that such drawings and data are made available to Contractor and Contractor is provided an opportunity to determine and verify such information, Contractor shall be responsible for all defects and discrepancies in such drawings and data as if Contractor itself had prepared such drawings and data. The Contractor may rely on information supplied by the City to the extent that it cannot be verified by reasonable survey and inspection. C. Statements of Fact Contractor statements of fact contained in Contractor's submissions in response to, and reply to inquiries made in connection with the Specification are true, correct and complete. No submission or reply made by or on behalf of Contractor in connection therewith contains any material misstatement of fact or omits to state any material fact necessary to make the statements made in connection therewith, in light of the circumstances in which they were made. 33. SUPERVISION BY CONTRACTOR A. Management of Work Contractor shall assign each key officer and employee named on its Management Plan (the "Plan") per the Specification to be responsible for the Material, and construction tasks for which the Plan indicates that such key officer and employee will be responsible. No key officer or employer will be permitted to delegate or transfer its responsibility for any task for which the Plan indicates he or she is responsible without cause or the prior consent of City. The Plan shall be submitted to City thirty (30) days following the Contract award. The Plan will consist of a detailed construction execution write-up of all major schedule activities, rigging requirements, working hours and days, means and methods of erection and EPCContract_0_8_ 14.doc 22 installation, and a discussion of how the critical path items will be achieved and maintained. The Plan will include a detailed Primavera CPM schedule which will be manpower loaded by craft and also cost loaded with Contractor's budget to produce craft and total job manpower curves, overall project progress curve, and a total project cash flow curve. The Plan must include sample reports showing an itemized schedule of commodity units, estimated hours of installation, a column for actual manhours for monthly reports, estimated and actual cost of installation by each unit category, earned value percent complete column for the period and cumulative column, plus bottom line percent complete for the total job. The percent complete will be based on quantities installed in place, which will be included in the monthly Payment Application. The Plan must show how the bulk materials and process equipment will be tracked from shop to site with expected and actual delivery dates by purchase order number and quantities. All data will become the baseline plan to which weekly progress will be measured against the Plan. A daily inspection form will be completed by Contractor and submitted daily to City's Representative. B. Control of the Work The methods, sequences, procedures and techniques by which Contractor shall administer and execute the Work shall be consistent with the Plan and the construction execution plan, delivered by Contractor pursuant to the Specification. Contractor shall remain solely responsible for all construction means, methods, techniques, sequences, procedures and safety programs in connection with the performance of the Work. 34. GOVERNMENTAL REGULATIONS AND TAXES A. Permits and Licenses Contractor shall have responsibility for and shall bear the cost of obtaining all necessary permits and licenses from all authorities required for Contractor's performance of the Work. Contractor shall assist City as necessary in obtaining environmental permits such as the Permit to Construct, California Environmental Quality Act, South Coast Air Quality, etc.. Throughout the performance of the Work, Contractor shall comply with Laws and Regulations. Compliance by Contractor with Laws and Regulations applicable to the Work that become effective or are changed after the effective date of this Contract, shall be handled in accordance with the procedures established in Appendix 4, Changes and Extra Work. B. Laws and Regulations Contractor shall conform with Laws and Regulations. EPCContract_0_8_ 14.doc 23 ^� 35. LIQUIDATED DAMAGES A. Delays If Contractor fails to complete erection or fails meet the performance deadline by the dates agreed upon in Section 313, , the Parties agree that City shall be damaged. The actual damages that would be suffered by City would be impossible to ascertain precisely. Therefore, the Parties agree that Contractor shall pay City liquidated damages (but not as a penalty) pursuant to the following schedule: Beneficial Use: Fifteen Thousand Dollars and 00/100 ($15,000) for every day with a Five Hundred Thousand and 00/100 ($500,000.00) maximum following the Beneficial Use milestone. B. HP Steam Pressure Loss The Contractor agrees to a liquidated damage of $1,250/psid for every psid over the guarantee point of 40 psid as measured between the HRSG/bidder interface and the steam turbine/bidder piping interface. Note the above is based on a calculation that indicates for every 1 psig loss in HP steam pressure to the turbine there is 3KW drop in steam turbine output. The $1,250/psid was determined based on lost revenue of 3 kw valued at $.05/kwhr for one year at 95% availability. C. Liquidated Damage Payment Liquidated damages owed by Contractor to City will be deducted from Contractor's monthly Payment Application, as such damages are accrued. D. Sole Remedy It is understood and agreed that payment of the damages specified in this Section shall be the sole and exclusive remedy of the City against the Contractor for the failure of Contractor to meet timely the dates of delivery of Mechanical Completion, and Commercial Operation. 36. MAXIMUM AGGREGATE LIQUIDATED DAMAGES The maximum aggregate liquidated damages payable under this Contract shall not exceed $500,000 maximum. 37. PERFORMANCE GUARANTEES A. Performance Guarantees Contractor warrants and guarantees that the Work supplied and installed pursuant to this Contract shall conform to the requirements and specifications set forth in the Specification, including without limitation, the noise emission and auxiliary power guarantees specified in the Specification. EPCContract_0_8_ 14.doc 24 B. Noise Emissions Limits The Contractor's guarantees covers equipment procured by the Contractor, only. Contractor's guarantees concerning noise are specifically stated in Appendix 1. In the event that the Contractor's equipment is proven to have failed the noise guarantees as stated, Contractor shall be granted access to the Contractor's equipment at time or times acceptable to City to repair or replace the defective component that has been duly demonstrated to be deficient. C. HP Steam Line Pressure Loss Contractor shall guarantee that the pressure loss through the HP steam piping, valves, etc. shall be less than the pressure loss allowed in the Specification when the Combined Cycle Power Plant is operating at the Guarantee Conditions as defined by the Specification. D. Obligations of the Contractor If the Work, as demonstrated by the Performance Tests, fails to achieve the Performance Guarantees, Contractor shall have the obligations set forth below. Contractor shall not claim as a defense or excuse for the failure of the Work to achieve the Performance Guarantees that the achievement of such Performance Guarantees was technologically impossible or impracticable. E. Corrective Action Contractor shall, within ten (10) days after the date of a notice of unsuccessful Performance Test, submit to City a plan of corrective action (Corrective Action Plan), specifying in reasonable detail the actions Contractor proposes to take to cause the Work to achieve the Performance Guarantees, and the period of time in which it proposes to complete the corrective action; the Parties must mutually agree upon the period of time for such corrective action. Contractor will not be liable for deficiencies caused by the City or it's other Subcontractors or suppliers. Contractor will not be liable for any deviation from any Corrective Action Plan where the deviation is caused by acts, omissions or requirements of the City or its other Subcontractors or suppliers. F. Standards for Plan of Corrective Action When implementing the Corrective Action Plan, Contractor shall (i) timely and diligently exercise its best efforts to repair and modify the Work to meet the Performance Guarantees, including but not limited to redesign, re -engineering, research, testing and associated construction work, (ii) consider and apply available know -.how and technology, including consultation with City and experts in the field, and (iii) consult with City with respect to City's concerns and preferences under the circumstances. 38. LIMITATION OF LIABILITY A. Contractor's aggregate liability for all claims of any kind, whether based on contract, warranty, tort, strict liability or otherwise, for all losses or damages arising out of, connected with or resulting from this Contract, its performance or breach shall not exceed the Contract Price. EPCContract_0_8_ 14.doc 25 B. In no event, whether as a result of breach of contract, warranty, indemnity, tort, or otherwise, shall Contractor be liable for indirect, special, incidental, or consequential damages including but not limited to loss of profits or revenue loss of data; loss of use of equipment; cost of capital; cost of substitute equipment, services or facilities; downtime costs or claims of third parties or customers for service interruptions. 39. DISPUTE RESOLUTION In the event that any dispute arises under this Contract, the Parties will in good faith attempt to informally resolve such dispute. Such attempts shall include at least one fact -to -fact meeting with the representatives of City and Contractor. 40. ENVIRONMENTAL PROTECTION A. Qualified Personnel Contractor agrees to use, and agrees that it shall require each of its Subcontractors, if any, to use only personnel who are qualified and properly trained and who possess every license, permit, registration, certificate or other approval required by any applicable Environmental Law or Government Agency for the performance of Contractor's obligations under this Contract. B. Material Contractor agrees that all Material to be supplied or used by Contractor, its Subcontractors, if any, in the performance of this Contract, including, but not limited to, vehicles, loading equipment, and containers, shall be in good condition and fit for the use(s) for which they are employed by Contractor or its Subcontractor. Such Material shall at all times be maintained, inspected and operated as required by applicable Environmental Law. Contractor further. agrees that all licenses, permits, registrations and certificates or other approvals required by any Environmental Law or Government Agency will be procured and maintained for such Material at all times during the use of the same by Contractor or its Subcontractors in the performance of any of its obligations under this Contract. C. Compliance with Laws Contractor agrees that in the performance of its obligations under this Contract, Contractor shall at all times fully comply with, and shall require all Subcontractors to comply with, all applicable Environmental Laws. Contractor further agrees that at all times during its performance under this Contract it, and any Subcontractors, shall have and keep in effect all licenses, pernlits, registrations, certificates, and approvals required by any Environmental Law or by any Governmental Agency for the performance of its obligations under this Contract. EPCContract_0_8_ 14.doc 26 D. Hazardous Materials Removal In the event Contractor or its Subcontractors are required to remove any Hazardous Material from the work area during the performance of the Work contemplated by this Contract, Contractor shall notify City of such fact promptly after discovering such requirement. Contractor shall appropriately remove such Hazardous Materials and deliver the same to City for proper handling and management. However, in the event any such Hazardous Materials are asbestos or asbestos containing materials, City will remove the same promptly after receiving Contractor's notice, as necessary for Contractor's performance of the Work, in compliance with applicable Environmental Law. E. Environmental Indemnity , Contractor hereby specifically agrees to indemnify, defend and hold harmless the City, its officials, officers, employees, agents, successors and assigns, herein collectively called the "Indemnitees," harmless from and against any and all losses, liabilities, claims demands, damages, causes of action, judgments, fines, penalties, costs and expenses (including but not limited to all reasonable consulting, engineering, attorneys' or other professional fees) which indemnitees, or any of them, may incur or suffer by reason of (a) any unauthorized release of a Hazardous Material by Contractor; (b) any enforcement or compliance proceeding commenced by or in the name of any Government Agency because of an alleged, threatened or actual violation of any Environmental Law by Contractor; (c) Contractor shall have no obligation to abate or remove any hazardous material and will have no liability for damages caused by any hazardous material unless the hazardous material is placed on the site by Contractor or released as a result of negligence by Contractor. Each Party will provide environmental indemnity to the other. F. Material Safety Data Sheets Contractor shall submit the current Material Safety Data Sheet, (MSDS) to City's Representative upon request, for each Hazardous Material used by Contractor, or any Subcontractor on City premises during the performance of the Work. G. Suspension and Notification Contractor shall immediately suspend all operations and immediately notify City's Representative if any violation or alleged violation of Environmental Law is encountered during performance of the Work. EPCContract_0_8_ 14.doc 27 41. LABOR AND MATERIAL A. General Contractor shall provide and pay for all labor, supervision, inspection and testing as may be necessary to complete performance of the Work, whether by the Contractor or its Subcontractors, except for inspection and testing included within the Work as defined in Appendix 1, Specification. To the extent permitted by law, any Work to be performed by Contractor hereunder which City would normally undertake with its regular work force and work that would otherwise fall within the terms and conditions contained in an existing agreement shall be performed by employees and Subcontractors who are members of a trade union, bona fide labor organization affiliated with the Building Trades of the AFL-CIO, or by employees and Subcontractors working under a Work specific union agreement. B. Employment of Licensed Personnel Whenever required by law, regulation or code, Contractor agrees to employ only licensed personnel to perform engineering, design, architectural or other professional service in the performance of the Work. All such professional services shall be performed with the degree of care, skill and responsibility customary among such licensed personnel. Contractor shall immediately remove from the site any employee or agent of Contractor or any Subcontractor as to whom City objects in writing. C. Assignment of Individuals Individuals assigned to this Work at a level of responsibility of technical discipline review and above cannot be assigned or reassigned or removed from this Work without approval of City. D. Material Contractor shall, provide and pay for all Material and other services as may be necessary to complete the performance of the Work, whether by Contractor or its Subcontractors, except for material and services included within City's scope of work as defined in Appendix 1. E. Start Up Spare Parts and Special Tools Contractor shall deliver and store where directed by City, prior to Mechanical Completion, the special tools and spare parts required, including without limitation those special tools and spare parts listed in the Specification. EPCContract_0_8_ 14.doc 28 F. Quality Control Program Contractor shall establish, implement and maintain a quality assurance and control program in accordance with the provisions of the Specification. The program shall be designed to meet the following objectives: (a) purchased items and documentation to meet specified requirements of this Contract; (b) the quality of items to be part of permanent installation not be degraded during receiving, storing, transporting„ handling, erection, installation, inspection and testing; (c) systems, equipment and structures are provided and installed in strict compliance with the manufacturers' instructions and this Contract; and (d) components meet performance and functional requirements of this Contract. G. Testing Contractor shall provide all specially trained or supervisory personnel for the Work. Contractor shall perform or cause to be performed all factory, laboratory and other tests together with all testing procedures described in the Specification and submit to City Monthly Reports (as defined in Appendix 3) of the results thereof, indicating whether such results warrant acceptance or rejection of any materials so tested or performance of such tests. H. City's Right to Inspect City shall have the right at all reasonable times to inspect the Work and to observe the tests relating to the Work that are conducted by Contractor. Contractor shall make arrangements and provide facilities and access for such inspection and observation of such tests at the Jobsite or at the facilities of any Subcontractor where any part of the Work is being fabricated or manufactured. Contractor shall give ample notice as to the time and place when each part of the Work will be ready for such inspection. City may reject any part of the Work found to be defective or not in accordance with this Contract, regardless of the stage of its completion or the time or place of discovery of such errors, and regardless of whether City has previously accepted it through oversight or otherwise. Such inspection by City shall in no way relieve Contractor from its obligations under this Contract. EPCContract_0_8_ 14.doc 29 IN WITNESS WHEREOF, the Parties have caused this Contract to be executed by and through their authorized officers on the date, month and year first written above. ATTEST: BRUCE V. MALKENHORST, City Clerk APPROVED AS TO FORM: EDUARDO OLIVO, City Attorney CITY OF VERNON By: LEONIS C. MALBURG, Mayor CONTRACTOR Date: , ` 2� - 0 2 Af N me —Title Title T , j�9D 4-1 %� Date: U -Z (1.� Name%VLi9L1s Title EPCContract_0_8_14.doc 30� APPENDIX 1 SPECIFICATION FOR DETAILED ENGINEERING, PROCUREMENT, CONSTRUCTION, and STARTUP FOR THE MALBURG GENERATING STATION PROJECT VERNON, CALIFORNIA Prepared by. Carter:: Burgess 216 16t' Street Suite 1700 Denver, Colorado 80202 C&B No, 070734 Specification No.: D-99 REV 0 JULY 25, 2002 SPECIFICATION PART 1 TECHNICAL SPECIFICATION PART 2 ERECTION SPECIFICATION PART 3 TECHNICAL ATTACHMENTS ELECTRONIC INDEX DISK 1 Contract, Part 1, Part 2, and EPC Data List DISK 2 C-B and Vendor Drawings DISK 3 Application for Certification, (AFC) and SCAQMD Permit Application PART 1 TECHNICAL SPECIFICATION FOR DETAILED ENGINEERING, PROCUREMENT, CONSTRUCTION, and STARTUP FOR THE MALBURG GENERATING STATION PROJECT VERNON, CALIFORNIA Prepared by., CarterBurgess 216 16`" Street Suite 1700 Denver, Colorado 80202 C&B No. 070734 Specification No.: D-99 REV 0 JULY 25, 2002 D_99Prt1_0.doc 1 TECHNICAL SPECIFICATION Table of Contents 1.0 SCOPE OF SUPPLY 1.1 General 1.2 Project Description 2.0 DEFINITIONS 3.0 SUPPLEMENTS 3.1 Discipline Design Basis Document 3.2 Engineering Standards 3.3 Owner Furnished Drawings and Data 3.4 Carter & Burgess Supplied Drawings 3.5 Owner Furnished Equipment Information 3.6 Owner Furnished Equipment and Delivery Information 4.0 EQUIPMENT AND SERVICES TO BE PROVIDED BY THE CONTRACTOR 4.1 Equipment to be provided by the Contractor 4.1.1 Detailed Contractor Furnished Equipment 4.2 Engineering Services to be provided by the Contractor 4.3 Construction Services to be provided by the Contractor 5.0 EQUIPMENT AND SERVICES TO BE PROVIDED BY OTHERS 6.0 DESIGN CONDITIONS 7.0 TERMINAL POINTS 8.0 DESIGN AND CONSTRUCTION 8.1 General 8.2 Codes, Standards and Regulations 9.0 COMPONENT AND SYSTEM DETAILS 9.1 Combustion Turbine 9.2 Heat Recovery Steam Generator 9.3 Steam Turbine 9.4 Main Steam System 9.5 Condensate System 9.6 Condensate Storage & Transfer 9.7 Circulating Water System 9.8 Fuel Gas System 9.9 Plant Raw Water 9.10 Potable Water 9.11 Plant Drain System Wastewater System Oil/Water Waste Sanitary Waste Chemical Feed Drainage 9.12 Water Treatment HRSG Chemical Treatment Cooling Tower Chemical Treatment 9.13 Fire Protection Underground Piping Fire Hydrants Fire Hose Station Wet Pipe and Waterspray Systems Wet Pipe Sprinklers Detection System Fire Protection Supervisory Panel Portable Fire Extinguishers 9.14 Instrument and Service Air 9.15 Not Used 9.16 HVAC D_99Prt1_O.doc i Page 1 1 2 2 2 2 3 4 5 5 5 6 7 11 11 12 13 13 14 14 15 17 17 18 20 20 21 21 22 23 24 25 26 26 26 27 27 27 27 28 28 29 30 30 30 30 30 30 31 31 32 32 9.17 Plumbing 9.18 Insulation & Lagging 9.19 Continuous Emissions Monitoring 10.0 ENGINEERING SERVICES 10.1 System Design Criteria 10.2 Equipment List 10.3 Piping Line List 10.4 System Descriptions 10.5 Operations and Maintenance Manuals 10.6 Operator Training 11.0 CIVIL STRUCTURAL 11.1 General 11.2 Earthwork 11.3 Structural 11.4 Inspection 11.5 Architectural Work 12.0 ELECTRICAL 12.1 General 12.2 Switchgear 12.3 NEMA Frame Motors 12.4 Medium Voltage Motors 12.5 Station Service Transformers 12.6 129 Vdc Station Battery 12.7 120 Vac UPS System 12.8 Switchgear Building 12.9 Electrical Equipment for Packaged Mechanical Equipment 12.10 69 KV Line Terminations 12.11 Plant Lighting 12.12 Electrical Commodities 13.0 INSTRUMENTATION & CONTROLS 13.1 DCS 13.2 Packaged Equipment and Field Instrumentation 14.0 PIPING 15.0 PERFORMANCE 16.0 PERFORMANCE TESTING 16.1 Auxiliary Power 16.2 Noise Emissions Tests 16.3 High Pressure Steam and Low Pressure Steam Pressure Drop 17.0 MATERIALS AND WORKMANSHIP 18.0 NOISE EMISSIONS 19.0 SHOP ASSEMBLY 20.0 CLEANING, FINISHING AND PAINTING 20.1 Prime Painting 20.2 Finish Painting 21.0 SPECIAL TOOLS AND DEVICES 22.0 SPARE PARTS 23.0 TECHNICAL DIRECTION OF INSTALLATION 24.0 DOCUMENTATION 25.0 QUALITY ASSURANCE 26.0 GUARANTEES 26.1 Equipment 26.2 Auxiliary Power 26.3 Noise 26.4 HP and LP Steam Pressure Loss 27.0 BID DATA 32 33 33 33 33 33 33 34 34 34 34 34 35 35 35 37 38 38 39 39 39 39 39 40 40 40 40 41 42 45 45 45 45 47 50 50 50 50 50 50 51 51 52 52 52 52 52 52 53 54 54 54 54 54 54 D_99Prt1_0.doc APPENDIX 1 PART 2 ERECTION AND STARTUP FOR THE MALBURG GENERATING STATION PROJECT VERNON, CALIFORNIA Prepared by: Carter:: Burgess 216 16'hStreet Suite 1700 Denver, Colorado 80202 C&S No. 070734 Specification No.: D-99Erect July 26, 2002 Rev 0 EPCD_99Part2_O.doc 0 PART 2 ERECTION SPECIFICATION Page 1.0 SCOPE 4 2.0 MECHANICAL EQUIPMENT REQUIREMENTS 6 2.1 General 6 2.2 Process Equipment Erection Requirements 6 2.3 Insulation Installation 6 2.4 Piping Systems 7 3.0 STRUCTURAL STEEL 8 4.0 GROUTING 9 5.0 FOUNDATIONS AND EARTHWORK 9 6.0 LUBRICATION 9 7.0 ELECTRICAL WORK REQUIREMENTS 9 7.1 General 9 7.2 Handling Transportation, and Storage of Equipment 10 7.3 Temporary and Construction Power 10 7.4 Equipment Installation 11 7.4.1 Cable Requirements and Installation 11 7.4.2 Cable Tray and Raceway 11 7.4.3 Locally Mounted Equipment 12 7.4.4 Miscellaneous 12 8.0 INSTRUMENTATION AND CONTROL ERECTION REQUIREMENTS 13 9.0 FIELD WELDING 13 9.1 General 13 9.2 Filler Metals 14 9.3 Filler Metal Control 14 10.0 QUALITY ASSURANCE DURING CONSTRUCTION 14 10.1 General 14 10.2 Welding Qualifications and Procedures 16 11.0 FIELD TESTS 16 11.1 Weld Acceptance Criteria 16 11.2 Weld Examination 16 11.3 Nondestruction Tests 16 11.4 Inspection of Ductwork 16 12.0 START-UP, TESTING & CHECKOUT 17 12.1 General 17 12.2 Electrical Test 18 12.3 Instruments and Control Calibration 18 12.4 Ready for commissioning 20 13.0 COOPERATION WITH OTHERS 21 14.0 PREMOBILIZATION 22 15.0 CONSTRUCTION SCHEDULE AND OBLIGATIONS 22 16.0 CONSTRUCTION EXECUTION PLAN 23 17.0 CONSTRUCTION DATA TO BE CHECKED 23 18.0 CHANGES IN WORK 23 19.0 CLAIMS FOR EXTRAS 24 20.0 OVERTIME OR SHIFT WORK 24 21.0 TEMPORARY BUILDINGS 24 22.0 JOB HEALTH AND SAFETY 24 TABLE OF CONTENTS (continued) 23.0 SECURITY REQUIREMENTS 23.1 Parking 23.2 Personnel Access 23.3 Personnel Identification 23.4 Tool Registration - Contractor Employee's Personal Tools 23.5 Tool/Material Pass — Contractor Employees 23.6 Contractor's Tools & Equipment - Control, Regulation, Security 23.7 Operating Plant Tools and Facility 24.0 DRUG & ALCOHOL ABUSE POLICY 25.0 CORRECTON OF WORK 26.0 RECORD DRAWINGS 27.0 SITE REGULATIONS & FACILITIES 28.0 FIRE PROTECTION 29.0 FLAMMABLE STORAGE 30.0 BUILDING PERMITS & CONSTRUCTIN LICENSES 31.0 SHIPPING INSTRUCTIONS & DELIVERY OF MATERIAL AND EQUIPMENT 32.0 HAZARD COMMUNICATION 33.0 LIENS 33.1 Prevention 33.2 Satisfaction 33.3 Releases 34.0 SITE MATERIAL PRACTICES 35.0 PROJECT CLOSEOUT 26 26 26 26 27 27 27 27 27 28 28 29 31 31 31 32 32 33 33 33 34 34 34 APPENDIX 1 PART 3 TECHNICAL ATTACHMENTS DETAILED ENGINEERING, PROCUREMENT, CONSTRUCTION, and STARTUP FOR THE MALBURG GENERATING STATION PROJECT VERNON, CALIFORNIA Prepared by: 216 161h Street Suite 1700 Denver, Colorado 80202 C&S No. 070734 Specification No.: D-99 REV 0 July 24, 2002 Table of Contents 1 List of Vendor and City Furnished Data and Drawings 2 Engineering, Specifications, and Data Sheets LIST OF VENDOR AND CITY FURNISHED DATA AND DRAWINGS (EPC DATA LIST) ENGINEERINGf SPECIFICATIONSf AND DATA SHEETS Number Description Earthwork and Concrete A-1 Site Preparation and Earthwork A-2 Concrete Construction A-3 Sampling Testing & Construction Control of Concrete, Earthwork, and Structural Steel A-4 Equipment Grouting Structural B-1 Prefabricated Buildings B-2 Supply of Structural and Miscellaneous Steel B-3 Erection of Structural and Miscellaneous Steel Piping C-1 Piping Specifications C-2 Piping Insulation Mechanical D-1 Installation of Mechanical Equipment D-2 Specification for Startup Activities D-3 Specification for Service and Instrument Air D-4.1 Specification for Vertical Condensate Pumps D-4.2 Specification for Vertical Circulating Water Pumps D-4.3 Specification for Vertical Fire Pump Equipment D-4.4 Data Sheet for Miscellaneous Pumps D-S Specification for Field Fabricated Tanks D-6 Not Used D-7 Specification for Water Treatment Equipment D-8 Data Sheet for Fuel Gas Heater D-9 Auxiliary Cooling Water Heat Exchanger D10 Oil Water Separator Information D-11 Parshall Flume Electrical E-1 Specification for 129 Volt Battery and Charger E-2 Specification for 6900 Volt Metal Clad Switch Gear and 480 Volt Motor Control Centers E-3.1 Specification for NEMA Frame Motors E-3.2 Specification for Medium Voltage Motors E-4 Specification for Station Service Transformers E-S Specification for Electrical Requirements for Packaged Mechanical Equipment E-6 Specification for UPS Instrumentation and Controls E-20.1 Specification for Central Plant Distributed Control System E-20.2 Specification for Instrumentation for Packaged Equipment Miscellaneous F-1 Field Painting I-1 Specification for Vendor Documentation NA Discipline Design Basis CITY COUNCIL LEONI9+C. MALBURG Mayor THOMAS A. YBARRA Mayor Pro-Tem WM. "BILL" DAVIS Councilman H. "LARRY" GONZALES Councilman W. MICHAEL MCCORMICK Councilman BRUCE V. MALKENHORST City Administrator/City Clerk FAX (323) 826-1438 CITY HALL 4305 SANTA FE AVENUE, VERNON, CALIFORNIA 90058 TELEPHONE (323) 583-8811 August 6, 2002 Scott Co. Industrial Contractors Attn: Steve Klaus, Project Manager 14920 S. San Pedro St. Gardena, CA 90248 Re: Letter Agreement Dear Mr. Klaus: EDUARDO OLIVO City Attorney FAX: (562) 869-1883 KEVIN WILSON Director of Community Services & Water FAX: (323) 826-1435 KENNETH J. DeDARIO Director of Municipal Utilities FAX: (323) 826-1425 STEVEN E. PARKER Fire Chief FAX: (323) 826-1407 BRUCE W. OLSON Police Chief FAX: (323) 826-1481 Transmitted herewith is a duplicate original copy of the above referenced approved by the Vernon City Council on July 24, 2002.. If you have any questions regarding this matter, please call Mr. Kenneth DeDario at (323) 583-8811 ext. 211. ery truly yours, Nel e54 Gi n Assistant to the Chief Deputy City Clerk NG/gm CC: Kenneth DeDario Dolores Fonseca Resolution No. 8032 Agreement No. 02-047 CITY COUNCIL 4 LEONIS C. MALBURG Mayor THOMAS A. YBARRA Mayor Pro-Tem WM. 'BILL" DAVIS Councilman H. "LARRY" GONZALES Councilman W. MICHAEL MCCORMICK Councilman BRUCE V. MALKENHORST City Administrator/City Clerk FAX (323) 826-1438 Finance Committee City of Vernon Honorable Members: CITY HALL 4305 SANTA FE AVENUE, VERNON, CALIFORNIA 90058 TELEPHONE (323) 583-8811 July 18, 2002 EDUARDO OLIVO City Attorney FAX: (562) 869-1883 KEVIN WILSON Director of Community Services & Water FAX: (323) 826-1435 KENNETH J. DeDARIO Director of Municipal Utilities FAX: (323) 826-1425 STEVEN E. PARKER Fire Chief FAX: (323) 826-1407 BRUCE W. OLSON Police Chief FAX: (323) 826-1481 The Malburg Generation Station Project is undergoing a six-month expedited permit process with California Energy Commission (CEC) and they are requesting that the City provides engineering design and drawings to support the expedited permitting process. This has been reviewed by the Director of Utilities and the City Attorney and it is hereby recommended that an Interim Letter Agreement with The Scott Company be approved and executed to provide the necessary engineering design and drawings at a cost not to exceed $150,000.00. Very truly yours, Bruce V. Malkenhorst Director of Finance BVM/gm Ju y 18, 2002 TO: Bruce V. Malkenhorst, City Administrator FROM: Kenneth J. DeDario, Director of Utilities SUBJECT: Malburg Generating Station Project Letter Agreement I recommend approval of the attached Letter Agreement between the City of Vernon and The Scott Company (Scott) to provide for needed engineering design and drawings to support the California Energy Commission (CEC) permitting process. Since Vernon is in the six-month expedited permit process the CEC is requiring this additional information. This Letter Agreement will authorize Scott to complete the required drawings at a cost not to exceed $150,000. This cost will be offset against the Detailed Engineering, Procurement, Construction, and Startup (EPC) contract between the City and Scott, if one is approved by the City Council. This Letter Agreement has been reviewed by the City Attorney. If you have any questions or comments, please contact me. Thank you for your consideration. KJD:dm Attachment DD R-, Z� p W. LETTER AGREEMENT Scott Company 14920 S. San Pedro St. Gardena, CA 90248 Attention: Mr. Steve Klaus Re: Malburg Generating Station Project: City of Vernon The City of Vernon (the "City") has received a proposal dated April 29, 2002, from Scott Company ("Scott") for the engineering, procurement and construction ("EPC") of the Malburg Generating Station ("MGS") Project. The parties have not yet negotiated a contract for the EPC. However, in order for the City to comply with the informational needs of the California Energy Commission ("CEC") as required by the six-month expedited license process and complete the required attachments for the EPC contract, the City needs Scott to develop and complete engineering design and drawings. This Letter Agreement shall be subject to the following terms and conditions: 1. The parties intend to proceed with the negotiation of an EPC contract with a fixed and a firm price that shall not exceed US$43,900,000 (forty-three million nine hundred thousand dollars). 2. Payment terms shall be mutually agreed upon. 3. The scope of services shall be as provided in Scott's EPC proposal dated April 29, 2002. Scott Company Letter Agreement Page 2 4. The effective date for this Letter Agreement shall be July 24, 2002. Based upon this Letter Agreement, Scott shall proceed to complete the engineering design and drawings to support the CEC permitting process and complete the required attachments for the EPC contract. 5. The City shall pay Scott an amount not to exceed one hundred fifty thousand dollars ($150,000), which sum shall be billed by Scott on a time and materials basis. 6. The parties intend to enter into negotiations as soon as practical and to complete such negotiations no later than August 24, 2002. 7. This Letter Agreement shall be governed by the laws of the State of California. 8. In no event shall Scott be liable to the City of Vernon for any special, incidental or consequential damages of any kind or nature. 9. The City of Vernon shall not be obligated or bound by any contract until and unless the negotiations result in a contract acceptable to both parties and the contract is approved by the Vernon City. Council or executed by the Vernon City Administrator and the Vernon City Attorney. 10. The City of Vernon may terminate this Letter Agreement at any time, without cause. 11. If the parties agree upon a contract that is approved by the City as set forth in paragraph 9 above, the Contract will replace this Letter Agreement. 12. If the parties are able to agree upon a contract, all sums paid under this Letter Agreement shall be treated as a credit to the City which shall be applied to the first payment to be paid by the City under the contract. Scott Company Page 3 Letter Agreement Please confirm your acceptance of this Letter Agreement by return. Sincerely, .CITY OF VERNON Bruce V. Malkenhorst Title: City Administrator Date: ACCEPTED BY SCOTT COMPANY Name Title Date CITY ADMINISTRATOR/CITY CLERK'S INTER -OFFICE MEMORANDUM DATE: July 30, 2002 TO: Cindy Calzada, Secretary FROM: Nelly Giron Assistant to the Chief Deputy City Clerk RE Resolution Nos. 8024, 8025, and 8032 Per your request, transmitted herewith are copies of the above referenced, approved on July 24, 2002. :gm CITY ADMINISTRATOR/CITY CLERK'S INTER -OFFICE MEMORANDUM DATE: September 17, 2002 TO: Karina Rueda, Personnel Clerk FROM: Nelly Giron Assistant to the Chief Deputy City Clerk RE: Scott Company Agreement and Insurance Schedule Per your request, transmitted herewith is a copy of the Scott Company Agreement, approved on September 4, 2002 and the Insurance Schedule. :gm CC: Agreement 02-065 Resolution 8051 a 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 8032 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF VERNON APPROVING AND AUTHORIZING THE EXECUTION OF AN INTERIM LETTER AGREEMENT BY AND BETWEEN THE CITY OF VERNON AND SCOTT CO. INDUSTRIAL CONTRACTORS, A SUBSIDIARY OF THE SCOTT COMPANIES, INC. WHEREAS, the City of Vernon ("City") is proceeding at this time to develop a 134 MW Combined Cycle Power Plant officially named the Malburg Generating Station (the "Malburg Project") for the purpose of installing additional generating capacity that will yield an efficient, cost-effective, and reliable source of electric generation to the City of Vernon; and WHEREAS, City staff has determined that it needs the services of a consultant to provide consulting services respecting a detailed engineering, procurement and construction ("EPC") contract for the Malburg Project; and WHEREAS, in order for the City to provide the California Energy Commission ("CEC") with information that it requires under its six-month expedited license process and complete the design requirements for the EPC contract, the City staff needs to proceed with the development and completion of the engineering design and drawings for the Malburg Project; and WHEREAS, Scott Co. Industrial Contractors, a subsidiary of The Scott Companies, Inc. ("Scott"), a firm specializing in Industrial Construction Services, is willing to provide such services to the City while the EPC is still being negotiated; and WHEREAS, City staff has determined that Scott possesses the technical knowledge and expertise to provide the necessary 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 engineering design and drawings to support the CEC permitting process and complete the required attachments for the EPC contract for the Malburg Project; and WHEREAS, during the negotiations for the EPC contract, the City and Scott desire to enter into an interim letter agreement setting forth the terms and conditions of providing the engineering design and drawing services to support the CEC permitting process and EPC contract for an amount not to exceed $150,000.00; and WHEREAS, in the event an EPC contract is finalized with Scott, any amount paid pursuant to this interim letter agreement shall be treated as a credit to the City to be applied to the City's first payment under the EPC contract; and WHEREAS, on July 23, 2002, the Finance Committee recommended that the City Council approve the recommendation of Bruce V. Malkenhorst, Director of Finance, dated July 18, 2002, that an interim Letter Agreement be approved and executed with Scott; and WHEREAS, the City Council of the City of Vernon has determined that, pursuant to the provisions of subsection (a) of Section 2.27 of the Vernon City Code, it is in the public interest and necessity to enter into an interim Letter Agreement with Scott setting forth the terms and conditions of the services to be performed for the Malburg project to enhance services provided to the Vernon community. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF VERNON AS FOLLOWS: SECTION 1: The City Council of the City of Vernon hereby finds and determines that the recitals contained hereinabove are true and correct. - 2 - 1 SECTION 2: The City Council of the City of Vernon hereby 2 approves the Letter Agreement with Scott, a copy of which is attached 3 hereto as Exhibit "A" and made a part hereof. 4 SECTION 3: The City Council of the City of Vernon hereby 5 authorizes the Mayor and the City Clerk to execute said Letter 6 Agreement for, and on behalf of, the City of Vernon. 7 SECTION 4: The City Council of the City of Vernon hereby 8- directs the City Clerk, or his designee, to send one fully executed 9 Agreement to: 10 Scott Co. Industrial Contractors Attn. Steve Klaus, Project Manager 11 14920 S. San Pedro St. 12, Gardena, CA 90248 13 SECTION 5: The City Clerk of the City of Vernon shall 14 certify to the passage of this resolution, and thereupon and 15 thereafter the same shall be in full force and effect. 16 APPROVED AND ADOPTED this 24th day of July, 2002. 17 18 . EONIS C. MA URG, M yor 19 20 ATTEST: 21 22 23 BRUCE V. MALKENHORST, City Clerk 24 25 26 27 28 3 - STATE OF CALIFORNIA ) ) ss COUNTY OF LOS ANGELES ) I, BRUCE V. MALKENHORST, City Clerk of the City of Vernon, do hereby certify that the foregoing Resolution, being Resolution No. 8032, was duly adopted by the City Council of the City of Vernon at an adjourned regular meeting of the City Council duly held on Wednesday, July 24, 2002, and thereafter was duly signed by the Mayor of the City of Vernon. (SEAL) BRUCE V. MALKENHORST, City Clerk - 4 - CITY COUNCIL LEONIS C. MALBURG Mayor THOMAS A. YBARRA Mayor Pro-Tem WM. 'BILL" DAVIS Councilman H. "LARRY" GONZALES Councilman W. MICHAEL MCCORMICK Councilman BRUCE V. MALKENHORST City Administrator/City Clerk FAX (323) 826-1438 CITY HALL 4305 SANTA FE AVENUE, VERNON, CALIFORNIA 90058 TELEPHONE (323) 583-8811 July 24, 2002 LETTER AGREEMENT Scott Co. Industrial Contractors Attention: Mr. Steve Klaus 14920 S. San Pedro Street Gardena, CA 90248 EDUARDO OLIVO City Attorney FAX: (562) 869-1883 KEVIN WILSON Director of Community Services & Water FAX: (323) 826-1435 KENNETH J. DeDARIO Director of Municipal Utilities FAX: (323) 826-1425 STEVEN E. PARKER Fire Chief FAX: (323) 826-1407 BRUCE W. OLSON Police Chief FAX: (323) 826-1481 Re: Malburg Generating Station Project: City of Vernon Gentlemen: The City of Vernon (the "City") has received a proposal dated April 29, 2002, from Scott Co. Industrial Contractors, a subsidiary of The Scott Companies, Inc. ("Scott") for the engineering, procurement and construction ("EPC") of the Malburg Generating Station ("MGS") Project. A contract for the EPC has not yet been fully negotiated. However, in order for the City to provide the California Energy Commission ("CEC") with information it requires under its six-month expedited license process and complete the design requirements for the EPC contract, the City must proceed with the development and completion of the engineering design and drawings. Scott has indicated a willingness to provide such services to the City. However, Scott is concerned that it will incur costs associated with the completion of the engineering design and development while the EPC is being negotiated. Scott Co. Industrial Contractor Letter Agreement Page 2 July 24, 2002 The City and Scott (hereinafter referred to as "the Parties") intend to proceed with the negotiation of an EPC contract as soon as practical. The Parties also intend to complete such negotiations no later than August 14, 2002. The City shall not be obligated or bound by any EPC contract until and unless the negotiations result in a EPC contract acceptable to both parties and approved by the Vernon City Council. The Parties hereto do mutually agree to this Letter Agreement subject to the following terms and conditions: 1. The effective date for this Letter Agreement shall be July 24, 2002. 2. Scott shall proceed to complete the engineering design and drawings to support the CEC permitting process and complete the EPC contract. 3. The City shall pay Scott on a time and material basis. The total amount to be paid to Scott under this Letter Agreement shall not to exceed one hundred fifty thousand dollars ($150,000.00). 4. Scott shall submit an invoice to the City within thirty (30) days of the end of any month in which services have been performed or costs incurred by Scott. The invoice shall state the amount due to Scott and itemize the services performed. 5. The City of Vernon may terminate this Letter Agreement at any time, without cause. 6. If the parties are able to agree upon an EPC contract, all sums paid under this Letter Agreement shall be treated as a credit to the City which shall be applied to the first payment to be paid by the City under the EPC contract. Scott Co. Industrial Contractor Letter Agreement Page 3 July 24, 2002 7. This Letter Agreement shall be governed by the laws of the State of California. Please confirm your acceptance of this Letter Agreement by return. Sincerely, CITY OF VERNON ATTEST: By: Bruce V. Malkenhorst, City Clerk APPROVED AS TO FORM: By: Eduardo Olivo, City Attorney ACCEPTED BY SCOTA Adiax'�i o T Name Title Leonis C. Malburg, Mayor INDUSTRIAL CONTRACTORS, Scl,et Companies, Inc. J 1 P( 5 c 09 Staff Report co ?00� Date: August 22, 2002 lRgj0RsO g F,cjCF To: Bruce V. Malkenhorst, City Administrator From: Kenneth J. DeDario, Director of Utilities K4A— Ramon Z. Abueg, Assistant Director of Engineering & Operations 49.0— RE: Malburg Generating Station Project: EPC Contract The Utilities Department recommends approval of the EPC contract with Scott Company (Scott) for the detailed Engineering, Procurement of the balance of plant materials, and Construction (EPC) of the Malburg Generating Station (MGS) Project for the contract price of Forty -Three Million Nine Hundred Thousand Dollars ($43,900,000). Scott is a well -established mechanical contractor in Southern California and will serve as the prime contractor for the consortium for the MGS Project. The consortium consists of Scott and Power Engineers. The Scott consortium is experienced at power plant construction, particularly the Alstom generator based plants. Although Scott is regarded principally as a mechanical contractor, the MGS Project construction will be heavily weighted toward mechanical work. Scott has provided construction services widely in California and will use specialty subcontractors for work in those areas that are outside of its principal areas of expertise. Scott's use of Power Engineers to develop the detailed design for the MGS Project is positive, since Power Engineers was involved in the detailed design of the Redding, California and Chaska, Minnesota Alstom generator based plants. BACKGROUND Carter -Burgess, the City's design engineer, originally estimated the MGS Project Cost at Ninety Million Four Hundred Sixty -Five Thousand Three Hundred Ten Dollars ($90,465,310); see Attachment 1. The Carter -Burgess Original EPC Cost Estimate was established by subtracting the non-EPC related activities from the Original Cost Estimate as follows: Original Cost Estimate 90,465,310 - Owner's Design Engineer (950,000) - Program Management (3,250,000) - Equipment Purchased by City (54,562,329) Original EPC Cost Estimate 31,702,981 August 22, 2002 Staff Report: Malburg Generating Station Project: EPC Contract EPC SELECTION PROCESS On the City's behalf, Carter -Burgess sent out Contractor Questionnaire packages to established EPC contractors in the industry. The purpose of the Contractor Questionnaire was to pre -qualify the top five EPC contract bidders for further consideration. Due to the extensive volume of documents that needed to be reviewed, the City and Carter -Burgess determined that the final EPC bid packages would only be sent to the top five qualified EPC contractors. The Contractor Questionnaire was sent to the following: Item Bidder Response 1 ARB Yes 2 Black and Veatch Yes 3 TIC Yes 4 Alstom Power, Prenco Yes 5 University Marelich Mechanical Yes 6 Irwin Industries Yes 7 Swingerton Yes 8 FHI Plant Services Yes 9 Cherne Construction Yes 10 B I BB/Kiewitt No 11 Brinderson E&C No 12 CRC No 13 Dillingham No 14 Fluor No 15 Johnson -Peltier No 16 Nepco No 17 Pacific Western No 18 Parsons No 19 Thomason Mechanical No 20 Turner Construction No 21 Turner Industries (Harmony) No August 22, 2002 2 Staff Report: Malburg Generating Station Project: EPC Contract Nine bidders responded to the Contractor Questionnaire and were evaluated on a weighted qualitative basis using the following factors: 1. Quality and Experience of the On -Site General Contractor Staff Proposed 20% 2. Previous Demonstrated Experience in the Construction of Similar 120 MW CC Power Plants 20% 3. Quality and Experience of the General Contractor's Home Office Support Staff 10% 4. Ability of the General Contractor to Support Construction Start & Completion Dates 10% 5. Quality of the General Contractor's and Designer's Project Management System 10% 6. Ability of the General Contractor to Provide Required Skilled Union Personnel 5% 7. Quality & Experience of the General Contractor's Designer of Similar 120 MW Power Plants 10% 8. General Contractor's Financial and Bonding Strength. 15% 100% Each category was given 5 points. Each category was then weighted as noted in the table above. A perfect score for item one would be 5 times 20% or a value of 1. A perfect score for the sum of all the categories would be 5. Carter -Burgess verified the information furnished in the responses including bank references, D&B rating, company's net worth, bonding capacity, insurance company, and credit references. ARB and Black & Veatch decided to team up during the evaluation process. TIC, BIBB, and Kiewit also formed a consortium. The evaluation process resulted in four qualified bidders with a fifth as an alternate. Resulting from the pre -qualification process, bid packages were sent to the following pre - qualified bidders: 1. ARB/Black & Veatch, 2. TIC/BiBB/Kiewitt, 3. Alstom Power (Prenco) & Power Engineers, 4. University Marelich Mechanical, 5. Irwin Industries August 22, 2002 3 Staff Report: Malburg Generating Station Project: EPC Contract During the bid process, Alstom Power (Prenco) contacted the City and Carter -Burgess. Prenco requested that the City consider a new consortium of Scott/Prenco/Power Engineers because Prenco would not be able to take a general contractor position because of a policy change in the Alstom Corporation. It was determined that this was satisfactory as long as Scott met the pre -qualification requirements. Scott submitted the requisite documents and referrals, which Carter -Burgess verified, to qualify Scott as a bidder for this project. Four of the five bidders submitted a proposal: • Scott/Prenco/Power Engineers $ 48,762,600 • University Marelich Mechanical $ 50,870,200 • ARB/Black & Veatch $ 63,000,622 • TIC/BiBB/Kiewitt $ 69,300,200 ADDITIONAL COSTS FOR EPC The prices provided by the bidders were significantly higher than the Carter -Burgess Original EPC Cost Estimate. Therefore, the Utilities Department instructed Carter -Burgess to re- evaluate the project cost estimate analyzing the factors that may have accounted for the difference between the Carter -Burgess Original EPC Cost Estimate and the bid prices. The following items were identified as the contributing factors to the variance in costs. CEC Licensing Process: During the Application for Certification (AFC) process with the California Energy Commission (CEC) for the construction and operation of the MGS, substantial modifications were made to the project design basis. The CEC required that the seismic design basis be changed due to the possible damaging effects of newly discovered earthquake faults, not shown in geographic maps, known as blind thrust faults. This additional cost for the changes in engineering design, additional equipment, and increased earthwork/foundation is estimated at $3,000.000, and was not included in the Carter -Burgess Original EPC Cost Estimate. 2. Site and Laydown Areas: The EPC bidders had concerns about the small area, tight space and availability of laydown areas at the project site. The project site is much smaller than the normal project site for this size of plant to accommodate construction offices, and parking, laydown, staging and storage areas. The EPC bidders, particularly Scott, expressed concerns regarding the risk due to congestion and the impact on productivity due to the size of the project site. The increased cost attributable to this risk is estimated to be $5,000,000, which consists of higher direct labor, overhead and equipment utilization. 3. Labor Cost: Carter -Burgess estimated the labor hours and rate based on a similar project that it had worked on previously in the Denver area. Carter -Burgess mistakenly failed to utilize the labor rates that applied in the Los Angeles area for skilled labor. Carter -Burgess also significantly underestimated the total labor man- hours required for this project. This results in a cost difference of approximately $2,945,000 in the labor component. August 22, 2002 4 Staff Report: Malburg Generating Station Project: EPC Contract 4. Contractor Supplied Equipment: There also has been some increase in the contractor furnished equipment cost. The water treatment system has been modified to process the reclaimed water that will be used for cooling. This results in an increase of $413,800. Below is Carter -Burgess' Adjusted EPC Cost Estimate which includes the changes due to the above items: Original EPC Cost Estimate Seismic Requirement Site and Laydown Risks Labor Costs Equipment Change Adjusted EPC Cost Estimate INDEPENDENT CONSULTANT REVIEW 31,702,981 3,000,000 5,000,000 2,945,000 413,800 $43,061,781 Since the proposals received from the four bidders came in higher than Carter -Burgess' Adjusted EPC Cost Estimate, the Utilities Department requested Navigant Consulting, Inc. (Navigant) to provide an independent review of the bid proposals, specifically Scott's proposal. Navigant compared the MGS Project data to recently published data for installation of a similar plant using the traditional EPC concept. Unlike the MGS Project, the traditional EPC concept would include procurement of all equipment. Navigant determined that the EPC cost should be on the order of $600/KW or approximately $80,000,000. This estimate was then adjusted for site location & conditions and required emissions equipment for an additional cost of $10,000,000 and $5,000,000, respectively. Navigant also noted that there is an unusual amount of concrete needed because of the additional seismic requirements for the MGS Project which adds approximately $4,000,000. Navigant's estimate for the MGS Project EPC cost, using the traditional EPC concept, (as noted above, this includes the purchase of all equipment) was approximately $100,000,000 excluding site costs, transmission, taxes, permits and interconnections. Navigant then estimated the EPC cost for the MGS Project by subtracting the cost of the equipment the City had already committed to purchase, approximately $58,000,000, from Navigant's total estimated cost of $100,000,000. This resulted in Navigant's EPC cost estimate of $42,000,000. However, the $58,000,000 equipment cost used by Navigant included approximately $4,000,000 of owner's engineer work which is being provided by Carter -Burgess. Therefore, Navigant's EPC cost estimate should have been $4,000,000 higher or approximately $46,000,000. Please see Attachment 4 for details. August 22, 2002 5 Staff Report: Malburg Generating Station Project: EPC Contract REJECTION OF BIDS All bids were rejected because the prices were higher than the Carter -Burgess Original EPC Cost Estimate of $31,702,981 and the Carter -Burgess Adjusted EPC Cost Estimate of $43,061,781. Staff contacted all bidders to ask them if they would be willing to negotiate their prices down to below $45,000,000. Two bidders, ARB/Black & Veatch and TIC/BiBB/Kiewitt, were not willing to drop their prices. University Marelich Mechanical did not respond. Only Scott was willing to negotiate. The Utilities Department then sought and received approval from the City Council to have an exclusive discussion with Scott Company, the lowest bidder, to attempt to negotiate a contract price close to the Carter -Burgess Adjusted EPC Cost Estimate of $43,061,781. NEGOTIATIONS and RESULT After several discussions with Scott, it offered a reduced price of $44,985,000. The Utilities Department continued to pursue Scott for additional price reduction. Scott indicated that it could reduce it's price further, if the City would allow Scott to change its consortium of Scott, Prenco (Alstom) and Power Engineers to Scott and Power Engineers, citing that only Prenco was unwilling to reduce its price. Prenco's role in the consortium was to specify and purchase the balance of plant equipment. However, since Power Engineers had worked on the Alstom power plant projects in Redding, California and Chaska, Minnesota, similar to the MGS Project, Power Engineers was well qualified to perform these activities. All the bidders rejected the liquidated damages requirements of the Sample EPC Contract Document provided in the Request for Proposals. Both the City and Carter -Burgess decided that it was economical to reduce the liquidated damages requirements in consideration for a reduction in the bid price. After further discussions with Scott the final negotiated EPC cost is $43,900,000, which is only approximately two percent (2%) higher than the Carter -Burgess Adjusted EPC Cost Estimate of $43,061,781. This negotiated price is a reduction of $4,862,600, approximately ten percent (10%) lower than Scott's original bid of $48,762,600. The Utilities Department, Carter -Burgess, Scott and Power Engineers have reviewed and conformed the EPC specifications, site conditions, schedule and engineering drawings as part of the EPC contract. As part of the negotiation the Utilities Department required Scott to produce detailed drawings to ensure that Scott had a good understanding of the specifications. The City Council authorized, through a Letter Agreement, to pay up to $150,000 for the cost of these drawings which shall be deducted from the final negotiated EPC cost of $43,900,000. Staff believes that because the detailed drawings are part of the EPC Contract, this price is firm and that the need for future change orders will be minimal. CONCLUSION Based on the above information, the Utilities Department has concluded that the EPC price of $43,900,000 is reasonable for the MGS Project. Therefore, this affirms our recommendation of approval of the EPC contract with Scott Company. RZA:dm Attachments August 22, 2002 Staff Report: Malburg Generating Station Project: EPC Contract Attachment 1. Original Project Cost Schedule Attachment 2. Carter -Burgess EPC Bid Analysis Attachment 3. Project Capital Cost vs EPC Bid Attachment 4. Navigant's Assessment of EPC Proposal August 22, 2002 7 ATTACHMENT 1 Original Project Cost Schedule Carter & Burgess, Inc. ESTIMATE SUMMARY Customer City of Vernon Proposal Number Location Vernon, CA Job Number 070734.400 Project Name 135 MW Combined Cycle Power Plant Date 12/17/2001 A/stom - GTX100 Estimated By Dan Heilig Revision Number 1 Estimated By Rev Date 12/17/2001 Craft Craft Labor Material Other Total % % Acct Description Hours Rate Dollars Dollars Dollars Dollars TEFC DFL A Earthwork & Concrete 27,000 $18.70 505,000 625,000 1,130,000 0.014 B Structural Steel/Buildings/Plant Items 3,500 $21.43 75,000 300,000 220,000 595,000 0.007 C Piping Systems 46,000 $25.00 1,150,000 1,875,000 3,025,000 0.038 D Process Equipment * 51,000 $25.00 1,275,000 54,056,500 200,000 65,531,500 0.689 E 1 Electrical Systems/instrument & Controls 82,000 $25.00 2,050,000 4,365,000 6,415,000 0.080 F I Painting & Insulation 400,000 400,000 0.005 Total Direct Field Cost 209,500 $24.13 5,055,000 61,221,500 820,000 67,096,500 0.83 G01 Field Staff & Office Expense 1,668,150 0.330 G02 Payroll Taxes & Insurance 925,065 0.183 G03 Const Expendables & Supplies 288,135 0.057 G04 Temporary Facilities 434,730 0.086 G05 Const Equipment & Tools 1.668,150 0.330 G06 Craft Benefits & Construction Camp 1,258,695 0.249 G07 Startup of Facilities 232,530 0.046 6,475,455 Total Indirect Field Cost 707,7001 640,3321 5,127.423 6,475,455 0.08 1.281 H Contractor Final Design less OFE foundations 2,850,000 0.04 H Owners Engineer 30% Design) 950,000 0.01 H Owners PM/CM/Startup/Long Lead Procure/Contract(plus OFE foundations $650K 3,250,000 0.04 turbine foundations design included in the $2,600,000 Total Field & Office Cost 80,621,955 1.0 J01 Sales & Use Tax 0.00% J02 Craft Premium Pa - 5% 252,750 J03 Contingency 5,769,500 7.16% Subtotal 86,644,205 J04 Contractors Fee - 5% 3,821,105 Jos 0.00% 90.465,310 Total Project Cost 135000 $ 670 /Per Kw 90,465,310 Note: Emission offsets, IDC, demolition, switchyard modifications, gas and water supply line, taxes forequipment and material and permits are not included. Note: This estimate is based upon Carter & Burgess' experience with projects of similar scope and size. The estimate utilizes actual equipment supplier quotes and budget estimates. This information is used to factor the total estimate based on historical data. The probability of maintaining the projects installed cost basis is -5% to + 20%. Note: * Includes price for combined catalyst system. ATTACHMENT 2 Carter -Burgess EPC Bid Analysis Carter Surgess May 28, 2002 City of Vernon Attn. Mr. Ramon Abueg 4305 Santa Fe Avenue Vernon, CA 90058 Reference: MALBURG GENERATING STATION EPC Bid Evaluation Dear Mr. Abueg; Summary LTR-143 216 Sixteenth Street Mall Suite 1700 Denier, Colorado 80202-5131 Phone: 303.820.5202 Fax: 303.595.0833 The bids from all four bidders was much higher than the value remaining in the original budget. Some of the items that impact the budget value have been discussed in letter 144. However, even taking these items into account all four bids were still high. We have recommended and the City concurred to essentially reject all bids and bring in the first lowest evaluated bidder, Scott, for detailed discussion as outlined in Itr 142 and Scott Itr 2. If Scott can not come to resolution with the City, the next step would be to bring in either ARB or University Marelich. Currently ARB has been told there is a possibility that they will be contacted. As discussed below ARB has good construction experience, however, there cost is much higher and their engineer has taken many significant exceptions to the RFQ. The University Marelich proposal is much closer the Scott bid in price. However, they do not show significant experience with this type of project and they have also taken significant exceptions to the RFQ. Bid Evaluation Technically acceptable bids were received from teams lead by TIC, Scott Co, University Marelich Mechanical, and ARB Inc. The quantitative, and qualitative bid comparison is in the attached excel spread sheet, (prop bid form). Table 1 includes the capital cost comparison. Table 2 includes the detailed manhours and cost estimates that were requested from the bidders. Table 3 includes the qualitative evaluation parameters. r� The adjusted bid price for each bidder is shown on Table 1. Several minor adjustments were required to bring the bids to a similar basis. The total costs identified have been adjusted as best as possible to allow all four bids to be compared directly. However, as noted below the Bidders have excluded some of the requirements of the RFQ. The bidders were requested to Carter & Bin-gess. Inc. Carter & Burgess Consultants, Inc. Nixon & Laird Architects -`Engineers. P.C. :Nixon & Laird Architects"Engineers. Inc. C&B : evada. Inc. CarternBurgess_ supply the estimated costs for the major equipment that they offered as well as the installation manhour for the major equipment. These items are shown in Table 2. Qualitative A simple matrix was included in the RFQ describing how the bidders non -cost issues would be evaluated. A summary of these items as well as C-B evaluation is included in the attached Table 3. Recent team or company experience with similar sized projects The TIC and ARB Company experience identified were very good. They were rated high. The University Marelich team had poor experience identified. They were rated 0 for this category.. Scott Co by itself does not show a great deal of large of project or scope. However, they are teamed with Alstom Power which has installed the only GTX100 machines in the US. They were given medium marks. Experience of the engineering team All four bidders have selected companies experienced in engineering combined cycle power projects with good experience. It also appears that the individuals assigned have good experience for all four teams. All four teams were given high marks in this category. Experience of Construction Team The TIC and ARB teams have much recent combined cycle experience. They were given high marks for this category. University Marelich proposed team, has very little combined cycle power plant construction experience as identified in their proposal. They were given low marks for this category. Scotts team also does not show much experience in larger combined cycle projects. It is assumed that Alstom Power would provide the needed experience. However, this needs to be discussed with them in detail. They were given medium marks in this category. Completeness and content of the technical proposal The Scott proposal was the most complete proposal. It was given high marks. The University Marelich was the least complete technical presentation. However, they took very few exceptions. It is unclear from the their proposal whether they understood the scope requirements. The University Marlich bid was given medium marks. The TIC and ARB bids had many technical exceptions and ignored significant items that really can't be changed. These two bidders were given very low marks for this category. Compliance with General Terms & Conditions University Marelich had very few quoted exceptions to the bid. They were given high marks. TIC, Scott and ARB had significant exceptions. They were given medium marks in this category. Carter & Burp ess. Inc. Carter & Burgess Consultants. Inc. Nikon & Laird ArchitectsTrigincers. P.C. Nixon & Laird Architects' Engineers. Inc. C&B N'ecada. Inc. Carter=Burgess Responsiveness to required schedule Scott and ARB both complied with the required schedule. Neither offered shorter schedules. The TIC and University schedules were very generic and did not indicate a clear understanding of the project. They were given medium marks Ability to of Contractor to Post bid bond All four bidders demonstrated the ability to adequately post the performance bond. All four wer given high marks. Financial stability of prime contractor All four bidders appear to be financially sound and capable of executing this project. All four were given high marks in this category. The total weighted result of the qualitative evaluation is shown at the bottom of the qualitative bid tab table. As can be seen C-B ranked the bidders in the following order:. Best evaluation 1 Scott 2 ARB 3 Marelich 4 TIC Lowest evaluation Detailed Bid Discussion • • • Scotts proposal included the lowest base bid taking into account any exceptions clarifications, etc. Scott's proposal was detailed and provided good technical information. It is clear that they understand the overall project. Specific Comments Scott's proposed project managers do not indicate a great deal of experience with this type of work and this size of project. This would need to be discussed in detail before proceeding. Scott has taken exception to the noise guarantee as have the other three bidders. Scott has taken exception to the auxiliary power requirement due to their concern about measuring the total. This item needs to be addressed. Carter & Burgess. Inc. Carter & Burgess Consultants. Inc. Nixon & Laird architects `Engineers. P.C. Nixon & Laird architects/Engineers. Inc. C&B Nevada. Inc. Carter -.:Burgess Scott has identified a long list of clarifications and exceptions. These have been addressed individually in letter 142 and Scottltr 2. These items will be reviewed with the bidder during the May 30, 2002 meeting. University Marelich Bid The University Marelich proposal was the second lowest in base cost. However, their technical proposal was very brief, incomplete, and did not allow C-B to realistically access their proposal. Their cost and manhour breakdown were similar to Scott's with some exceptions. Specific comments University Marelich's chose to modify the balance of plant equipment layout. It is not clear at this time whether the changes proposed offer a net benefit or not. If they were to be considered, substantial review would be required. U_M did offer a deduct for the site security of $120,000 U_M did not include any specific vendor information for any of the equipment they may offer. This makes a technical evaluation very difficult. U_M did not include any manhours for plant commissioning. U_M did not provide a noise guarantee. They did include an allowance of $750,000 for noise related efforts. Since none of the other bidders offered a noise guarantee. This value was deducted from their bid. U_M did not supply a management plan. It would be provided after award. This does not allow C-B to evaluate their approach. U_M has identified that all cables listed in the Alstom equipment are to be provided by Alstom. As clearly stated in the Alstom Contracts, which are part of the RFQ not all of the cables are provided. U_M has not included transportation to the site and unloading. As clearly identified in the Alstom Contracts, Alstom will deliver to the site all equipment. Unloading is not part of Alstom's Contract. U_M did not understand the auxiliary power request. They have estimated the entire aux power demand, most of which is not in the Contractors scope. Their aux power guarantee is not what was requested. U_M also prepared a GTPro heat balance model using the generic Alsto9m data. This balance is not very relevant and was un-necessary effort on their part. U_M did agree to the Alstom pressure limitations on HP and LP steam lines. Carter & Burgess. Inc. Carter & Burgess Considtanis. Inc. Nixon & I .tird Arciiit ctsiEiigineers. P.C. Dixon & Laird Architects'Enpineers. Inc. C&B Nevada. Inc. Carter=Burgess The U-M schedule does not reflect the revised start date and includes engineering functions for the equipment already completed. It is difficult to review the schedule in detail U_M did provide a manloading curve. However, the loading details do not appear logical and appear somewhat arbitrarily defined. U_M did provide an equipment list, but it appears there is some duplication and confusion within the Fist. Other than a single general arrangement the bid, contains very little technical information. ARB The ARB evaluated proposal was the third highest by a wide margin, approximately 30% higher than the low bidder. However, their technical proposal was well organized and provided a good description of their bid. Their engineering approach appears to be based on designing the plant from scratch and does not appear to take into account the work that has already been completed. There are several significant items in the ARB bid that would require detailed discussion. Specific comments The construction HRSG manhours do not appear to take into account the modular basis of the Alstom design. ARB offered a deduct of $72,000 if it does not include site security. This is a much lower deduct than the other bidders. ARB also offered a deduct of $150,000 if does not have to rent warehouse space. (CONFIRM) The equipment cost information requested is consistent with the project estimates. The direct manhours identified in the ARB proposal are approximately 20% higher than the low bidder and the engineers factored estimate. It is unclear if the field supervision in this number is on an equivalent basis with the other bidders and the engineers estimate. ARB has identified a 90 day delay on receiving equipment. This would have to be discussed, as there would be substantial cost involved in this arrangement. The schedule provided appears to be based on another project and is somewhat generic in nature. ARS did offer a-aux power and steamline pressure drop guarantee. The steamline pressure drop guarantees are lower than the value required by Alstom. This would offer a small benefit to the total plant operating costs. This would not be a large savings. Carter & Burgess, Inc. Carter & Burgess Consultants. Inc. Nixon & Laird .%reliitects,'Engitteers. P.C. Nixon & Laird Architects/Engineers. Inc. C&B Nevada. Inc. Carter -.:Burgess ARB did not include a noise guarantee. ARB offers a lower retention and a lower LD for schedule than requested. ARB identified that the plant will be engineered to their engineer's standards and essentially takes exception to the RFQ technical requirements. This is not an acceptable approach. ARB has decided that it needs 5 acres of laydown area and has not included this in their cost. This response is unacceptable. ARB has not included startup spares, an estimate for these has been added to the ARB proposal price. ARB has excluded any special tools or rigging. This item would have to be reviewed in detail. ARB has taken numerous exceptions to the technical details of the RFQ. Some of the items are worthy of review and comment. However, many of the items have been addressed in the details of the RFQ. If ARB is to be considered all of these items need to be addressed. ARB did not include technical information as requested. This makes an evaluation of the technical merits of their proposal difficult. TIC The TIC bid is the highest bid by over 40% of the low bid. In addition, TIC refused to provide any of the, manhour or cost breakdown information requested in the RFP proposal form. TIC did indicate the direct field mahours in their schedule. This value is actually close to the direct mahour estimate from C-B and the Scott bid. TIC took significant technical and commercial exceptions. Since their price was excessively higher than the other bidders and as noted excessively higher than the remaining budget. Further review was not conducted at this time. trte 13ui ess, Inc. Moore Project Engineer CC: File Carter & Burgess, Inc. Carter & Burgess Consultants. Inc. Nixon &P.C. Nixon & Laird Architectsll ngineers, Inc. C&B Nevada- Inc. CITYOF VERNON MALBURG STATION EPC BID EVALUATION TABLE 1 BIDDER TIC SCOTT ARB UNIVERSITY MARELICH Home Office En ineering Material $0 $78,000 $0 $0 Labor 896 000 10 900 527 700 000 Total 3 974 000 10 900 527 7 000 Earthwork and Concrete Material $0 $3,545,000 $1,340,489 $956,200 Labor 4 675 000 $4.323.605 $1.434.300 Total $0 $8,220,000 $5,664,094 2 390 500 Widinp and Enclosures Material $0 $429,000 $254,650 $475,400 Labor 351 000 $352.268 $713,100 Total 780 000 918 1 188 500 Structural Steel Pipe Rack Material $0 $117,000 $456,720 $155,200 Labor 95,000 $187,184 700 Total 312 000 $643.904 $387,900 Structural Steel, Other Material $0 $55,000 $119,470 $291,800 Labor 2 000 $130.487 38 800 Total 117 000 $249,957 730 600 Process Sptems Material $0 $5,454,000 $2,957,915 $2,096,700 Labor $0 $4,675,000 $8,587,51S $11,012,100 Total 10 129 000 $11,545,43D $13,108,800 Piping System Material $0 $935,000 $3,022,779 $3,167,400 Labor 1091000 $4,669,950 $3,676,200 Total 2 026 000 $7,692,729 $6,843,600 Electrical Material $0 $3,081,000 $2,745,493 $3,129,400 Labor 7 791000 $7.127,003 3 019 400 Total 10 872 000 $9,872,496 148 800 Instrumentation & Controls Material $0 $312,000 $1,678,985 $2,569,200 Labor 31 000 715 888 587 000 Total 24 000 2 394 873 156 200 Paintingand Insulation Material $0 $358,000 $0 $455,400 Labor 390 000 34 413 13 100 Total 748 000 34 413 1268 500 Indirect Field Costs Material $0 $1,558,000 $0 $1,433,300 Labor 0 454 000 295 279 1413 500 Total 7 012,000 295 279 2 846 800 Contractor Conlin $0 $766,000 $350,000 $1,700,000 Contractor Fee $0 $3,132,400 $5,950,000 $3,000,000 Craft Premium Pa $0 $50,000 $0 $500,000 Firm LumpSum Price $0 $48,762,400 $63,000,620 $49,970,200 STARTUP SPARES Noise alkwvance excluded Engineering work station HRS System Plant commissioning No site security TOTAL Builders Risk for City Equip $69,300,2 ? $0 inc inc inc NA $69,300,2 ? 1 $48,762,600 INC $0 $253,000 $338,100 inc -120,000 $49,233,700 $382,140 $63,000,622 $125,000 $0 $0 $0 472,800 $63,052,822 1 ? $50,870,000 ? -$750,000 $500,000 4120,000 $50,500,000 ? 8119/200211:58 AMProp FormCity.)ds w ^ 'o O O O O >.= N M NN M Z c O 0 o C 0 C!00 g N Q S tff ri C N aO k 0 0 goo pO co U O N N M lax~= a O N O O O Z Z Z C v 0 0 'Q U) L E O O C-NF` Oc -c v m cli 7 .O (C(��7 O �% � to A 11=ii.. U m U !1W U- i O O MNOO C4 M co C4 c rn v- M a O a c, a OrOn� M %D 0 C N go O 7 N U E u'l aci E _a O 0 W *' ioc 78 aci � a ao cnc ►- L c O +� O C N naaL U°c 00 g g O O� ClCD O O VO' � {O O O N U w P. Ln M o -W -64- g0o0o00 g o o0 00 �OOOOggg �OggclO l0 co Ln nN rl r-1 t4 OD LLn m r 4 d- g g O O S Co p pp O O p O OR pN Cl O^ N N Ot p Ln U O� N 0% VA e q N P. iM 4 Noy O7 N N N� a a m OJ cc cc N cc o ac w c Ig 12 U O O O O O O O O O O Z Z Z Z Z Z Z Z Z Z Y C H V ra E� v Lra V m vl �a pu,Ev 7N R L p� OCT �N� W a 6 W Ujjl W W 0 0 Itr 49 0 0 - T` g le CO) N 40 O O OD OD u1 co st vi va UC 0 V C 0 L o LU a 3 - c a EE E 4 Q 0. = a. J o3 � o apq s R upi u�i 9 or. C N G G 14 .+ O O n O 8 8 8 8 0 p O Z r: er ui ao .� ,� 40 .� s ..ci C4 ui.. ., 8 8 8 8 R 5t 8 L Op ti .p-ipO CD } O oN O 8 8.8 U�Oa vi �Or N ®g i6 ZNW N N WNW NW WNN 3�y NWOS } Z } Z ]W } } } � Q V } >W R " W V Z N C a 8 It 8 It co to co co co co c co c 9n � wwwzzov>W Z_" !Zor z aN� 8 8 1Q O fn WmW fn fWWn fn m "' to g O i'� E N ?WYYr V Z�ZZW U C � N C p 0 "yWc-Z`` �Z}ZU a �N E kx n m ru LO in Z W O Q J 0 U. u 8 8 8 0Ln v .� fV tV O O ti C O 1z U O O O O 8 8 8. O 8 a m C �ar V j C E Ev Cm ' a _u`u'' u E E ue Y u C Y �Q�j R a 00 � vIM v u�+ p ~ C C V L C C U O W O�+ Yam° 3i c av 0 a p•-�. �w �E aS8. 1 _ aLr m u! t�- O N LLJ >• V >r z C r y §g o w g pp - C w ��g ax _oaa9 -j m mc . °CL OWZ N 20 VOw,O-N.E 0 i' E. O W 0. CW U d V V m E m �CL w C IM N V m�t�=IL �� m�uj g _� as U)i Uaz°O� .miw ATTACHMENT 3 Project Capital Cost vs EPC Bid Carter Surgess May 23, 2002 City of Vernon Attn. Mr. Ramon Abueg 4305 Santa Fe Avenue Vernon, CA 90058 Reference: MALBURG GENERATING STATION Project Capital Cost vs. EPC Bid Dear Mr. Abueg; LTR-144 216 Sixteenth Street Mail Suite 1700 Denver, Colorado 80202-5131 Phone: 303.820.5202 Fax: 303.595.0833 Since November of last year the project team has been concentrating on supporting the City in its efforts to get the appropriate permits. This effort has required some decisions that have affected the capital cost of this project. C-B has looked at the factors that have contributed to a higher project cost. They are discussed in detail below. The attached table summarizes these additions: Project Cost, December estimate 2001 $90 465 310 Additional Items ApproArnate Cost 1 Seismic Criteria Change, engineering, concrete, earthwork, etc $3,000,000 Added Equipment Costs 2 Cooling Tower Adder, complete $236 000 3 Condenser Adder, complete $133,000 4 ALSTOM-equipment added, Complete $625 000 5 Water Treatment System, In EPC Scope) 413 800 6 Noise Mitigation Allowance $750,000 Construction Impacts 7 1 Added cost for congestion and lack of la down $5 000 000 8 Contractor's Risk $1,000 000 9 Direct Contract Labor Increase approx. 20% $1,300,000 10 Indirect Craft labor based on direct increase $585,000 TOTAL REVISED PROJECT COST ESTIMATE $103 508 110 Item 1 Carter & Burgess, Inc. Carter & Burgess Consultants. Inc. Nixon & laird Architects/Engineers. P.C. Nixon & Laird Architects/Engineers-_ Inc. C&B Nevada. Inc. Carter Burgess The revised seismic criteria required by the CEC has had a significant impact on the installation cost. Primarily due to the large increase in foundation size and earthwork required. Items 2, 3, 4, & 5 Since the early estimates we have seen an increase in the process equipment cost. Additionally several other challenges have surfaced, mostly with respect to the permit application. All of these items have had an impact not only in the capital cost but indirectly the installation cost. We have estimated the impacts of these changes. These items include, the Alstom change orders, cooling tower added costs, condenser added costs, and the water treatment system that was initially based on a potable water supply instead of the reclaimed water which is currently being used. Item 6 The noise mitigation requirements were increased between when the estimate was prepared and the present. The exact value is unknown until negotiations can be completed with the Contractor. However, one of the bidders assigned a value of $750,000 for this effort. This was included to account for this effort. Item 7 & 8 We have also re -looked at the possible impacts of the limited laydown area available, site congestion, productivity, and Contractors risk and have assigned the a value to them. Item 9&10 As a comparison the following table indicates the estimated direct manhours that the bidders proposed as compared to the revised factored estimate. As can be seen from the table the factored estimate direct manhour estimate is essentially equal to the low bidder and close to the others. Original Est I Revised Estimate Scott Co I ARB 1209,500 1260,750 1263,963. 284116 312 962* * This value may contain some supervision hours. However, it appears that the EPC bidders are using a higher direct manhour rate than C- B used last April for the average direct labor rate. As can be seen from the estimate sheets we utilized a direct labor rate of $24.13/hr. It appears that a current union value should be higher Based on rough order of magnitude of current labor rates we revised the estimate using an average rate of $28.10/hr. This results in a cost increase of $1,300,000 for direct labor and $585,000 for the indirect labor portion. We included the impacts of this labor change in the revised estimate of 5/22/02 Carter & Burgess. Inc. Carter R Burgess Consultants. Inc. Nixon & Laird Architects -Engineers. P.C. Nixon & Laird ArchitectsiEngineers. Inc. C&B Nevada. Inc. Carter: -Burgess These additions and changes have been incorporated into a revised factored cost estimated dated 5/22/02, which is attached together with the original estimate. To see the impact of these changes and to compare EPC Bids with these estimates Table 1 was prepared. This table also shows the equivalent cost of the EPC bid price for the original project estimate, the original project estimate plus 20%, the 5/22/02 and the three bidders that supplied detailed information. This effort was completed to provide a basis for further discussions with prospective bidders. Please call if you have questions or comments. Sincerely, rter urgers, Inc. Kelvin Moore Project Engineer CC: File Carter & Burgess, Ine. Carter & Burgess Consultants. Inc. Nixon & i,aird Architects'Isn;gineers, P.C. Nixon & Laird ArchitectsTrigineers, Inc. C&B Nevada; Inc. Carter & Burgess, Inc. ESTIMATE SUMMARY Customer City of Vernon Proposal Number Location Vernon, CA Job Number 070734.400 Project Name 135 MW Combined Cycle Power Plant Date 12/17/2001 Alstom - G7X100 Estimated By Dan Heilig Revision Number 1 Estimated By Rev Date 12/17/2001 Craft Craft Labor Material Other Total 1 °A °A Acct Description Hours Rate Dollars Dollars Dollars Dollars TEFC DFL A Earthwork & Concrete 27,000 $18.70 505,000 625,000 1,130,0001 0..014 B Structural Steel /Buitdin s/Plant Items 3,500 $21.43 75,000 300,000 220,000 596,000 0.007 C Pi in Systems 46,000 $25.00 1,150,000 1,875,000 3,025,000 0.038 D Process Equipment 51,000 $25.001 1,275,000 54,056,500 200,000 55,531,500 0.689 E Electrical S stemstinstrument & Controls 82,000 $25.00 2,050,000 4,365,000 6,415,000 0.080 F Painting & Insulation 400,000 400,000 0.005 Total Direct Field Cost 209,500 $24.13 5,055,000 61,221,500 820,000 67,096,5001 0.83 G01 Field Staff & Office Expense 1,668,150 0.330 G02 Payroll Taxes & Insurance 925,065 0.183 G03 Const Expendables & Supplies 288,135 0.057 G04 Temporary Facilities 434,730 0.086 G05 Const Equipment & Tools 1,668,150 0.330 G06 Craft Benefits & Construction Camp 1,258,695 0.249 G07 Startup of Facilities 232,530 0.046 6,475,455 Total Indirect Field Cost 707,7001 640,332 5,127,423 6,475,455 0.08 1.281 H Contractor Final Design (less O FE foundations) 2,850,000 0.04 H Owners Engineer 30°A Design) 950,000 0.01 H Owners PM/CM/Startup/Lon Lead Procure/Contract(plus OFE foundations $650K 3,250,000 0.04 turbine foundations design included in the $2,600,00 0 Total Field & Office Cost 80,621,955 1.0 J01 Sales & Use Tax 0.00% J02 Craft Premium Pa - 5°A 252,750 J03 Contingency 5,769,500 7.16% Subtotal 86,644,205 J04 Contractors Fee - 5% 3,821,105 J05 0.00% 90,465,310 - Total Project Cost 135000 $ 670 /Per Kw. 90,465,310 Note: Emission offsets, IDC , demolition, switchyard modifications, gas and water supply line, taxes forequipment and material and permits ar a not included. Note: This estimate is based upon Carter & Burgess' experience w ith projects of similar scope and size. The estimate utilizes actual equipment supplier q uotes and budget estimates. This information is used to factor the total estimate based on histor ical data. The probability of maintaining the projects installed cost basis is -5% to + 20%. Note:' Includes price for combined catalyst system. Carter & Burgess, Inc. PESTIMATE SUMMARY Customer City of Vernon Proposal Num bar Location Vernon, CA Job Number 070734.400 Project Name 135 MW Combined Cycle Power Plant Date 5/22/2002 Alstom-GTX100 Estimated By DanHeilig Revision Number 2 Estimated By Jerry Gotlieb Rev Date 5122/2002 5/22/2002 Craft Hours Craft Rate Labor Dollars Material Dollars Sic Dollars Total Dollars % TEFC 04 DFL Acct Description A Earthwork & Concrete" 66,988 $22.44 1,503,510 1,283,051 2,786,561 0.031 B Structural Steel /Buiklin s/Plant Items"' 21,400 $25.71 550,286 2,300,000 440,000 3,290,286 0.036 C Piping Systems 59,048 $30.00 1,771,440 1,875,000 3,646,440 0.040 D Process Equipment • 52,000 $30.00 1,560,000 54,310,815 55,870,816 0.616 E Electrical Systems/instrument & Controls 61,314 $30.00 1,839,432 4,839,314 300,000 6,978,746 0.077 F Painting & Insulation 450,000 450,000 0.005 Total Direct Field Cost 260,750 $28.10 7,224,6681 64,608,180 1,190,000 73,022,848 0.81 G01 Field Staff & Office Expense 2,384,140 0.330 G02 Payroll Taxes & Insurance 1,322,114 0.183 G03 Const Expendab les & Sup lie s 411,806 0.057 G04 Temporary Facilities 621,321 0.086 GOS Const Equipme nt & Tools 2,420,264 0.335 G06 Craft Benefits & Construction Camp 3,251,101 0.450 G07 Startup of Facilities 332,335 0.046 $ 68.91 Total indirect Field Cost 10,743,081 0.12 1.487 H Contractor Final Design less O FE foundations 2,850,000 0.03 H Owners Engineer 30% Design) 950,000 0.01 H Owners PWCM/Startu /Lon Lead Procure/Contract plus OFE foundations $650K 3,100,000 0.03 turbine foundations design included in the $3.MM Total Field & Office Cost 90,665,929 1.0 J01 Noise requirements Sales & Use Tax, Exempt 0.00% 750,000 - J02 Craft Premium Pa - 10 Hours Per Week 732,740 J03 Contingency. 7,183,935 7.86% Subtotal 99,332,605 J04 lContractors Fee - .035% 3,476,641 J05 Subtotal Risk for Owner's Terms & Schedule UD's $ 60,000.00 per day 102,809,246 350,000 Total Project Cost 1350001 $ 767 /Per Kw 103,509,246 Note: Emission offsets, IDC , demolition, switchyard modifications, gas and water supply line, taxes for equipment and material and permits ar a not included. Note: This estimate is based upon Carter & Burgess' experience with projects of similar scope and size. The estimate utilizes actual equipment supplier q uotes and budget estimates. This information is used to factor the total estimate based on histor ical data. The probability of maintaining O O O O O 0 O N O 10A O O C O LOA COD 0 0 O 00 o In p O CD M M M N O 0 Lo O) V' N N „M,L t0 •-� N � � Vi er .69,,� 4> Y p O p O p O O Op 0 0 0 0 0 0 U O N M v t0 N V_ N t0 V• VO. O t Ln M M N 00 O N O � N O O uo) M M MV N n LfDo O V' O M O t0 t0 t0 V' .M-L O f0 C Cq 6, ,y Mq M � 4A fR AA N� N Ll V' 00 Of O MO M Oi O O O N n VM' n .M-i N O v N m M N O O O O O O 0 OOjLr? l0 N O O) Oui ..,L 1-4N t0 y� co N COO p O O� O ff-, N Ln O� fr1 n Ln m 0 et O t0 co c Lo N Ch O N N p f9 M N N N tT V' N O O Lo � N Q OOi M M coo t00 O tOtl O � VN_ OR 00 O N o .a V' � cli C6 It N t0 Cl) CD C.p CD CD O O (R O O CD O O O Lo N to Im C � 00p ci tq NN.L O) N f00 L 61). M 00 N N N N U) cei fR p p O CDO O O p O CD 0 0 0 O O O CDO O CD O O 00 O 00 00 Q0 CD 00 - pp O O O CO V• 0601 %0 M W Ln N V' LL) 00 V' to lA N O .� O+ M 0 M O O to O V- to. Ln Lo Lq U N co an t0 f0 � v_ tp � O Cl) . L M M M O t0 U VI M C6 V' -7 td t, ,4 C6 O � - Ln H An O 0 00 � to N CD 0 Co V, C4 C `1 O M n O fNV Ln OOD OOi OD sO CDO n V 0 fNi� 00 00 N N N N M O� N t0 M O Lo F- W W 0 O O O 0 000 0 O 0 p O o pV� O N 00 O O r 0 W R 0 C L(1 O N O Lt).-� O M 00 M O O O� 00 b9 ff? CD O W N LOA M VN' 10f1 CND_ ^ CMp � O W Q' LL N Ef3 fA ~ E9 .-i fit Oo Ln d O Op b t� O O O O O O O V' _N lOA M Lo LLn N .~-� 00 R n N Ln M O O N N CM M V, t0 � � H M Am ba fA J W O 0 0 0 0 0 0 0 0 0 0 O O Vim' O Q Q p 0 CD O p p p p u)O p o p O N Z 00 EAcq Ltj upi Ovoi OOt 40Ln ti 0O O 00 O rfNO OFF W, (7 NO M4N tC tN0 V' I- cli fq OW N 64Lo �~ b9~ �N in a O N 0000 0 eOe�� LLn O O N - N O M O N e' O N O ON L0 a t0 Lo co CDCMO N N M C C S tM0 O tM0 Lo O co M M M M v LA 01 co v; is O H CD aO O Lo O0 00 O C.J CD Lq O 0 co Lo O N 0 0 O M V' 00 OL Cl) N 0 � 0 N O m M o 0 t0 O N N_ O N O Lo .-f N M T 6 M O 09, 0 O O fA Ot � � V' 0 Lo N O r O! N N N 00 Lo N 'O fh .4 •4 T. Q EAbn tH 64 vq? 4A V) 6q inVi C N H L = e •C V N C O. —qq W N (Oi L O E •~O 9 :� O FA {fl A iLLffil O O d y W0•"� C O 9`° _ {; ti ii i � a0 O E O- =-= i LO i0 i O ip aic� Ll �1O 10 - +mac V' tD r�-+c O y O N- : O O C E O t- LO m '�'O A .n(p *'p 7 m LShIL p Lam. LO m o •- r�O O d yy io '$ o •LO m tao o C yN m 0 0 0 i m S f JF-W 2: CO f f � f-d ��F-W ��F-O �JF-Lr f �H G%67:7 W 5 ly0 � U � N CL G. 'L C O N Y w y co c - a o U co Cl) c r U c to o N O � W Z C Co ATTACHMENT 4 Navigant's Assessment of EPC Proposal gant� CONSULTING, INC. MEMORANDUM DATE: June 18, 2002 TO: Ramon Abueg City of Vernon, California FROM: Max Walenciak SUBJECT: Assessment of EPC Proposal from Scott Co. for the Malburg Generating Project I have completed a preliminary assessment of the Scott Proposal to provide EPC services to the City of Vernon (COV) for the Malburg Generating Station (Project). This assessment was based on a review of their proposal dated April 29, 2002 and as updated with the pricing proposal that reduced the overall cost to $44,985,000. I have not had the opportunity to visit the site, review purchase documents for equipment that COV is supplying or design drawings that Carter -Burgess has developed. In summary it is my opinion that the revised cost offered by Scott is still high by at least $3M, and that this excessive cost is primarily in the areas of "Earthwork and Concrete and "Electrical/I&C". My assessment, at this point in the process, is that it is worth the effort to negotiate with Scott to further reduce the cost. Recently published data for installation of a similar facility indicated that the EPC cost (including major equipment) should be on the order of $600/KW or approximately $80M. This figure would need to be adjusted for site location and conditions, which I estimate at 25% on half of the EPC cost or $10M. Emissions equipment or equipment options could add an additional $5M. In addition, there is a unusual amount of concrete (5600 cy) required for this project that adds an additional $4+M Therefore, my estimate for total project EPC cost for this site would be approximately $100M excluding site cost, transmission, taxes, permits and interconnections. Based on COV equipment purchases of $58M, I estimate that the EPC price would be approximately $42M. The difference between my estimate and Scott's price is small in comparison to total project cost and I would anticipate that Scott would be willing to concede some or all of this price difference. If COV would decide to re -bid the contract, there is no guarantee that the prices would be lower, although the current depressed market could result in a lower price. As mention above, one area of concern is the "Earthwork and Concrete" cost, which Scott estimated at $8.22M, representing 179/6 percent of their total project cost. Their revised price reduces this cost down to close to $7M (assumes $800K of contingency plus $300K for Misc. Sub Work), but this is still very high. This cost is more that double the industry average for this type of work because of the small project site size, location and the seismic requirement that resulting in a large foundation. The "Contractor Contingency" line item seems low, which would indicate that each item in their cost breakdown has contingency. For Earthwork and Concrete, Scott may have assigned higher that normal risk factors (and thus contingency) to account for site conditions. This contingency adder should be negotiable, especially if it was developed early in the design process. I feel that the price savings (through additional negotiations) for this line item should be $1-2M. The Electrical/I&C costs as proposed were $11,496,000 or almost 24% of the proposed total cost. The revised figure would be approximately $10M (reduce by $525K plus contingency of $768K), which is still approximately 20% higher than expected. This added cost could be due to selecting Alstom Power (not competitively bid) to supply the controls or due to a premium from the electric sub (Morrow Meadows), which is a certified as a WBE business or associated with a high contingency. I feel that the price savings (through additional negotiations) for this line item should be $1-2M. As we discussed on Wednesday, having Carter -Burgess do a large amount of engineering followed by a separate EPC contractor can lead to excessive costs due to re -engineering and additional administration. These excessive costs could be on the order of $1-2M. I have not used Scott for services in the past but I have considered them for mechanical work on a large project in Arizona. They have a good reputation for supplying mechanical services. A review of their experience indicates that taking the lead for all trades, as proposed, is not their normal line of business. Scott does not have any recent experience as a lead contractor although they have performed a limited amount in the past. Scott's focus on being a mechanical contractor may be a reason for excessive cost in the "Earthwork and Concrete" and "Electrical/I&C" areas of their proposal. In further discussions with Scott, other than the above economic discussions, I recommend focusing on the control system (setup, checkout, training, service), redundancy, owner approvals, equipment access and isolation, system turn over, steam blows, testing and startup responsibility as these are areas where cost savings might be achieved and also reduce the potential for change orders. It should be noted that the current market for EPC work has fallen off dramatically and this should give COV an advantage with Scott negotiations. We hope this assessment is useful to you. Please contact us with any questions or comments you may have. Cc: Paul Maxwell v •. t Total Total Equipment/Service Supplier/Contractor Oty Committed Expended W W Combustion Gas Turbine ALSTOM Power Inc. 2 27,938,950' 27,921,150 Heat Recovery Steam Generator ALSTOM Power Inc. 2 15,487,660" 9,332,750 Steam Turbine Generator ALSTOM Power Inc. 1 5,842,100"' 959,000 Performance Guarantee for power ALSTOM Power Inc. 1 1,363,000 204,450 output and emission of power block Owner's Engineer for 30% Design Carter & Burgess 1 809,000 809,000 and support of AFC CTG Step Up Transformers Delta Star 2 735,720 729,720'" STG Step Up Transformer and Delta Star 2 828,920 0 Spare Fuel Gas Compressors Gas Packagers 3 526,875 421,500 Continuous Emissions Monitoring CISCO 2 354,100 0 Systems Cooling Tower Marley 1 711,000 112,665" Steam Surface Condenser Holtec 1 624,000vl 243,200 Generator Breakers General Electric 3 113,574 Owners' Engineer for Program and Carter & Burgess 1 3,100,000 870,545 Construction Management Total Committed as of 06/13/02 58,434,899 41,603,980 'Original contract price of $28,200,000 reduced by $278,850 pursuant to change orders. Additional change orders of §15,000 issued for delayed delivery and $2,800 for the seismic redesign. New contract price is $27,938,950. " Additional change orders issued: 1) Spare CO catalyst during commissioning, $308,000; 2) engineering for seismic 4 zoning, $56,750; and 3) additional materials for structures for seismic improvements, $187,910. New total is $15,487,660. iii Change order of $2,100 for seismic redesign increased price to $5,842,100. " 8% tax paid on invoice. Tax not included in the $735,720 price, $6,000 credit applied for early delivery. 8.25% tax included. Cal Board of Equalization # is SRZOHA 30-646-826. V' A change order of $16,000 issued for modifications to meet seismic requirements. CITY COUNCIL LEONIS C. MALBURG Mayor THOMAS A. YBARRA Mayor Pro-Tem WM. 'BILL" DAVIS Councilman H. "LARRY" GONZALES Councilman W. MICHAEL MCCORMICK Councilman BRUCE V. MALKENHORST City Administrator/City Clerk FAX (323) 826-1438 City Council City of Vernon Honorable Members: CITY HALL 4305 SANTA FE AVENUE, VERNON, CALIFORNIA 90058 TELEPHONE (323) 583-8811 August 14, 2002 EDUARDO OLIVO City Attorney FAX: (562) 869-1883 KEVIN WILSON Director of Community Services & Water FAX: (323) 826-1435 KENNETH J. DeDARIO Director of Municipal Utilities FAX: (323) 826-1425 STEVEN E. PARKER Fire Chief FAX: (323) 826-1407 BRUCE W. OLSON Police Chief FAX: (323) 826-1481 h\ �C7 �v. The Director of Utilities is requesting that a contract for Detailed Engineering, Procurement, Construction, and Startup be entered with Scott Company to provide engineering services, equipment purchases, and construction of the Malburg Generating Station Project (MGSP) at an approximate cost of $43.9 million. On July 24, 2002, this legislative body approved the execution of an Interim Letter Agreement to provide engineering design and drawings to support the expedited permitting process at a cost not to exceed $150,000.00 that will be offset against the detailed engineering cost. This has been reviewed by the City Attorney and it is hereby recommended that the contract with Scott Company be approved and executed. Very truly yours, Bruce V. Malkenhorst City Administrator/City Clerk BVM/gm August 14, 2002 TO: Bruce V. Malkenhorst, City Administrator FROM: Kenneth J. DeDario, Director of Utilities Kx9d- SUBJECT: Malburg Generating Station Project I recommend approval of the attached Contract For Detailed Engineering, Procurement, Construction and Startup By And Between The City of Vernon And Scott Company for the Malburg Generating Station Project (MGSP). This Contract provides for engineering services, equipment purchases and construction of the MGSP. The Contract price is $43.9 million. The City Attorney has reviewed the Contract. If you have any questions or comments, please contact me. Thank you or your consideration. KJD:ah Attachment CONTRACT FOR DETAILED ENGINEERING, PROCUREMENT, CONSTRUCTION, and STARTUP FOR THE MALBURG GENERATING STATION PROJECT VERNON, CALIFORNIA August 14, 2002 I EPC Contract_0_8_ 14. doc CONTRACT Table Of Contents Page 1. GENERAL 2 A Scope of Work 2 BDefinitions ......................................................... 2 2. RISK OF LOSS ....................................................... 8 3. CONTRACT PRICE AND PAYMENTS ................. 8 A. Contract Price 8 B. Payment Schedule 8 C. Invoices 9 D Form and Content 10 E. Payment 10 F. Failure to Achieve Progress 10 G. Payments Withheld 10 H. Retainage 11 I. Payments Not Acceptance of Work 11 4 NOTICE TO PROCEED 11 5. CHANGE ORDERS ................................ 11 A. General 11 B. Change Work Authorization 12 C. Unauthorized Changes 12 D. Effect on Schedule and Warranties and Guarantees 12 E. Payment Procedure 12 6. BONDING REQUIREMENTS 13 7. PRE-EXISTING SITE CONDITIONS ..................... 13 8. LAWS AND REGULATIONS ................... 13 9. INSPECTION....................................................... 14 10. FORCE MAJEURE................................................. 14 11. DELAYS/SUSPENSION.......................................... 14 12. WARRANTIES...................................................... 15 A. General 15 B. Warranty Period 15 C. Remedy of Defects 15 D. Survival of Warranties 16 E. Extent of Warranties and Guarantees 16 F. Prevention 16 G. Assignment of Warranties and Guarantees 16 13. INFORMATION FURNISHED TO AND BY THE CITY 16 14. INFORMATION FURNISHED TO CONTRACTOR 16 A. Access to Confidential Information 16 B. No Disclosure 17 C. Court Ordered Disclosure 17 D. Remedies 17 15. TECHNICAL DATA ................................................ 17 16. PATENTS............................................................. 17 17. CANCELLATION/DEFAULT...................................... 18 A. Termination 18 B. Contractor's Breach 18 C. City's Breach 18 18. ASSIGNMENT....................................................... 18 19. PARTIAL INVALIDITY ............................................ 19 20. CHOICE OF LAW ................................................... 19 21. INSTALLATION/FIELD SERVICES ........................... 19 22. INDEMNIFICATION AND INSURANCE ..................... 19 EPCContract 0 8 l4.docEPGGen4r- et 0 8 14. diie PGG ntfae+ n u i doe A. Indemnity B. Insurance 23. NON -WAIVER ....................................................... 24. AMENDMENTS ............................................. 25. ENTIRE AGREEMENT ............................................. 26. BENEFIT OF AGREEMENT ...................................... 27. FORUM SELECTION ............................................... 28. COUNTERPARTS................................................... 29. NOTICES.............................................................. 30. INDEPENDENT CONTRACTOR ................................ 31. CONTRACTOR NOT AGENT .................................... 32. REVIEW OF EXISTING CONDITIONS ...................... A. Premises B. Verification of Existing Conditions C. Statement of Fact 33. SUPERVISION BY CONTRACTOR ............................ A Management of Work B. Control of Work 34. GOVERNMENTAL REGULATIONS AND TAXES ...... A. Permits and Licenses B. Laws and Regulations 35. LIQUIDATED DAMAGES ......................................... A. Delays B. HP Steam Loss C. Liquidated Damage Payment D. Sole Remedy 36. MAXIMUM AGGREGATE LIQUIDATED DAMAGES 37. PERFORMANCE GUARANTEES ............................... A. Performance Guarantees B. Noise Emissions C. Auxiliary Power Limit D. HP and LP Steam line Pressure Loss E. Obligations of the Contractor F. Corrective Action G. Standards for Plan of Corrective Action 38. LIMITATION OF LIABILITY .................................... A. B. 39. DISPUTE RESOLUTION .................................... 40. ENVIRONMENTAL PROTECTION ............................ A. Qualified Personnel B. Material C. Compliance with Laws D. Hazardous Materials Removal E. Environmental Indemnity F. Material Safety Data Sheets G. Suspension and Notification 41. LABOR AND MATERIALS ....................................... A. General B. Employment of Licensed Personnel C. Assignment of Individuals D. Material E. Start up Spare Parts and Special Tools F. Quality Control Program G. Testing H. City's Right to Inspect 19 19 20 20 20 20 20 20 21 21 21 22 22 22 22 22 22 23 23 23 23 24 24 24 24 24 24 24 24 25 25 25 25 25 25 25 25 26 26 26 26 26 26 27 27 27 27 28 28 28 28 28 28 29 29 29 EPCContract 0 8 14.docEPC;C; * t o B i n ,t •• EZ C-C; + t n 8 1 a k APPENDIX Page Appendix 1 Specification for Combined Cycle Power Plant 31 Appendix 2 Project Control Requirements for Contract 32 Appendix 3 Unconditional Waiver & Release Upon Final Payment 36 Appendix 4 Insurance Schedule 40 Appendix 5 Miscellaneous 42 EPCContract 0 8 14.docEPGG + 0 8 1 n J EPCG + t-0-8_1 dee l CONTRACT THIS CONTRACT is made, entered into and executed in duplicate originals, either copy of which may be considered and used as the original hereof for all purposes, as of this -th 2002, in the City of Vernon, County of Los Angeles, BY AND BETWEEN . 101 1 Contractor RECITALS THE CITY OF VERNON 4305 Santa Fe Avenue Vernon, CA 90058 SCOTT COMPANY 14290 South Pedro Gardena, CA 90248 WHEREAS, the City of Vernon ("City") has completed the development of a Combined Cycle Power Plant (hereinafter, the "Project") for purposes of installing additional generating capacity within the City that is capable of yielding cost effective, efficient and reliable electricity to meet its goals, while meeting Federal, State and local environmental and siting requirements; and WHEREAS, City has sought proposals for the detailed engineering, procurement, construction and startup of a combined cycle power plant to create the Project; and WHEREAS, Contractor submitted a proposal to City dated _, _ 2002 for the equipment and services defined herein; and WHEREAS, City's Utilities Department has determined that the construction of the Project and the purchase of the equipment and services from the Contractor will assist City in meeting its electricity goals and is in the public interest; and WHEREAS, Contractor has advised City that it is qualified to perform such services under this Contract NOW, THEREFORE, THE PARTIES HERETO DO MUTUALLY AGREE AS SET FORTH HEREIN: EPCContract 0 8 l4.docEPGC= * t 0 8 14. d EPCC + +_n_u_t doe I 1. GENERAL The Contract shall consist of the following: Purchase Order The terms and conditions as set forth in this Contract Appendix "1" Specification for Combined Cycle Power Plant Appendix "2" Project Control Requirements for Contract Appendix "3" Unconditional Waiver & Release Upon Final Payment Appendix "4" Insurance Schedule Appendix " 5" Miscellaneous All Appendices are attached hereto and incorporated by reference as though fully set forth herein. To the extent that there are any conflicts between the terms of the Appendices and the terms and conditions set forth below, the terms and conditions set forth herein shall prevail. The above order of precedence shall prevail in the event that there is a conflict or inconsistency among the documents that comprise the Contract. A. Scope of Work The Project shall consist of the detailed design and engineering, balance of plant equipment supply, and installation of a "two on one" natural gas fired combined cycle power plant as defined in Appendix 1. B. Definitions AFC Application for Certification to the California Energy Commission AQMD Shall mean the South Coast Air Quality Management District. Beneficial Use Shall mean that the Contractor has completed the Work (including commissioning requirements) and the plant is ready for the Stability and Performance Testing by the City and the City has provided a Notice of Acceptance. Best Efforts Shall mean those efforts which a skilled, competent, experienced, prudent contractor would use to perform the requirements of the Contract in a timely manner exercising the degree of professional skill, care, competence, and prudence customarily imposed on a contractor performing similar services for similar electric utility projects. For the purposes of the Contract, a timely manner shall mean strict adherence to the milestone schedule dates. Business Day Shall refer to normal business days at the City of Vernon, Monday through Thursday, excluding legal holidays. Bid Shall mean the offer or proposal of the Bidder submitted on the prescribed forms setting forth the price or prices for the Work to be performed. EPCContract 0 8 l4.docEPGGePAfaet 0 8 i n d3 EPCG + n 4 i ,a Bidder Shall mean all Parties approved to bid on the RFQ Package as determined by the City. Change Order Shall mean a design or field Change Order or Amendment to this Contract, signed by City's Representative, authorizing an addition, deletion or revision in the Work or an adjustment in the Schedule or any change to the Contract Price resulting therefrom. City Shall mean the City of Vernon, a California Municipal Corporation. City or Owner's Shall mean that individual designated by City, who shall have the Representative responsibility and authority specifically delegated to such individual by City and made known in writing to Contractor. Combined Cycle Power Shall mean the complete Malburg Generating Station units 1,2 & 3 Plant generating units and the auxiliaries and controls as required to produce a complete and operable power station as defined by the Specification, Appendix 1. Contract Shall mean this Contract and all of the Appendices, as such Contract and Appendices now exist and as they may be hereafter amended from time to time. Contract Price Shall mean that price specified in Section 3 of the Contract that is the total amount payable by City to Contractor for the Work to be performed hereunder. Contractor's Project Shall mean that individual designated by Contractor who shall be Manager responsible for the performance of the Work, be authorized to execute Change Orders and to act on behalf of Contractor and its Subcontractors. Commercial Operation Shall mean the successful completion of all Emissions Tests and Performance Tests and acceptance of the Combined Cycle Power Plant for dispatch by the City. Commissioning Shall mean the services and craft work required to check out all mechanical, electrical and control systems and subsystems and declare the System ready for its Stability Test after Mechanical Completion. Contract Documents Shall mean the Purchase Order, the terms and conditions as set forth in this Contract, Appendix 1 Specification for Combined Cycle Power Plant, Appendix 2 Project Control Requirements for Contract, Appendix 3 Unconditional Wavier & Release Upon Final Payment, Appendix 4 Insurance Schedule, and Appendix 5, the Proposal Form EPCContract 0 8 14.docEPGC= + + 0 B i n d8 EPGG + + n Q t d Contract Time Schedule Shall mean the period during which Contractor will be required to deliver, erect, commission, and startup the System under this Contract. Contractor Shall mean Scott Company, (Scott), its legal representatives, successors, and assigns. Contract Drawings Shall mean all drawings, diagrams, illustrations, schedules, and other data which are specifically prepared by or for the Contractor to illustrate some portion of the Work and all illustrations, brochures, standard schedules, prepared by a supplier and submitted by the Contractor to illustrate material or equipment for some portion of the Work. Day Shall mean a calendar day and shall include Saturdays, Sundays and holidays, except that, in the event that an obligation to be performed under this Contract falls due on a Saturday, Sunday or legal holiday in the State of California, the obligation shall be deemed due on the next business day. Defects or Deficiencies Shall mean materials and workmanship that do not conform to Contract Drawings and/or specifications, are of inferior workmanship, or will materially and adversely affect the performance of the Work. Defective Work Shall mean work that is unsatisfactory, damaged, faulty, deficient, does not conform to the Contract, or does not meet the requirements of any inspection, reference standard, test or approval referred to in the Contract. Delaying Event Shall mean a delay in the performance of the Work caused by City or an event of Force Majeure. Emissions Test The purpose of the Emissions Tests will be to demonstrate that the unit meets the emissions guarantees for the specified fuel, i.e. natural gas. The Emissions Tests will also serve as a compliance test to demonstrate that the Combined Cycle Power Plant complies with all guaranteed emissions limits as specified in the BRSG Contract between the City of Vernon and Alstom Power. Engineer or City's Shall mean Carter & Burgess, Inc. Engineer Equal Shall mean equal as determined by the City._ EPCContract 0 8 14.docEPGGeR4r-a t 0 8 i, 4eEPr7GoFAr-ae+ n 4 i d e-- Environmental Law Shall mean any federal, state, regional or local law, regulation, decision of the courts, ordinance, rule, code, order, directive, guidelines, permit or permit condition, currently existing or as amended, enacted, issued or adopted in the future, which relates in any way to worker or workplace safety, environmental conditions, environmental quality or policy, health and/or safety issues or concerns (including product safety). Environmental Law includes, without limitation, the Comprehensive Environmental Response, Compensation and Liability Act of 1980, as amended (42 USC, Section 9601 et. seq.), the Resource Conservation and Recovery Act (42 USC, Section 6901 et. seq.), the Carpenter -Presley -Tanner Hazardous Substance Account Act (California Health & Safety Code, Section 25300 et. seq.), the California Hazardous Waste Control Law (California Health & Safety Code, Section 25100 et. seq.), the Occupational Safety and Health Act (29 USC § 651 et. seq.), the California Occupational Safety and Health Act (California Labor Code § 6300 et. seq.), and any regulations or rules promulgated thereunder. Final Payment Shall mean the last payment of the remaining Retainage after the Contractor has fulfilled all the obligations defined in this Contract. FOB Jobsite Shall mean when the conveyance has stopped next to the off-loading area at the Jobsite. Force Majeure Shall have the meaning set forth in Section 10 herein. Jobsite Shall mean the location of Station A at 2715 East 50th Street, Vernon, CA 90058. Generating Hours Shall mean operating the Combined Cycle Power Plant to generate electricity electrical grid from minimum to maximum load as defined in Appendix 1, Part 1. Government Agency Shall mean any federal, state or local government agency or other public body having the mandate, authority or power to implement, coordinate, administer or enforce an Environmental Law. Governmental Rules Shall mean all laws, regulations, orders, decrees, conditions of any franchise, license, permit or other authorization issued by a governmental authority, and decisions of courts and governmental agencies. EPCContract 0 8 14.docEPCG + + 0 8 i n d6 UGG + + 0 Q 13 ,a Hazardous Materials Shall mean any chemical, substance, material, controlled substance, object, conditions, solid or hazardous waste or combination thereof which is or may be, hazardous to human health or safety or the environment due to its radioactivity, ignitability, corrosivity, reactivity, toxicity, or other harmful or potentially harmful properties or effects. Hazardous Material include, without limitation, oil or petroleum and petroleum products, asbestos and any asbestos containing materials, radon, polychlorinated biphenyls (PCBs), urea formaldehyde insulation, lead paints and coatings, and all of those chemicals, substances, materials, controlled substances, objects, conditions and waste or combinations thereof which are now or become in the future listed, defined or regulated in any manner by any federal, state or local Environmental Law. Laws and Regulations; Shall mean laws, rules, regulations, ordinances, codes, and/or Laws or Regulations orders defined in the AFC. Material Shall mean all materials, machinery, equipment, construction equipment, supplies, and items, as described in the Contract and necessary to successfully complete the Work described in the Contract Documents. Mechanical Completion Shall mean the date defined in Section 3 when the Contractor has completed the installation and the System is ready for Commissioning. Mobilization Shall mean the date defined in the Contract that the Contractor can commence Work on the Jobsite. Notice to Proceed Shall mean the written notice to be issued by City to Contractor, directing the commencement of the Work or portion of the Work. Notice of Acceptance Shall mean written notification provided by the City defining the completion of the Work or portion of the Work Owner Shall mean the City of Vernon. Parties Shall mean Contractor and City collectively. The Parties may at times herein be referred to individually as Party. Payment Application Shall mean the written explanation of the Contractor's request for monthly payment for reimbursement based on quantities installed multiplied by the unit installation prices plus material quantities and equipment delivered to the Jobsite or adjacent laydown area. Performance Test Shall mean the testing of the Combined Cycle Power Plant to verify that the guaranteed performance values are met as defined in the Specification. EPCContract 0 8 14.docEPCGo~ r-aet 0 8 i n a6eEPGG r+Faet n 4 i doe Performance Guarantees Shall mean the Performance Guarantees set forth in Section 37 of this Contract. Purchase Order Shall mean the standard purchase order that is issued by the City. Retainage Shall mean the withholding of payment by City as set forth in Section 3H of this Contract. RFQ Package Shall mean the City furnished bid documents, including applicable specifications, drawings, data sheets, and sample contract. Schedule Shall mean the Construction Execution Plan Schedule of key dates and milestones for the timely completion of the Work. Services Shall mean all related work to be supplied by Contractor, including furnishing of necessary equipment, craft labor, supervision, startup labor, vendor technical support (for Contractor furnished equipment) and required management, as described in the Contract and necessary to successfully complete the Work described in the Contract. Specification Shall mean the scope of work and the documents included and referenced in Appendix 1 to this Contract including Part IJechnical Specification, Part 2-Erection Requirements and Part 3-Technical Attachments. Stability Test Shall mean a test that is conducted after Commissioning is completed in order to verify that the Combined Cycle Power Plant can operate in a stable condition at various loads within the conditions specified in the operating manuals over a 24 hour period. When the Stability Test has been completed successfully, the plant shall be deemed ready for Performance Testing. Subcontractor Shall mean any person, firm, or corporation that provides under contract with Contractor the design engineering, construction, equipment, labor and materials for some part of Contractor's obligation under the terms of this Contract. System Shall mean the Combined Cycle Power Plant. Underground Facilities Shall mean all pipeline, conduits, ducts, cables, wires, manholes, vaults, tanks, or other such facilities or attachments, and any encasements containing such facilities that have been installed or are existing underground to furnish any of the following services or materials: electricity, gases, steam, liquid petroleum products, telephone, cable television, computer or control data, sewage, drainage, traffic, control systems, or water. EPCContract 0 8 14.docEPCG t 0 8 i n d6I EPCG t n u i a A Witness Points Shall mean a test or inspection point during manufacturing for which City indicates a desire to witness. Work The Work shall include all of the home -office, on -site related engineering, design, supervision, labor, Contractor equipment, construction equipment, tools, fabrication, materials, startup, Commissioning as required in the Contract and required to provide City with a functioning System. 2. RISK OF LOSS Title and risk of loss or damage shall pass to the City and shall be deemed to be complete upon Beneficial Use. 3. CONTRACT PRICE AND PAYMENTS A. Contract Price City shall pay Contractor the Contract Price of Forty Three Million Nine Hundred Thousand and 00/100 Dollars ($43,900,000.00) for the Work to be performed by Contractor under this Contract. Contractor shall not be entitled to payment exceeding the Contract Price, except to the extent that the Contract Price may be changed in accordance with the terms of this Contract. Prices shall not include sales, or use taxes, special financing fees or value-added taxes, the City shall either pay any and all such applicable charges or provide Contractor with acceptable exemption certificates. B. Payment Schedule Contractor and City shall mutually agree to an earned installed quantity Payment Application. Payment will be made in accordance with the agreed -upon monthly -earned progress less five percent (5%) retention (the "Retainage") until Commercial Operation and receipt of as -built data. Payments will also be paid in accordance with the Payment Application in Appendix 2 Commencement and Completion of Workset forth below. The Engineer will perform a quantity validation to approve the Pay ApplicationPayment Application. Neither the final certificate nor final payment shall relieve the Contractor from responsibility for defects in design, materials and workmanship. Five percent (5%) retention will be withheld until the progress or the project reaches fifty percent (50%) complete. All subsequent invoices rendered shall be paid net with no retention. EPCContract 0 8 14.docEPCG + + 0 8 i n d8 RPGG + + n u i 3 a • A SCHEDULE DATES SUBJECT TO AFC APPROVAL Estimated Award Date August 21, 2002 Mobilization October 15, 2002 Estimated Contractor to Start Onsite Construction December 3, 2002 Estimated Combustion Turbine Unit 1 Mechanical Installation Complete July 20, 2003 Estimated Steam Turbine Unit 3 mechanically Complete August 8, 2003 Estimated Combustion Turbine Unit 2 Mechanical Installation Complete August 15, 2003 Estimated HRSG Unit 1 Hydrostatic test Complete September 8, 2003 Estimated HRSG Unit 2 Hydrostatic Test Complete October 8, 2003 Mechanical Completion November 30, 2003 Beneficial Use March 26, 2004 Completion of the Performance Test Aril 2, 2004 Commercial Operation Aril 12, 2004 Payment Application Date Milestone Description 1. 8/21 /02 Contract Award 2. 12/03/02 On Site Mobilization 3. 12/31/02 Engineering, Submittals, Procurement of balance of Plant 4. 08/01/03 Erection of HRSG #1 Modules 5. 09/15/03 Erection of HRSG #2 Modules 6. 07/20/03 Erection of CTG #1 7. 8/15/03 Erection of CTG #2 8. 8/08/03 Erection of ST #3 9. 11/08/03 Hydrotest of Power Train #1 10. 11/22/03 Hydrotest of Power Train #2 11. 11/30/03 Completion of Mechanical Work 12. 03/26/04 Beneficial Use Contract Percentage 10%* 10%* 10% 15% 15% 10% 10% 8% 2% 3% 4% 3%* All payments except those identified with an asterisk will be reviewed and approved by the City based on quantities installed and or deliveries as defined in the Schedule. C. Invoices Contractor shall submit an invoice to City on a monthly basis based on progress agreed to herein. Contractor shall not include progress payments made to Subcontractors of material or equipment during its manufacture thereof. The adjacent laydown area and Contractor's Gardena facility can be considered part of the project site for partial payments for delivery; however, the risk of loss shall be determined by Section 2 of this Contract. EPCContract 0 8 14.docEPGG + + 0 8 i n as EKG t + n Q i 3.d r D. Form and Content Contractor shall provide adequate documentation to City's Representative to support its invoice for purposes of confirming the accuracy of the invoice. E. Payment Payment will be due net 30 days after City's receipt of Contractor's invoice. F. Failure to Achieve Progress In the event City, in its sole discretion, elects to pay all or any portion of any such payment, notwithstanding Contractor's failure to make progress pursuant to Schedule, such payment shall not be deemed a waiver by City of the requirement for timely completion of said progress, or of City's right to withhold future progress payments pending completion of the progress required. G. Payments Withheld City may withhold payment and shall withhold payment to the extent indicated by the City's Representative to be necessary to protect City from loss because of: (a) any defective Work not remedied whether or not payment has been made therefore; (b) any claim of lien or stop notice has been filed or recorded, or City has received notice that a claim of lien or stop notice maybe filed or recorded, regarding; (c) any damage caused by the Contractor, its Subcontractors or agents to the City, its employees, officers or agents while "Contractor is performing its duties under this Contract; (d) any claim by a Subcontractor that it has not been paid any amount due and owing from Contractor (e) Contractor fails to pay, when due, any amount of principal or interest or is otherwise in breach of any agreement in respect to any of its indebtedness or guarantee of indebtedness; fails to pay its debts as they come due; becomes insolvent; makes an assignment for the benefit of creditors; files a petition, or becomes the subject of a petition filed against it, in any bankruptcy, insolvency or similar proceeding; or one or more final judgments are entered against it in the aggregate amount in excess of Ten Million Dollars and 00/100 ($10,000,000.00) and the same shall remain un-discharged and un-stayed for sixty (60) days; (f) reasonable evidence that the Work cannot be completed as required by the Contract; (g) failure to carry out the Work in accordance with the Contract; or (h) the amount of any exception taken by the City as a result of a progress quantity audit. EPCContract 0 8 14.docEPGG + 0 8 14. dAEPGG + +_0_8_i 7 doe I H. Retainage City may apply the Retainage and other amounts withheld against amounts owed to City by Contractor under this Contract, or payable by the City to third Parties by reason of the Contractor's breach of any of its obligations under this Contract, and shall pay the remainder with the Final Payment. Payment shall be made in accordance with the agreed upon progress less five percent (5%) retention of the gross billing each month until the progress or the project reaches fifty percent (50%) completion which amount shall be due and payable to Contractor upon the successful completion of the Performance Test and delivery to City of the as -built data and drawings required by the Contract. All subsequent invoices rendered shall be paid net with no retention. Upon successful completion of the Performance Test, or in the event the Performance Test has not been conducted within the time period set forth herein, or in the event City elects not to run the Performance Test for causes not due to Contractor, Contractor shall submit the following: (i) the as -built drawings and other documents required under Appendix 1, Specification and (ii) data establishing payment or satisfaction of all obligations, including without limitation, releases and waivers of liens and assignment of warranties and consents to assignment of warranties, arising out of this Contract. I. Payments not Acceptance of Work No payment made hereunder shall be considered as approval or acceptance of any Work by City. Payment of Applications for Payment shall be subject to correction or adjustment by City in subsequent payments of invoices submitted by Contractor. 4. NOTICE TO PROCEED The City shall provide written notice to the Contractor, directing the commencement of the engineering and or construction of the Work or portion of the Work as necessary. Contractor shall not perform any portion of the requirements of this Contract without written Notice to Proceed from City. 5. CHANGE ORDERS A. General Only City may issue a request for Change Order under this Contract. Such request shall be by written notification to Contractor. As soon as practicable after receipt of the notice, Contractor shall prepare and forward to City, in writing, the price for the change or extra Work in accordance with the requirements of this Section and any required adjustment to the Schedule. Except for minor modifications to the Work, not involving extra cost and consistent with the purposes of the Work, and except in an emergency endangering life or property, no extra work or change shall be performed unless a written Change Order from the City authorizes the extra work or change. x B. Change Work Authorization Should the City authorize a Change Order, Contractor shall furnish the necessary labor with requisite equipment and small tools, and/or materials required for performing such additional work. All authorized changes and the agreed to price shall be confirmed and directed through a Change Order. The price shall include all costs associated with performing the Change Order, including the impact on the Schedule for the original Work, inefficiencies and overhead created by the Change Order. All Change Orders shall be performed under the terms and conditions of this Contract. All Change Orders shall be signed by both City's Representative and Contractor's Representative before Contractor begins work on the Change Order. The total dollar value for any individual Change Order shall not exceed Twenty Thousand Dollars and 00/100 ($20,000.00) under any condition. This dollar limitation shall not be circumvented by the issuance of more than one Change Order for a specified change or extra work. Any changes that may exceed this amount, if any, must be agreed to by an Amendment to this Contract. C. Unauthorized Changes Contractor hereby expressly waives any compensation for any changes to the Work or any extra work that is performed by Contractor if such changes or extra work is unauthorized by an executed Change Order. No compensation for labor or schedule impacts from such unauthorized work shall be considered. D. Effect on Schedule and Warranties and Guarantees Contractor shall have seven (7) days after receipt of a Change Order request to notify City in writing that the change requested will have an adverse effect on Contractor's ability to meet the scheduled date for Beneficial Use, or upon any of Contractor's warranties or guarantees under this Contract. Such notice shall provide a detailed statement of the reasons for and the extent of any such effect. City shall have seven (7) days in which to respond to such notice. If City agrees with the representations in Contractor's notice, the date of Beneficial Use and/ or the warranties or guarantees shall be changed as appropriate. Unless directed otherwise by City, Contractor shall proceed with the Work during the exchange of notices described in this Section. E. Payment Procedure As a condition precedent to the right to receive any compensation for changes or extra work pursuant to a Change Order, Contractor shall furnish to the City an itemized bill of the cost of such work and, unless it is so received, the claim for said additional work shall be deemed waived by Contractor. The total of the itemized Change Order shall be entered on Contractor's monthly invoice, properly identified under the designated numbered Change Order, and payment shall be made in accordance with this Contract. EPCContract 0 8 14.docCCent-r-aet 0 8 14.d&EPC 4:a�n8-1 ao� 6. BONDING REQUIREMENTS Contractor shall, upon execution of the Contract and before beginning Work, furnish an executed Performance Bond and a Labor and Materials Payment Bond each for one hundred percent (100%) of the Contract Price with a corporate surety, guaranteeing the Work will be done according to the Work and Specifications, and further, that Contractor will rebuild, repair, or replace any or all items which have proven defective due to unsatisfactory material and/or workmanship; or due to failure to meet the conditions, requirements and/or specific guarantees noted in the referenced Specifications. Such bonds shall be written with a qualified surety company licensed to do business in California and listed in current U.S. Treasury Form 370 and with Best Rating of "A" or better. Such bonds shall be effective for a period extending to one (1) year from the date of acceptance of the Work by City. Contractor will supply a bond on and subject to the terms and conditions of Standard AIA Form 312. Contractors Bond excludes any liability by Surety for Performance Guarantees. 7. PRE-EXISTING JOBSITE CONDITIONS Nothing herein shall be interpreted as placing any responsibility or liability on: (a) Contractor for pre-existing Jobsite conditions related to pollution, contamination, hazardous waste, asbestos or toxic materials or for the generation, emission or disposal of such substances; or (b) City for pollution, contamination, hazardous waste, asbestos or toxic material introduced to the Jobsite by Contractor including the generation, emission, or disposal of such Contractor introduced substances. City shall indemnify, defend and hold harmless Contractor against any and all claims or liabilities based on the conditions identified in paragraph (a) above. Contractor shall indemnify, defend and hold harmless City, its officers, employees and agents against any and all claims or liabilities based on the conditions identified in paragraph b. above. 8. LAWS AND REGULATIONS Contractor agrees to comply with all federal, state and local laws that apply to Contractor as a supplier to City under this Contract. All laws, regulations and design codes expressly incorporated herein shall be those in effect on the effective date of this Contract. In the event of any subsequent revisions or changes thereto, except in connection with the business activities of Contractor or its Subcontractors or agents, Contractor assumes no responsibility for compliance therewith unless an appropriate Change Order is issued. Nothing contained herein shall be construed as imposing responsibility or liability upon Contractor for the obtaining of permits, licenses or approvals from any environmental, siting or public utility authority or other agency required in connection with the supply, erection or operation of the System, except business licenses, building permits, transit waivers, and/or contractor's licenses as may be required in the name of Contractor or its Subcontractors to support its business activities. EPCContract 0 8 14.docEPGCe +, aet 0 8 14 ,a&r.. PC-C ntf, .+ n Q i 9. INSPECTION Contractor shall provide City reasonable escorted access to Contractor's manufacturing facilities, after receipt of reasonable notice, for the purposes of inspecting the Work and witnessing any tests prearranged to be witnessed and required by this Contract. Neither completion of manufacturing nor shipment of any part will be delayed to accommodate such inspection or witnessing. For agreed Witness Points, Contractor will provide at least twenty-one (21) days advance notice. If Contractor does not receive written confirmation that City will attend, or if City fails to appear at the time of the test/inspection mentioned in the notification, Contractor shall proceed with the Work. Contractor shall provide City a schedule of potential Witness Points within thirty days of execution of this Contract. Within two weeks of receipt of the schedule, City will provide Contractor with an initial indication of potential Witness Points it may wish to witness. 10. FORCE MAJEURE Neither Contractor nor City shall be considered to be in default with respect to any of their obligations under this Contract when a failure of performance shall be due to an uncontrollable force. The term "uncontrollable force" shall mean any cause beyond the control of the Party affected, including, but not restricted to, flood, earthquake, storm, fire, lightning, epidemic, war, terrorist action, riot, civil disturbance or disobedience, sabotage, federal, state, or municipal action, statute, ordinance, or regulation, embargoes of the United States Government or any other government, which by exercise of due diligence such Party could not reasonably have been expected to avoid and by exercise of due diligence has been unable to overcome. Either Party rendered unable to fulfill any of its obligations under this Contract by reason of an uncontrollable force, shall give written notice within five Business Days of such fact to the other Party and shall exercise due diligence to remove such inability with all reasonable dispatch. The City shall pay the Contractor for earned progress up to the force maj eure event. 11. DELAYS/SUSPENSION In the event of any delay attributable to City, its subcontractors or agents that negatively affects the Contract Time Schedule, Contractor shall be entitled to an equitable adjustment of the Schedule dates defined in Section 3B and the consequences thereof and reimbursement of all impact costs. EPCContract 0 8 14.docEPCGentfaet 0 8 1 n d tEPGr + n y a 12. WARRANTIES A. General Contractor represents and warrants that: (a) Contractor is fully experienced and properly licensed, equipped, organized, financed and qualified to perform the Work pursuant to this Contract. (b) Contractor will design, engineer, construct, install, equip, start-up, and complete the Work in accordance with the requirements of this Contract, including the requirements, codes, standards and regulations specified in the Specification. the Work will be designed, engineered, constructed, installed, equipped, started up, and completed in accordance with sound, generally accepted and the best trade engineering and construction practices and in compliance with all applicable requirements of federal, state or local laws, codes and regulations governing the construction and operation of the Work. The Work will be uniformly new, of good quality and free from fault or defects in material, workmanship or performance, and all Work, including substitutions not so conforming to these standards may, at the option of City be considered defective and the Material and Work shall be fit for its intended purposes as exhibited by the Performance Guarantees and shall conform to the requirements of this Contract. B. Warranty Period The warranty period shall be eighteen (18) months from the date of Beneficial Use by the City or eight thousand (8,000) station Generating Hours which ever comes first. The warranty period for deficiencies under paragraph A above, shall be one (1) year from the date of correction of the deficiency or eighteen (18) months after Beneficial Use by City, whichever occurs first. Contractor procured equipment will carry a one year warranty from date of Beneficial Use by City or eighteen (18) months from date of shipment, documented by formal shipping documents, whichever comes first. C. Remedy of Defects If City or City's Representative notifies Contractor of any deficiencies under this Section discovered in the Work during the warranty period as defined herein, whether such Work has been performed, fabricated, installed, tested, completed or accepted, Contractor shall promptly replace, repair or re -perform the Work to conform to the requirements of this Contract, all at Contractor's expense, including repairs to other parts of the Work, or other property damaged as a result of such deficiencies or corrective actions, and including the costs of City's Representative or any outside consulting services thereby made necessary. Contractor shall also perform such tests as City may reasonably request to verify that such correction, replacement, repair, re -performance or rework complies with the requirements of this Contract. Contractor shall perform its warranty obligations hereunder as expeditiously as possible and shall in every case commence the necessary corrections, repairs, replacements, performance and tests within seven days of written notice to Contractor. In the event Contractor fails to commence such performance within such seven (7) day period, City may perform or cause to be performed the same, all at Contractor's expense. ens.�•��...�,...��.+r�ri��aeaan�ssa�� D. Survival of Warranties All representations, covenants, and warranties in this Section shall: (a) survive any inspection and acceptance of the Work and continue for the warranty period in Section 12B; (b) be extended for one (1) day for each day that Contractor is unable to achieve Beneficial Use in accordance with the Specification due to a breach of Contractor's warranties; and (c) shall continue in respect of any defect notice of which has been given by the City to Contractor prior to the date on which the warranty period in Section 12B would have expired but for this provision for the extension thereof in respect of such defects. E. Extent of Warranties and Guarantees Contractor's warranties and guarantees under this Section do not extend to any repairs, adjustments, alterations, replacements or maintenance which may be required to the Work as a result of normal corrosion, normal erosion or normal wear -and- tear in the operation of the Work. F. Prevention Contractor agrees not to file or otherwise assert, suffer or permit a mechanic's lien to be filed or continued against any property of City for services or Work performed or Material, furnished in connection with the Work by Contractor. G. Assignment of Warranties and Guarantees On the date of the Notice of Acceptance of the Work after Commercial Operation, Contractor shall assign, by executing a document or documents, all warranties and guarantees that it procures from third parties on product incorporated into its Work, which, upon such assignment shall be valid, and Contractor shall obtain from all such third parties consents to such assignment. Contractor shall enforce all such warranties and guarantees on behalf of City during the warranty period and shall provide City with all reasonable assistance in the enforcement of such warranties and guarantees whether or not such enforcement occurs during the warranty period. 13. INFORMATION FURNISHED TO AND BY CITY Not used 14. INFORMATION FURNISHED TO CONTRACTOR A. Access to Confidential Information. City may provide Contractor with, or allow Contractor access to certain information not available to the public concerning City, or businesses located in the City or City's vendors. The information may include company information, taxes, sales, value of assets, or other such information. All such information shall be known as "Confidential Information" and shall be marked clearly as "Confidential Information". EPCContract 0 8 14.docEPGGe„,r- 4 0 8 i "EPGG,,,,+.aet n 7 doe B. No Disclosure. Except as expressly permitted, Contractor shall not disclose, permit the disclosure of, release, disseminate, or transfer, whether orally or by any other means, any part of such confidential information to any other person or entity, whether corporate, governmental, or individual, without the express prior written consent of an authorized representative of City. Contractor shall return any written Confidential Information and all copies made of such items to City upon City's written request, but in any event not later than the date that Contractor has performed all services to be performed pursuant to this Contract. Contractor hereby agrees that such confidential information and any documents provided may be used by Contractor only as authorized by City. Contractor shall take reasonable measures to avoid any disclosure of any such confidential information to any unauthorized person. C. Court Ordered Disclosure. Contractor shall immediately notify City of any court order or subpoena requiring disclosure of confidential information, and shall cooperate with the City's legal counsel in the appeal or challenge of any such order or subpoena. Recipient may only disclose confidential information required to be disclosed pursuant to court order or subpoena after legal counsel has exhausted any lawful and timely appeal or challenge. D. Remedies. In addition to any other remedies that it may have at law or in equity, City shall be entitled to a temporary and permanent injunction by a court of competent jurisdiction against any breach or threatened breach of the confidential information provisions of this Contract. Contractor acknowledges that in case of such breach or threatened breach of said provisions, City would have no adequate remedy at law. 15. TECHNICAL DATA All operating or other performance information and data under this Contract are based on the conditions specified in the attached Appendices. Contractor's sole liability in respect to performance of the Work shall be only as expressly stated in the attached Appendices, or as set forth herein. 16. PATENTS Contractor shall defend, indemnify and hold City and its officers, employees and agents free and harmless from any claim, litigation or other judicial or administrative proceeding the basis of which is that the Work supplied hereunder infringes on a U.S. apparatus patent issued prior to the date of this Contract other than those arising out of (a) Material supplied according to City's detailed design; (b) modifications, alterations, additions or changes made by City to the Work or to Material supplied by Contractor, (c) the use of the Work or Material supplied hereunder in conjunction with any other process or Material not supplied by Contractor, or (d) claims covering a process performed or a product produced by said Work. City will notify Contractor in writing within a reasonable period of time of such claim. Contractor shall have control over the defense and/or settlement of such claim and reasonably required assistance in said defense. EPCContract 0 8 14.docEPGGoPAfaet 0 8 1 n ,ai ZEPGG r,, aet n u t doe If the Work is determined to infringe on a patent, or in Contractor's reasonable opinion may infringe on a patent, Contractor will, at its option and expense, either (i) procure for City the right to continue using said Work or part thereof, (ii) modify it so it becomes non -infringing Work, (iii) replace it with substantially equivalent non -infringing Work. 17. CANCELLATION/ DEFAULT A. Termination. Any order or contract may be terminated by City for its convenience upon fifteen (15) days prior written notice and upon payment of reasonable and proper termination charges, including, but not limited to, all costs incurred or committed prior to the effective date of notice of termination and all charges incurred by Contractor in connection with the termination, plus reasonable overhead and profit. B. Contractor's Breach In the event Contractor commits a breach of a material condition of this Contract, City shall notify the Contractor in writing of said breach and if Contractor has not cured or begun reasonable efforts to cure after 15 working days of receipt of said notice, and fails to diligently pursue corrective action, then City shall have the right to cancel this Contract. The City may: 1) proceed against the Contractor's Bond in accordance with the terms and conditions of the Bond or, 2) deviate from the terms and conditions of the Bond, thereby waiving its right to make claim against the Contractor's Bond; the City may then pursue whatever other remedies it may have under the law against Contractor.. Contractor shall be responsible for any direct costs due to City's re -procurement of the equivalent of the Work or services cancelled from Contractor. Among other things, Contractor shall be deemed to be in default under this Contract if Contractor files for bankruptcy or another person or entity institutes against Contractor a bankruptcy, reorganization, moratorium, liquidation or similar insolvency proceeding or other relief under any bankruptcy or insolvency law affecting creditor's rights or a petition is presented or instituted for its winding -up or liquidation. C. City's Breach If City fails to make any contractual payment to Contractor when due under the provisions of this Contract, and such failure is not remedied within fifteen (15) days of City's receipt of written notice of such default, then Contractor will notify City. If such failure is not remedied within seven (7) days of City's receipt of the second notice then Contractor may terminate this Contract for City's default. 18. ASSIGNMENT Contractor may not directly or indirectly sell, assign, transfer, pledge, mortgage or encumber (each, a "Transfer") any of its interest in any of its rights or obligations under this Contract, without the prior written consent of City. Any Transfer that is made without the prior written consent of City shall be void. EPCContract 0 8 14.docEPGG + 0 8 ! n ,r, EPGG +_0_8_13x ,a 19. PARTIAL INVALIDITY Wherever possible, each provision hereof will be interpreted in such manner as to be effective and valid under applicable law, but in case any one or more of the provisions contained herein will, for any reason, be held to be invalid, illegal or unenforceable in any respect, such provision will be ineffective to the extent, but only to the extent, of such invalidity, illegality or unenforceability without invalidating the remainder of such invalid provision or provisions or any other provision hereof, unless such a construction would be unreasonable or contrary to the intent of the Parties as expressed in this Contract. 20. CHOICE OF LAW The rights and remedies of the Parties hereunder shall be governed by the laws of the State of California. 21. INSTALLATIONXIELD SERVICES Unless specifically excluded, all field services required by the Work shall be completed by the Contractor. 22. INDEMNIFICATION AND INSURANCE A. Indemnity Contractor shall indemnify, hold harmless and defend City, its officers, employees and agents from and against any claims, demands, suits, proceedings, liabilities, judgments, awards, losses, damages, costs or expenses (including reasonable attomey's) whatsoever arising out of and caused or occasioned by any negligent act or omission of Contractor, or any of its officers, directors, agents or employees, contractors or Subcontractors in connection with the per- formance of the Work under or in connection with this Contract. In the event that any losses arise, directly or indirectly, in whole or in part, out of the joint or concurrent negligence of both Parties and their respective representatives, each Party's liability therefore shall be limited to such Party's proportionate degree of fault. B. Insurance Prior to commencing Work hereunder, Contractor shall provide City with proof of insurance providing and maintaining the coverage's and endorsements set forth in the Insurance Schedule attached hereto as Appendix 4, Insurance Schedule, and made a part hereof by reference. Said proof of insurance shall also provide that said policy or policies shall not be canceled or materially reduced in coverage without giving at least 30 days prior written notice to City. Contractor shall not permit a Subcontractor or vendor to perform work on City premises unless and until proof of insurance is obtained showing that such Subcontractor or vendor has worker's compensation coverage. If Contractor employs Subcontractors as part of the services rendered, Contractor's protective coverage is required. Contractor may include all Subcontractors as insureds under its own EPCContract 0 8 14.docEPG nt t 0 8 i ,a&EPGG + t o Q 1 ,a policy or shall furnish separate insurance for each Subcontractor, meeting the requirements set forth herein. 23. NON -WAIVER The failure of either Party to insist upon or enforce, in any instance, strict performance by the other Party of any provision of this Contract or to exercise any right herein conferred shall not be construed as a waiver or relinquishment to any extent of its right to assert or rely upon any such provision or rights on any future occasion. 24. AMENDMENTS This Contract may be modified or amended only by a written document executed by both Contractor and City. 25. ENTIRE AGREEMENT This Contract is the entire agreement of the Parties. Contractor represents that in entering into this Contract, it has not relied on any previous representations or understandings of any kind or nature. 26. BENEFIT OF AGREEMENT This Contract shall bind and benefit the Parties hereto and their heirs, successors, and permitted assigns. 27. FORUM SELECTION Any action brought relating to this Contract shall be brought and held exclusively in a State Court in the County of Los Angeles, California. 28. COUNTERPARTS This Contract may be executed simultaneously in two or more counterparts, each of which shall be deemed to be an original, but all of which together shall constitute one and the same instrument. EPCContract 0 8 l4.docEPCC' t o 8 i n ,r&EPCG + t_n_8_l a 29. NOTICES Notices to the Parties, unless otherwise requested in writing, shall be sent to: City: THE CITY OF VERNON ATTN: BRUCE V. MALKENHORST CITY ADMMSTRATOR 4305 SANTA FE AVENUE VERNON, CA 90058-0805 CONTRACTOR: SCOTT COMPANY ATTN: STEVE KLAUS 14920 SOUTH PEDRO GARDENA CA, 90248-2036 Notices shall be deemed to have been received by the close of Business Day two days after the date on which it was mailed. 30. INDEPENDENT CONTRACTOR At all times during the term of this Contract, Contractor shall be an independent contractor and shall not be an employee of City. City shall have the right to control Contractor only insofar as the results of Contractor's services rendered pursuant to this Contract; however, City shall not have the right to control the means by which Contractor accomplishes services rendered pursuant to the Contract except to the extent that such services involve the use of City property or Confidential Information. 31. CONTRACTOR NOT AGENT Except as City may specify in writing, Contractor shall have no authority, express or implied, to act on behalf of City in any capacity whatsoever as an agent. Contractor shall have no authority, expressed or implied, pursuant to this Contract to bind City to any obligation whatsoever. EPCContract 0 8 14.docEPCX + t 0 8 i n M EPCG +_n_u_i a 32. REVIEW OF EXISTING CONDITIONS A. Premises Contractor represents that (i) it has relied upon its own examination of the area on which the Work is to be performed, the adjacent premises and the site, (ii) it knows the applicable federal, state and local laws, ordinances and regulations in existence as of the effective date of this Contract, and (iii) it assumes responsibility therefore. Contractor knows, or shall be deemed to have known, the facilities or lack thereof for delivering, handling and storing materials, equipment on and near the site and the applicable labor conditions. Contractor represents and warrants that all such matters are acceptable and will not interfere with the timely performance of its Work under this Contract. B. Verification of Existing Conditions Contractor represents that (i) it has reviewed the site survey and site proposal drawings and other data concerning the Work included in the Specification, (ii) Contractor has determined and verified all materials, field measurements and field construction criteria related thereto, and it has checked and coordinated the information contained within such submittals with the requirements of the Work and this Contract. To the extent that such drawings and data are made available to Contractor and Contractor is provided an opportunity to determine and verify such information, Contractor shall be responsible for all defects and discrepancies in such drawings and data as if Contractor itself had prepared such drawings and data. The Contractor may rely on information supplied by the City to the extent that it cannot be verified by reasonable survey and inspection. C. Statements of Fact Contractor statements of fact contained in Contractor's submissions in response to, and reply to inquiries made in connection with the Specification are true, correct and complete. No submission or reply made by or on behalf of Contractor in connection therewith contains any material misstatement of fact or omits to state any material fact necessary to make the statements made in connection therewith, in light of the circumstances in which they were made. 33. SUPERVISION BY CONTRACTOR A. Management of Work Contractor shall assign each key officer and employee named on its Management Plan (the "Plan") per the Specification to be responsible for the Material, and construction tasks for which the Plan indicates that such key officer and employee will be responsible. No key officer or employer will be permitted to delegate or transfer its responsibility for any task for which the Plan indicates he or she is responsible without cause or the prior consent of City. The Plan shall be submitted to City thirty (30) days following the Contract award. The Plan will consist of a detailed construction execution write-up of all major schedule activities, rigging requirements, working hours and days, means and methods of erection and EPCContract 0 8 14.docEP et-0-8 14.dQEP G t + n u y ,a installation, and a discussion of how the critical path items will be achieved and maintained. The Plan will include a detailed Primavera CPM schedule which will be manpower loaded by craft and also cost loaded with Contractor's budget to produce craft and total job manpower curves, overall project progress curve, and a total project cash flow curve. The Plan must include sample reports showing an itemized schedule of commodity units, estimated hours of installation, a column for actual manhours for monthly reports, estimated and actual cost of installation by each unit category, earned value percent complete column for the period and cumulative column, plus bottom line percent complete for the total job. The percent complete will be based on quantities installed in place, which will be included in the monthly Payment Application. The Plan must show how the bulk materials and process equipment will be tracked from shop to site with expected and actual delivery dates by purchase order number and quantities. All data will become the baseline plan to which weekly progress will be measured against the Plan. A daily inspection form will be completed by Contractor and submitted daily to City's Representative. B. Control of the Work The methods, sequences, procedures and techniques by which Contractor shall administer and execute the Work shall be consistent with the Plan and the construction execution plan, delivered by Contractor pursuant to the Specification. Contractor shall remain solely responsible for all construction means, methods, techniques, sequences, procedures and safety programs in connection with the performance of the Work. 34. GOVERNMENTAL REGULATIONS AND TAXES A. Permits and Licenses Contractor shall have responsibility for and shall bear the cost of obtaining all necessary permits and licenses from all authorities required for Contractor's performance of the Work. Contractor shall assist City as necessary in obtaining environmental permits such as the Permit to Construct, California Environmental Quality Act, South Coast Air Quality, etc.. Throughout the performance of the Work, Contractor shall comply with Laws and Regulations. Compliance by Contractor with Laws and Regulations applicable to the Work that become effective or are changed after the effective date of this Contract, shall be handled in accordance with the procedures established in Appendix 4, Changes and Extra Work. B. Laws and Regulations Contractor shall conform with Laws and Regulations. EPCContract 0 8 14.docEPCG + 0 8 1 n ,d&EPGC + n 8 i e r. 35. LIQUIDATED DAMAGES A. Delays If Contractor fails to complete erection or fails meet the performance deadline by the dates agreed upon in Section 3B, , the Parties agree that City shall be damaged. The actual damages that would be suffered by City would be impossible to ascertain precisely. Therefore, the Parties agree that Contractor shall pay City liquidated damages (but not as a penalty) pursuant to the following schedule: Beneficial Use: Fifteen Thousand Dollars and 00/100 ($15,000) for every day with a Five Hundred Thousand and 00/100 ($500,000.00) maximum following the Beneficial Use milestone. B. HP Steam Pressure Loss The Contractor agrees to a liquidated damage of $1,250/psid for every psid over the guarantee point of 40 psid as measured between the HRSG/bidder interface and the steam turbine/bidder piping interface. Note the above is based on a calculation that indicates for every 1 psig loss in HP steam pressure to the turbine there is 3KW drop in steam turbine output. The $1,250/psid was determined based on lost revenue of 3 kw valued at $.05/kwhr for one year at 95% availability. C. Liquidated Damage Payment Liquidated damages owed by Contractor to City will be deducted from Contractor's monthly Payment Application, as such damages are accrued. D. Sole Remedy It is understood and agreed that payment of the damages specified in this Section shall be the sole and exclusive remedy of the City against the Contractor for the failure of Contractor to meet timely the dates of delivery of Mechanical Completion, and Commercial Operation. 36. MAXIMUM AGGREGATE LIQUIDATED DAMAGES The maximum aggregate liquidated damages payable under this Contract shall not exceed $500,000 maximum. 37. PERFORMANCE GUARANTEES A. Performance Guarantees Contractor warrants and guarantees that the Work supplied and installed pursuant to this Contract shall conform to the requirements and specifications set forth in the Specification, including without limitation, the noise emission and auxiliary power guarantees specified in the Specification. EPCContract 0 8 14.docEPGC .,,+, aet 0 8 1 n &tEPGrvent-.a + n u i doe B. Noise Emissions Limits The Contractor's guarantees covers equipment procured by the Contractor, only. Contractor's guarantees concerning noise are specifically stated in Appendix 1. In the event that the Contractor's equipment is proven to have failed the noise guarantees as stated, Contractor shall be granted access to the Contractor's equipment at time or times acceptable to City to repair or replace the defective component that has been duly demonstrated to be deficient. C. HP Steam Line Pressure Loss Contractor shall guarantee that the pressure loss through the HP steam piping, valves, etc. shall be less than the pressure loss allowed in the Specification when the Combined Cycle Power Plant is operating at the Guarantee Conditions as defined by the Specification. D. Obligations of the Contractor If the Work, as demonstrated by the Performance Tests, fails to achieve the Performance Guarantees, Contractor shall have the obligations set forth below. Contractor shall not claim as a defense or excuse for the failure of the Work to achieve the Performance Guarantees that the achievement of such Performance Guarantees was technologically impossible or impracticable. E. Corrective Action Contractor shall, within ten (10) days after the date of a notice of unsuccessful Performance Test, submit to City a plan of corrective action (Corrective Action Plan), specifying in reasonable detail the actions Contractor proposes to take to cause the Work to achieve the Performance Guarantees, and the period of time in which it proposes to complete the corrective action; the Parties must mutually agree upon the period of time for such corrective action. Contractor will not be liable for deficiencies caused by the City or it's other Subcontractors or suppliers. Contractor will not be liable for any deviation from any Corrective Action Plan where the deviation is caused by acts, omissions or requirements of the City or its other Subcontractors or suppliers. F. Standards for Plan of Corrective Action When implementing the Corrective Action Plan, Contractor shall (i) timely and diligently exercise its best efforts to repair and modify the Work to meet the Performance Guarantees, including but not limited to redesign, re -engineering, research, testing and associated construction work, (ii) consider and apply available know-how and technology, including consultation with City and experts in the field, and (iii) consult with City with respect to City's concerns and preferences under the circumstances. 38. LIMITATION OF LIABILITY A. Contractor's aggregate liability for all claims of any kind, whether based on contract, warranty, tort, strict liability or otherwise, for all losses or damages arising out of, connected with or resulting from this Contract, its performance or breach shall not exceed the Contract Price. EPCContract 0 8 l4.docEPGCeatmet 0 8 1 n dffbEPr-r + + n Q i -doe B. In no event, whether as a result of breach of contract, warranty, indemnity, tort, or otherwise, shall Contractor be liable for indirect, special, incidental, or consequential damages including but not limited to loss of profits or revenue; loss of data; loss of use of equipment; cost of capital; cost of substitute equipment, services or facilities; downtime costs or claims of third parties or customers for service interruptions. 39. DISPUTE RESOLUTION In the event that any dispute arises under this Contract, the Parties will in good faith attempt to informally resolve such dispute. Such attempts shall include at least one fact -to -fact meeting with the representatives of City and Contractor. 40. ENVIRONMENTAL PROTECTION A. Qualified Personnel Contractor agrees to use, and agrees that it shall require each of its Subcontractors, if any, to use only personnel who are qualified and properly trained and who possess every license, permit, registration, certificate or other approval required by any applicable Environmental Law or Government Agency for the performance of Contractor's obligations under this Contract. B. Material Contractor agrees that all Material to be supplied or used by Contractor, its Subcontractors, if any, in the performance of this Contract, including, but not limited to, vehicles, loading equipment, and containers, shall be in good condition and fit for the use(s) for which they are employed by Contractor or its Subcontractor. Such Material shall at all times be maintained, inspected and operated as required by applicable Environmental Law. Contractor further agrees that all licenses, permits, registrations and certificates or other approvals required by any Environmental Law or Government Agency will be procured and maintained for such Material at all times during the use of the same by Contractor or its Subcontractors in the performance of any of its obligations under this Contract. C. Compliance with Laws Contractor agrees that in the performance of its obligations under this Contract, Contractor shall at all times fully comply with, and shall require all Subcontractors to comply with, all applicable Environmental Laws. Contractor further agrees that at all times during its performance under this Contract it, and any Subcontractors, shall have and keep in effect all licenses, permits, registrations, certificates, and approvals required by any Environmental Law or by any Governmental Agency for the performance of its obligations under this Contract. EPCContract 0 8 l4.docEPGGePAfaet o 8 i ,26.EPGG + t o 4 1 doe D. Hazardous Materials Removal In the event Contractor or its Subcontractors are required to remove any Hazardous Material from the work area during the performance of the Work contemplated by this Contract, Contractor shall notify City of such fact promptly after discovering such requirement. Contractor shall appropriately remove such Hazardous Materials and deliver the same to City for proper handling and management. However, in the event any such Hazardous Materials are asbestos or asbestos containing materials, City will remove the same promptly after receiving Contractor's notice, as necessary for Contractor's performance of the Work, in compliance with applicable Environmental Law. E. Environmental Indemnity Contractor hereby specifically agrees to indemnify, defend and hold harmless the City, its officials, officers, employees, agents, successors and assigns, herein collectively called the "Indemnitees, harmless from and against any and all losses, liabilities, claims demands, damages, causes of action, judgments, fines, penalties, costs and expenses (including but not limited to all reasonable consulting, engineering, attorneys' or other professional fees) which indemnitees, or any of them, may incur or suffer by reason of: (a) any unauthorized release of a Hazardous Material by Contractor; (b) any enforcement or compliance proceeding commenced by or in the name of any Government Agency because of an alleged, threatened or actual violation of any Environmental Law by Contractor; (c) Contractor shall have no obligation to abate or remove any hazardous material and will have no liability for damages caused by any hazardous material unless the hazardous material is placed on the site by Contractor or released as a result of negligence by Contractor. Each Party will provide environmental indemnity to the other. F. Material Safety Data Sheets Contractor shall submit the current Material Safety Data Sheet, (MSDS) to City's Representative upon request, for each Hazardous Material used by Contractor, or any Subcontractor on City premises during the performance of the Work. G. Suspension and Notification Contractor shall immediately suspend all operations and immediately notify City's Representative if any violation or alleged violation of Environmental Law is encountered during performance of the Work. EPCContract 0 8 14.docEPG + 0 8 i n &IEPCG + + n u 1 41. LABOR AND MATERIAL A. General Contractor shall provide and pay for all labor, supervision, inspection and testing as may be necessary to complete performance of the Work, whether by the Contractor or its Subcontractors, except for inspection and testing included within the Work as defined in Appendix 1, Specification. To the extent permitted by law, any Work to be performed by Contractor hereunder which City would normally undertake with its regular work force and work that would otherwise fall within the terms and conditions contained in an existing agreement shall be performed by employees and Subcontractors who are members of a trade union, bona fide labor organization affiliated with the Building Trades of the AFL-CIO, or by employees and Subcontractors working under a Work specific union agreement. B. Employment of Licensed Personnel Whenever required by law, regulation or code, Contractor agrees to employ only licensed personnel to perform engineering, design, architectural or other professional service in the performance of the Work. All such professional services shall be performed with the degree of care, skill and responsibility customary among such licensed personnel. Contractor shall immediately remove from the site any employee or agent of Contractor or any Subcontractor as to whom City objects in writing. C. Assignment of Individuals Individuals assigned to this Work at a level of responsibility of technical discipline review and above cannot be assigned or reassigned or removed from this Work without approval of City. D. Material Contractor shall provide and pay for all Material and other services as may be necessary to complete the performance of the Work, whether by Contractor or its Subcontractors, except for material and services included within City's scope of work as defined in Appendix 1. E. Start Up Spare Parts and Special Tools Contractor shall deliver and store where directed by City, prior to Mechanical Completion, the special tools and spare parts required, including without limitation those special tools and spare parts listed in the Specification. EPCContract 0 8 14.docEPC + 0 8 i, dbEPC-G + n u 1 ,a F. Quality Control Program Contractor shall establish, implement and maintain a quality assurance and control program in accordance with the provisions of the Specification. The program shall be designed to meet the following objectives: (a) purchased items and documentation to meet specified requirements of this Contract; (b) the quality of items to be part of permanent installation not be degraded during receiving, storing, transporting, handling, erection, installation, inspection and testing; (c) systems, equipment and structures are provided and installed in strict compliance with the manufacturers' instructions and this Contract; and (d) components meet performance and functional requirements of this Contract. G. Testing Contractor shall provide all specially trained or supervisory personnel for the Work. Contractor shall perform or cause to be performed all factory, laboratory and other tests together with all testing procedures described in the Specification and submit to City Monthly Reports (as defined in Appendix 3) of the results thereof, indicating whether such results warrant acceptance or rejection of any materials so tested or performance of such tests. H. City's Right to Inspect City shall have the right at all reasonable times to inspect the Work and to observe the tests relating to the Work that are conducted by Contractor. Contractor shall make arrangements and provide facilities and access for such inspection and observation of such tests at the Jobsite or at the facilities of any Subcontractor where any part of the Work is being fabricated or manufactured. Contractor shall give ample notice as to the time and place when each part of the Work will be ready for such inspection. City may reject any part of the Work found to be defective or not in accordance with this Contract, regardless of the stage of its completion or the time or place of discovery of such errors, and regardless of whether City has previously accepted it through oversight or otherwise. Such inspection by City shall in no way relieve Contractor from its obligations under this Contract. EPCContract 0 8 14.docEPCG + + 0 8 14.d&EPGGoa4aet-0-8-13.doe IN WITNESS WHEREOF, the Parties have caused this Contract to be executed by and through their authorized officers on the date, month and year first written above. ATTEST: BRUCE V. MALKENHORST, City Clerk APPROVED AS TO FORM: EDUARDO OLIVO, City Attorney CITY OF VERNON LEONIS C. MALBURG, Mayor CONTRACTOR Date: Name Title Date: Name Title EPCContract 0 8 l4.docEPGGefATaet 0 8 i 4 ,ace EPCG t t n Q y 3.doe r APPENDIX 1 SPECIFICATION FOR COMBINED CYCLE POWER PLANT EPCContract 0 8 14.docEPG + 0 8 1 n &bEPCG + + n u 1 a r It APPENDIX 2 PROJECT CONTROL REQUIREMENTS FOR CONTRACT 1. INTRODUCTION This procedure defines the concepts that Contractor shall comply with during performance of the Work. Precise reporting by Contractor is required and compliance with these requirements will be directly related to the approval of Payment Application invoices. Contractor shall implement his own unit manhour/earned value monitoring and controls system to fulfill his contractual obligations and management needs based on commodity quantities. The effort by City is not intended to duplicate Contractor's effort, but rather to obtain an overview of his performance. City must be assured that Contractor's performance is adequate relative to cost and schedule, there are no significant variances from established baseline target goals, and whenever variances do occur they are quickly identified and corrected so they do not impact the overall project completion. 2. PROJECT CONTROLS REQUIREMENTS FOR PRE -MOBILIZATION MEETING 2.1 Pre -Final Design Kickoff Meeting. Contractor and its major Subcontractors shall meet with City at the time of the Pre -Final Design kickoff meeting to finalize the guidelines, level of detail and summaries to be used in developing the design and construction portion Project Controls program. Contractor shall prepare a Primavera Level I Summary and Level 2 Detailed CPM Network Diagram and logic bar chart stamped "Preliminary" for this meeting showing in detail the activities to be accomplished during the first sixty (60) calendar days of the design work plus a summary of the construction site -work. 2.2 Schedule. Contractor shall submit for City's approval, within 30 calendar days after award of Contract, a detailed Primavera critical path schedule for all Contractor's activities including engineering, procurement, construction, testing and start-up, and performance testing activities, identifying Contractor's plan of execution for the Contract Scope of Work. This schedule shall incorporate and show the activities to accomplish the major interfaces and milestones. This schedule shall identify the critical path(s), sub - critical path(s) (10 days or less float), and provide sufficient logic/activities to demonstrate Contractor's ability to achieve the schedule. The engineering and construction activities will be man-hour loaded by engineering discipline and construction craft man-hour including all subcontract man-hours. Manpower histograms by engineering discipline and construction craft will be produced as a baseline target plan to be measured against weekly with actual manpower spent. A total project progress curve will be developed based on the resource loaded Primavera schedule. This baseline target plan will also be measured against weekly with actual progress based on earned value earned. For the engineering phase of Work, the schedule shall be sufficiently detailed so that the Contract deliverables and engineering milestones are identified. EPCContract 0 8 14.docEPGG .„+, aet 0 8 i n ,a, EPGC „+, aet n 4 i dee f For the erection phase of the Work, Contractor's schedule shall be sufficiently detailed so that milestones, all equipment and material deliveries, drawing requirements, submittals, and other Subcontractor interfaces are clearly identified. If, in the opinion of City, it becomes necessary to work after regular hours or on holidays in order to maintain the schedule and to complete the Work within the time specified, Contractor, upon request by City, shall do so forthwith. Unless failure to maintain schedule is due to causes beyond the reasonable control of Contractor, such Work after regular hours or on holidays shall be without additional cost to City. 2.3 Construction Execution Plan. The written Plan shall describe in detail the methods to be employed, including planned overtime or shift work intended, equipment to be used and associated duration, access routes and requirements, the sequencing and interfacing of events, material control, any interface requirements and any specific requirements necessary to support Contractor's methods and techniques. This execution plan shall be consistent with Contractor's Schedule and must be submitted 30 days prior to mobilization. 2.4 Material List. A purchase order register of equipment and materials supplied by Contractor, including purchase order and delivery dates, shall be submitted with the detailed Contract Schedule. This is to be submitted with the initial schedule submittal and updated bi-monthly. 2.5 Submittal Compliance. Contractor's failure to submit any of the information outlined in 2.2, 2.3, 2.4 above with the timing, format and level of detail defined by City/Engineer, will result in City withholding payment of all invoices until delivery of the information is reviewed and accepted. 3. PROJECT CONTROLS REPORTING FOR CONTRACT EXECUTION AFTER MOBILIZATION 3.1 Weekly Progress/Coordination Meeting. Meetings will be held in order to discuss job progress, coordination and safety and Contractor and Subcontractors (if appropriate). 3.2 Two Week Look Ahead Schedule. Contractor shall submit to City a two week look ahead schedule. This schedule shall identify all activities scheduled to be worked on in the next two weeks and indicate manpower requirements by craft. The two week look ahead schedule shall be based on Contractor's detailed project schedule. However, when required by City, it shall show greater detail than Contractor's project schedule. At a minimum, the two week look ahead schedule shall include all activities and milestones identified on the detailed project schedule for the two week period. The two week look ahead schedule shall be presented at the Weekly Progress/Coordination Meeting. 3.3 Daily Force Report. The Contractor shall submit to City a daily force report which shall include the following information: 3.3.1 Contractor's scheduled versus actual manpower by type and total; 3.3.2 Contractor's administrative total; EPCContract 0 8 14.docEPGC + 0 8 i n ,a&EPC-G + + n Q i ,a i 3.3.3 Major construction equipment being utilized; 3.3.4 Description of Work being performed and location of Work on -site; 3.3.5 Other pertinent remarks, manpower shortages, visitors, material received, etc.; and 3.3.6 Purchase Order Register. 3.4 Weekly Quantity/ Manhour Report. Upon start of construction and each week thereafter, Contractor shall submit a quantity/manhour report, indicating actual material quantities installed and manhours expended. In addition, an updated quantity installation curve shall be provided by commodity. 3 .5 Updated Detailed Project Schedule. Contractor shall update the detailed project CPM schedule on a monthly basis (minimum) and be included with the monthly progress report which must be submitted with proposed Payment Application. The physical completion of each activity by percentage or remaining duration shall be included and a description of all logic changes and a narrative report indicating the status of the project shall accompany the updated schedule. This report, at a minimum, shall list activities that are behind schedule, identify the corrective action necessary to overcome these deficiencies, and identify required delivery dates for material and equipment supplied by Contractor. This update shall be provided to City within five working days following the close of the update period. 3.6 Updated Manpower Curves. The manpower curves shall be updated to reflect status per the project schedule and are to be submitted with the updated schedule. If requested, Contractor shall revise them and furnish City with three or more revised copies, as required. The Engineer/City shall make periodic analysis of the manpower progress and productivity and Contractor shall adjust the manpower to coincide with meeting activity completion dates/requirements of the project schedule. 3. 7 Monthly Reports. At monthly intervals from the date of Contract award, Contractor shall submit detailed factual progress reports to City for the entire duration of the Contract. The progress reports shall show clearly and accurately the status of all activities including the exact amount of time each activity is ahead of or behind the agreed Contract schedule. The report shall detail the action being taken by Contractor to avoid possible delays in his Work, and to expedite any aspects or progress which are behind schedule and shall summarize any change in the critical activities since the date of issue of the previous report. The format of the Monthly Report shall be approved by City and shall be forwarded to City within seven days of report period close. The report on City's material deliveries shall be included and shall give the date and details of orders placed and indicate the delivery date quoted by the manufacturer or supplier, in relation to the agreed Contract Schedule. If any delivery has an adverse effect on the Contract Schedule, Contractor shall state the remedial action taken to ensure that delays do not occur. Contractor shall be responsible for expediting the delivery of all material and equipment to be provided by Contractor and its Subcontractors. The report shall also show detailed progress towards awarding of any contracts by Contractor to its Subcontractors. EPCContract 0 8 14.docEPGG * t 0 8 14.&bEPGGon4r-aet_0_8_13.doe 4 ! The report shall, for each section of Contractor's Work, give the percentage completion and the projected completion date of each of the main items of Work in relation to the agreed Contract Schedule. Contractor shall report with respect to various sections of this Work, the erection equipment in use or held in readiness, a summary of labor and supervisory staff and details of any matters arising that may generally affect the progress of the Work. Contractor shall be responsible for providing the evaluation methodology and systems necessary to determine all progress measurement including, but not limited to, installed quantities of Work. Contractor shall notify City prior to the time such evaluations are made. City, at its discretion, may arrange to have City's Representative witness and independently verify all quantity evaluations made by Contractor for determining drawings completed, equipment and material deliveries, installed quantities of Work, etc. for payment under the Contract. Copies of notes, computations and other records made by Contractor for the purpose of determining progress/quantities installed shall be furnished to City upon request. Contractor's measurement and computations shall be made by methods considered appropriate by City for the class of Work measured. City may also, at its option, independently verify by performing its own computations, the quantities of Work to be paid for under the Contract. 3.8 Monthly Payment Applications will be broken down by WBS item number or schedule ID number in the Primavera schedule. This Payment Application will show quantities, unit of measure, price per unit, extended price and percent complete based on the schedule value "earned", not spent. EPCContract 0 8 14.docEPCGo r-ae^ 0 8 i n dR&-EPGG rtFae+ n u y ,a , i APPENDIX 3 Unconditional Waiver & Release Upon Final Payment EPCContract 0 8 14.docEPCC ++ 0 8 14. "EPC-G + + n Q 1 doe i t 41 CONDITIONAL WAIVER AND RELEASE UPON FINAL. PAYMENT (CALIFORNIA CIVIL CODE SECTION 3 62 ) Upon receipt by the undersigned of a check from ( Maker of Check l in the sum of $ payable to (Arnold of Check) ( Payee of Payees of Check) and when the check has been properly endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic's lien, stop notice ° or band right the undersigned has on the job of located at Owner to the following extent . ( .tab oesaip�� ) This release covers the final payment to the undersigned for all labor, services, equipment or material furnished on the job, except for disputed claims for additional work in the amount of Before any recipient of this document relies on it, said party should verify evidence of payment to the -undersigned Dated (Oc-pany dame ) By NOTE: THIS FORM' COMPLIES WITH THE REQUIREMENTS OF CIVIL CODE SECTION 3262(d){3). IT IS TO BE USED BY A PARTY WHO APPLIES FOR A FINAL' PAYMENT WHEN THE FINAL PAYMENT CHECK HAS NOT YET CLEARED THE BANK. THIS RELEASE ONLY BECOMES' EFFECTIVE WHEN THE CHECK, PROPERLY ENDORSED, HAS CLEARED THE BANK. EPCContract 0 8 14.docEPGC= „,.,-aet 0 8 i n ,ace EPCG r+,-aet—n_u_f -doe CONDITIONAL WAIVER AND RELEASE UPON PROGRESS PAYMENT Civil Code 3262 (d) (t) Upon the receipt by the undersigned of a check from in the sum of payable to or and when the deck has been property endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic's lien, stop notice, or bond` right the undersigned has on the job of located at - (Job Do=0-). to the following extent. This release covers a progress payment for labor, services, equipment, or material furnished to through only and does not cover any retention`s retained before or after the release date; extras furnished before the release date for which payment has not been received; extras or items furnished after the release date. Rights based upon work performed or items furnished under a written change order which has been full executed by the parties prior to the release date are covered by this release unless specifically reserved by the claimant in this release. This release of any mechanic's lien, stop notice, or bond right shall not otherwise affect the contract rights, including rights between parties to the contract based upon a recission, abandonment, or bream of the contract, or the right of the undersigned to recover compensation for fumished labor, servies, equipment, or material covered by this release if that furnished labor, services, equipment, or material was not compensated by the progress payment.. Before any recipient of this document relies on it, said party should verify evidence of payment to the undersigned. Dated : COMPA r 3Y PLEM ? rRmrr NAM a TME Where the claimant is required to execute a waiver and release in exchange for, or in order to induce the payment of, a progress payment and the claimant is riot in fact, paid in exchange for the waiver and release or a single payee check or joint payee check is given in exchange for the waiver and release, the waiver and release shall follow substantially the above form EPCContract 0 8 14.docEPGG t 0 8 i n ,a&EPGr t + n kr i ,t i 'k CAUFORNIA PREUMINARY 20-DAY NOTICE (PRIVATE OR PUSUC WOW RE NOTPMD W FULL POR THE LABOR. $ERVICS3, EQUIPMENT.OR WAISR"S PUUMSD OR TO BE:PURNWNED, A "S LUM LEAOWG TO THE LOSS, TRRWCX COURT FORECLONyRE PR00E900" OF Au OR PART OF YOUR PROPERTY W PRIMED BAY SE PLACED AGANIET THE PROPERTY EVEN THOUGH YOU WS PAID 'YOUR 'CONTRACTOR W PULL-. YOU: TO PROTECTYOUN$EGP AGAINST THIS CONSEW)ENCR SY It)RHQUNWIG YOUR CONTRACTOR TO PUNWSN A: Sam NY THE'. PERSON Oft FIRN GHVWG YOU TREE SOME BEFORE W WWG PAYWNETTO YOUR CONTRACTOR. R) REQUNtNIO IMOTOR TO PUSNISN A RECENT TO ESTASL)"7"AT YOU PAM THE COKTKACM S l FULL A" ROOMING NO LATER AYR Mtn& 0119 t1" fiF-TNT PRELRINIARY NOTICE AN AFFIDAVIT TIIATYOU PAID TNS:t OWAACTOR:Bill FULL. OR MANY DATE: YOU ARE'HEREBY WMIEDTHAT 7W UNDERSIGNED "AS RpMomED OR WILL FURNISH LABOR, SEWAGES. EQUIPMENT OR MATERIAL OF THE PULOWMG DESCFtPTXW PERSON FURNI.SHM LABOR. SERVK= BOUIPIAWT OR MATERIAL CA TO: OWNER. REPU7L°D OWNER, Olt PUBLICA43ENCY (SEE OVER) WHOM NOT) (STATE) TO: PRW REPUTED,.OR OPX.K L CONTRACTM fmyjWrAm tap) � THIS BOX0C B KiW. 7NEHAIM3AND ADDI OF ANY LASQRENS:TO WHOM EMPL.OYM PAYMBRSARE DIEA$OFTIM OATS OF TNBIWTICE ARECCNTAMNEDON ATTAC HMINT'A`... WBO"aI OORINNATMN6ISIN A34DYADEA P*WHIBOOF- I=t ATUREj Ia+iU DESCRP710H Of LABOR, SERVICES, EQUIPMENT OR MATERIAL TQBE SUPPLED 7HE.NAME AND:ADDRESS OF PERSON COWMACTING THE ABOVE CIOUR CIS. I_. JOS+STM ($TREET AND LEGAL DESCRU'WW F KNOWN) F ..... AN ESTMA7E OF'RE TOTAL PRIM OF 7HE LABOR, SERVICE$. EQUPMENiOR'MA7ERW.$fURNISHED OR TO BE FURNISHED 6' TWWPLIIOB TO WWCH rJFPLIMENTAL PRIIMlVo nAREMYAItFr. tON:Y swowRACTOR57HRE "Am v mwwf THL:TMWT Me" INAHLLOP PFRaOHaW1aND) (MLE). PRow OF.SERVIGEAFFOAVif(Gva. CCO mr.t) . daClafa MHst l Ifay! l61YadHaPiM d YIa abaM PRELNIMiARY NOTICE (CFIM.'SI �fCgiMO � a $YPWxmWIydNnstiA *0" to LAeldroul an — ism at tlala L. FimClass CMWed or RepitlaHM-Maii sw**. p~ PHaPaid aft4sad lP Oath Of ft PaM" N Mae sdit" OwWn dww 00- I derJarig.UW* 00AWly ofPWPO LmdW MW bws d tEW sMW dC4IBQMJa"WLMW*X*O V it VW ON Coff*a (ATTACH RECEIPTS OF CERTFED Oft REL315TERED MAT. WHEN RETURNED) SCGNAAM OF PERSON MAKING SERVICE EPCContract 0 8 14.docEPGG ++ 0 8 T 4 MEPC-r + + 0-813.doG t ,s APPENDIX 4 INSURANCE SCHEDULE Contractor shall provide proof of insurance, within 30 days of the full execution of this Contract, including a standard certificate of insurance, in at least the following amounts and coverage (combined single limit permitted): I. Coverage and Limits Bodily Injury Property Damage Hazards Each Person Each Accident Each Accident Automobile Liability $100,000 $300,000 $300,000 Owned Automobiles $ 2,500,000 $5,000,000 $ 2,500,000 Hired Automobiles $ 2,500,000 $5,000,000 $ 2,500,000 Non -Owned Automobiles $ 2,500,000 $5,000,000 $ 2.500,000 Workers' Compensation $ Statutory Employers' Liability $1,000,000 per employ U. Comprehensive General Liability General Liability $5,000,000 $5,000,000 $5,000,000 Premises Operations $5,000,000 $5,000,000 $5,000,000 Independent Contractors $5,000,000 $5,000,000 $5,000,000 Products - Completed Operations $5,000,000 $5,000,000 $5,000,000 Contract Liability $5,000,000 $5,000,000 $5,000,000 a. The general liability policy shall contain the following special endorsements which shall be noted on or attached to the standard certificate of insurance: 1. An endorsement naming the City of Vernon, its officers, and employees as additional insureds under the policy only to the extent of Contractor's indemnity obligations assumed under the Contract. The additional insured endorsement will be per standard CG20 10 1185. 2. An endorsement providing the City of Vernon 30 days notice of cancellation or material reduction of coverage. 3. An endorsement providing coverage for all operations under this Contract. 4. Such other endorsement as may be required by addendum hereto. b. In addition to the standard certificate of insurance, proof of general liability coverage shall be furnished in the form checked below. Certification of the following proofs by the insurance agent or broker will be accepted: X For each policy, a notarized letter from the underwriter or carrier certifying that the coverage and statements in the standard certificate of insurance (attached thereto) are true and correct and that the signator is an officer authorized to so certify. _ A copy of each policy certified by an officer of the underwriter or carrier and notarized. EPCContract 0 8 14.docEPG +, + 0 8 i n dWEPCC t + n u 1 n dee 16, q a 4 (NOTARIZED INSURANCE CERTIFICATE TO BE INCLUDED BEFORE EXECUTION) EPCContract 0 8 14.docEPCG t 0 8 i n d EPGG t n u 17 a APPENDIX 5 MISCELLANEOUS 1. SITE SAFETY PLAN Attachment To be added within 30 days of Contract signing via an addendum. 2. QUALITY CONTROL AND QUALITY ASSURANCE MANUAL Attachment To be added within 30 days of Contract signing via an addendum. 3. SITE LABOR AGREEMENT Attachment To be added within 30 days of Contract signing via an addendum. SITE CONSTRUCTION PLAN DRAWING Attachment To be added within 30 days of Contract signing via an addendum. EPCContract 0 8 14.docEPGGo„+r-get 0 8 i ,au EPC-r n+, ae4 n 4 l doe