Resolution No. 83163 4 5_ 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 8316 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF VERNON TERMINATING CONTRACT NO. 565 FOR SEVILLE AVENUE SEWER MAIN REPLACEMENT AWARDED TO CODY ENGINEERING, INC. BY THE CITY PURSUANT TO RESOLUTION NO. 8088 WHEREAS, on October 23, 2002, Contract No. 565 was awarded by the City Council of the City of Vernon to Cody Engineering, Inc. ("Cody") for Seville Avenue Sewer Main Replacement (the "Project") in accordance with Resolution No. 8088; and WHEREAS, the Project was intended to upgrade the existing (sewer main and manholes for the Malburg Generating Station Project (the "Malburg Project"); and WHEREAS, construction of the Project has been delayed because of difficulty by the Contractor in meeting the insurance requirements and because of delays in the construction schedule of the Malburg Project; and WHEREAS, Cody has requested that it be allowed to either increase its bid by $91,376 or terminate its contract; and WHEREAS, by letter dated November 13, 2003, Bruce V. Malkenhorst, City Administrator/City Clerk, has recommended that the City pay Cody for costs incurred for insurance and traffic plans of $6,852.00 and that Contract No. 565 be terminated and re -bid when the Malburg Project is ready to proceed. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF VERNON AS FOLLOWS: SECTION 1: The City Council of the City of Vernon hereby finds and determines that the recitals contained hereinabove are true 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 and correct. SECTION 2: The City Council of the City of Vernon hereby repeals Resolution No. 8088, the award of Contract No. 565 for Seville Avenue Sewer Main Replacement to Cody Engineering, Inc. is hereby rescinded and the City Clerk is hereby authorized to pay Cody $6,852.00 for costs. SECTION 3: The City Clerk of the City of Vernon shall certify to the passage of this resolution, and thereupon and thereafter the same shall be in full force and effect. APPROVED AND ADOPTED this 19th day of November, 2003. ATTEST: BRUCE V. MALKENHORST, City Clerk EONIS C. MAL URG, M yor - 2 - 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 STATE OF CALIFORNIA ) ) ss COUNTY OF LOS ANGELES ) I, BRUCE V. MALKENHORST, City Clerk of the City of Vernon, do hereby certify that the foregoing Resolution, being Resolution No. 8316, was duly adopted by the City Council of the City of Vernon at a regular meeting of the City Council duly held on Wednesday, November 19, 2003, and thereafter was duly signed by the Mayor of the City of Vernon. (SEAL) BRUCE V. MALKENHORST, City Clerk - 3 - SUPPORTING DOCUMENTS CITY COUNCIL LEONIS C. MALBURG r Mayor THOMAS A. YBARRA Mayor Pro -Tern WM. 'BILL" DAVIS Councilman H. "LARRY" GONZALES Councilman W. MICHAEL MCCORMICK Councilman BRUCE V. MALKENHORST City Administrator/City Clerk FAX (323) 826-1438 City Council City of Vernon Honorable Members: EDUARDO OLIVO City Attorney FAX: (562) 869-1883 V KEVIN WILSON Wir Community Services & Water FAX: (323) 826-1435 KENNETH J. DeDARIO Director of Light & Power FAX: (323) 826-1425 STEVEN E. PARKER Fire Chief FAX: (323) 826-1407 CITY HALL BRUCE W. OLSON 4305 SANTA FE AVENUE, VERNON, CALIFORNIA 90058 Police Chief TELEPHONE (323) 583-8811 FAX: (323) 826-1481 November 13, 2003 At this time it is necessary that Contract No. 565, Seville Avenue Sewer, awarded to Cody Engineering, Inc., be terminated. The contractor delayed the project for over a year due to schedule not meeting the insurance requirements and due to the construction of the Malburg Generating Station. He is now requesting an increase on the contract due to increased costs over the last year. After review of such request, staff has concluded that the increase cost is not justifiable, contract should be terminated, and the project should be re -bid. This has been reviewed by the Acting City Attorney. It is hereby recommended that the City pay the contractor $6,852.00 for cost incurred and that the contract with Cody Engineering, Inc. be terminated. Very truly yours, Bruce V. Malkenhorst City Administrator/City Clerk BVNi/gm pF E'ER 6 m'VE6T two COMMUNITY SERVICES & WATER DEPARTMENT OFFICE MEMORANDUM TO: Bruce Malkenhorst, City Administrator FROM: Samuel Kevin Wilson, irector of Community Services & Water DATE: November 12, 2003 SUBJECT: Seville Avenue Sewer, Contract No. 565 — Cody Engineering, Inc. The contractor for the Seville Avenue Sewer, Contact No. 565, has submitted a request to change the terms of the contract awarded to him. The contract was awarded Cody Engineering, Inc. by the City of Vernon on October 12, 2002 but the project construction was delayed by the contractor in meeting the requirements for insurance and then due to the construction schedule of the Malburg Generating Station. The delay is now over a year and the contractor requests a significant increase in the contract due to the increased costs over the last year or release from the contract. The proposed increase in costs is not justifiable and the contract should be terminated and the project bid again. However, the contractor has incurred costs for insurance and traffic plans required by the Malburg Generating Station Chief Building Official. The costs are $6,852.00 and I recommend we pay these costs as a settlement of all claims and terminate the contract. The Acting City Attorney's Office has reviewed the file and also recommends this course of action. If you concur, the Acting City Attorney will draw the necessary documents to effect this termination and rebid the project. SKW/sn Enclosure C: Eric Fresch Eduardo Olivo NOV-11-2003 TUE 01:33 PM OLIVO & PLASCENCIA FAX NO. 1 P. 02/06 C O Y COUNC IL LFONI5 C. M AI -BURG, M.,yor TITOMAS A. YIIATtI1A Mayor Pro ••7em WM, "BILL" DAVIS (:mini ilmnrl IL "LARkY" GONZALES Camurilmin W. MICI 1AFT, MCC'ORMICK Co.tildM1,11 UU(Ti V. NiAEKFNI IORST CITY HALL City Atlutin6r lratnr/City Clerk 4305 SAN-fA FE AVENUE, VJ,RNC)N, CALIFORNIA 90058 FAX, (323) 826-11M IT- LEPHONh (3')3) Sf? ,8811 November 11, 2003 Via Facsimile & U. s. Mail 1;T)TJARDO OLIVO City Attorney FAX: (562) 669-188:1 KE•,VIN WITSON 17irectnr of Community Se►vicvs lZ Water I'AX: (323) 8264435 KENNETH J. DcUARIO Director of Utilities 1 'AX: (323) 826.1425 S'11-'V1;N E. PARKER rlre Chief FAX: (323) 826-1407 BRUCE W. OLSON rt)lice corer FAX: (323) 826-1481 Kevin Wilson CONFIDENTIAL Woody Na,tsuhara ATTORNEY -CLIENT COIvJWMICATZON COMMONITY SERVICLS & WA HR 4305 Santa Po Avenue Vernon, California 90058 Re: Contract No. 565 with Cody Engineering, Inc., for the Seville Avenue Sewer Main Replacement C3enL-lemen: You have-xequestod advice regarding the potential tex,mination of Contract No. 565 (the "Contract") between. the City of Vernon and Cody Engineering, Inc. ("Cody"). You have asked the following questions: (1) is the City required to approve a request by Cody to increase its original bid price; (2) may the City terminate the Contract because it is not able to proceed with the project at this time,, (3) if the City desires to terminate the Contract, what procedure must be followed; (4) if the City terminates the Contract, will it be required to reimburse Cody for the costs incurred by Cody; and (5) may the City pay such costs through the "change order" procedure. NOV-11-2003 TUE 01:33 PM OLIVO & PLASCENCIA FAX NO. 1 P. 03/06 Kovin Wilson Woody Na tsuhaz a November 11, 2003 Page 2 FACTS The City sent out Notice Inviting Rids for the furnishing of all equipment, materials and supplies necessary fob the Seville Avenue Sewer Main Replacement (the "Project") . The Project was intended to upgrade the existing sewer main and manholes for the MGS Project. The City received several bids and, on October 23, 2002, awarded the Contract to Cody. Cody was required to obtain a labor and materials bond, as well as a performance bond, upon the execution of the Contract and prior to beginning the work. The bond: were obtained and the contract was executed and delivered to Cody on or about April 15, 2003. According to the documents I reviewed, a start date was originally projected for January of 2003. However, the Contract was not executed until April. 15, 2003, and the pre -construction meeting was not scheduled until April 30, 2003. On May 1, 2003, the City advised Cody that it needed a daily construction schedule, a traffic control plan and other itomo. By letter dated May 13, 2003, Cody confirmed that the :Mart date had been changed "once again" to June 9, 2003. At that time, Cody advised that " [tl his uncertainty/confirmation of a start date makes it very difficult. for Cody Engineering to schedule our projects." Pursuant to a memo dated June 3, 2003, Cody recplested that the City authorize a progress billing for mobilization and advised the City that Cody had paid for the bonds, traffic plans and shoring- plans. On June 5, 2003, Cody submitted an invoice for .$6,852.00 for the cost of the bonds and the traffic and shoring plans. The start date for. the Contract was continued on sevora.l other occasions to July 14, 2003, August 4, 2003 and September 8, 2003. Cody complained about its inability to schedule other jobs and about its increased insurance costs. Cody also complained that the uncertainties regarding the start d Ue was causing it an undue financial impact. On October 9, 2003, Cody advised the City that it needed to adjust its bid price from $243,440 to $334,816. Cody asked the City to accept its increased bid and commit to a start date of no latex than January 5, 2004. NOV-11-2003 TUE 01:33 PM OLIVO & PLASCENCIA FAX NO. 1 P. 04/06 r Itavin Wi l son Woody Natauhara .November 11, 2003 Page 3 A1tea:-natively, Cody requested that its (1) be released from t:ho Contract and that the City reimburse Cody $6,852.00, the cost of the bonds bids and traffic and shoring plans, or (2) the City pay Cody 10% of the Contract amount, $24,344, which would have been the amount, Cody would have forfeited if it could not proceed with the Contract. You have advised that tho City is stall not able to commi.t: to a start dare. Further, you believe that the City can obtain a lower bid than Cody's revised bid. Theref_orE!, you have advised that the Community Services Department recommends that the Contract be terminated and that the Project be re -bid when the MGS Project is ready to proceed. provides ,ANALYSIS Section 44 of Contract No. 565 ("Termination") "(b) Optional Termination of Contract by City (Contractor. Not at Fault) City may terminate the Contract upon ten (10) days written notice to the Contractor, if it is found that reasons beyond the control of either the City or the Contractor make it impossible or against the City's interests to complete the work. in such a case, the Contractor shall have no claims against the City except (1) for the value of work performed up to the date the Contract is terminated, and (2) for the cost of materials and equipment on hand, in transit, or on definite oommitmont, as of, the date the Contract is terminated, provided that such materials and equipment would be needed in the work and meet the requirements of the opecif icat ions . The value of work performed and the cost of materials and equipment, as mentioned above, shall be determined by the City in accordance with the procedure NOV-11-2003 TUE 01:34 PM OLIVO & PLASCENCIA FAX NO. 1 P. 05/06 Kevin Wilson Woody Watsuhara Novoanher 11, 2003 Pago 4 .prescribed for making of a final estimate and payment as described in Section 3." If Cody were forced to file a breach of contract: lawsuit, they would generally be entitled to delay damages. Cody would probably not be entitled to the increased bid Price.. However, some adjustment in the price due to increasod costs caused by the delay, would be recoverable. Cody would also be Entitled to costs for office overhead, lost profits and other matters that they would attribute to the delay. Rather than continue to delay the stars: date, I agree that the City ahou.ld terminate the Contract, Pursuant: to Section 44, the City may provide ten days written notice of its intent to terminate, If it does so, the City is obligatod to pay the "value of the work performod and the cost of material and equipment'. Cody would not he entitled to a termination payment of 10% of the Contract price. The cost of the bonds are not, technically, `°materialoll or "equipment." Nevertheless, a. court would probably interpret this provision to require the reimbursement of reasonable costs, including the cost of the bonds. Considering the damages that could be alleged in a broach of contract action., X recommend that the City accept Cody's "settlement" proposal of $6,852.00.3 The following steps need to be taken to address this CT at Ler: 1. The termination of the Contract should be put on the agenda for City Council consideration. Kevin should request that the matter be placed on the agenda. 2. A closed session item will also be needed to discuss the potential for litigation. Z will advise the Acting City Attorney of that item and request that it be placed on the agenda. x It appears that Cody has provided sufficient proof that these coots were incurred in connection with the Contract. NOV-11-2003 TUE 01:34 PM OLIVO & PLASCENCIA FAX NO. 1 P. 06/06 1Cev-.113 W11,1.'0n Woody Natsubara N'ovembe.r. 1.1, 2003 t Page 5 3. if the City Council approves the termination and the payment of the funds, the 10-day notice should be sent to Cody immediately. The notice should also indicate that the City Council has agreed to accept Cody's October 9, 2003, "proposal" that payment, of $6,852.00 be accepted as full and final paymerit of all costs allegedly owed to Cody. P11ease call cite if. you have any questions. Sincerely, Eduardo Olivo Lcgal Counsel Cc: City Administrator Acting City Attorney CodV Engineeringg Inc. License Nbr 783530 "A" PO Box 341 Norwalk, CA 90651 Ph: 562/868-2252 Fx: 562/868-2552 e-mail: codyengdnc@earthlink.net October 9, 2003 Sent via Facsimile City of Vernon Mr. Samuel K. Wilson 4305 S. Santa Fe Avenue Vernon, CA 90058 RE: Seville Avenue Sewer Main Replacement — Contract #565 Dear Mr. Wilson: This morning I received a call from Mr. Sherwood "Woody" Natsuhara, City of Vernon's P.E., regarding the start date of the above referenced project. This is a project that was bid, and awarded, approximately a year ago and has had numerous changes in the start date. On August 25, 2003, we sent a letter to Woody explaining that, due to the increases in wages, workman's compensation as well as all other insurances and supplies to name a few items, the delays would require an adjustment to our prices. We anticipated a start date around the month of October. This morning we were informed that the "new" projected start date is around January / February 2004. As a contractor, and in order to insure ongoing projects be properly serviced, we must schedule our bidding and work schedule at least 60 days in advance. As per the instructions to bidders, Cody Engineering was compelled to furnish, within 7 days, the bonds and other submittals or risk the loss of our bid guarantee of $24,344.00. The cost of the bonds, traffic plans and shoring plans were in excess of $6,800. and were paid the several months ago. In conversations with Mr. Pin Chan the first part of June 2003, he instructed us to invoice the City of Vernon and he would arrange for payment. To date, we have not received the funds. These delays and uncertainties have created an undue financial impact on our company. We have not been able to commit to other work due to the constant uncertainty of this yearlong situation. Cody Engineering Inc. has calculated the increased costs for this project since the original bid opening. A copy is enclosed for your review. We anticipate a start date no later than January 56' 2004. Cody Engineering Inc. requests that the adjusted costs be acknowledged and accepted in writing within 10 calendar days from the receipt of this letter. In the event that the City of Vernon chooses not to accept the increased costs, we request that we be released from the contract. In addition, Cody Engineering would accept a 101% payment of $24,344. from the City of Vernon, similar to the assessment that would be imposed had we failed to perform, or prompt payment of our invoice #119 originally submitted June 5, 2003 in the amount of $6,852. City of Vernon Page 2 October 9, 2003 As suggested in our prior correspondence (copy attached), we feel it would benefit all parties concerned to settle this matter promptly or, the City of Vernon pay Cody the damages stated, cancel the contract and put it out for rebid when the City is ready to move forward on this project. We await your comments. Respectfully submitted, CODY ENGINEERING, INC. Bob Kratz President Cc: Mr. Sherwood Natsuhara R.S. Bonding and Insurance Agencies N O O H to O m M O I- .. rn I` r-I o -+ N N N tTl 4-) ro ro -rl a4 Q E-, P4 O E-i E-+ M W zo w z �w cn w 0 N > E-+ zH� oUx O O O O o 0 0 0 0 0 O O O O O O O O O O O O O O O O O O O O 0000000000 LnLO LOoIzTor(Doco ri LO e-i [- t.f) M m m N m �t NOkDNrnL I'D V -1 N M ri 0000000000 0000000000 0000000000 oLn00000Ln0o LNO10IzTu)(-r-iLnM riC NM LO EOM CO N r-i LO M 1 -IJ I EiHE-4xxxMPHx ri I r-444F4UUUU44r-4 1~ I zzz1:4 F:cFt� lt4(DI Z I aaa W wwwm] 4 W >, I o 0 0 0 0 0 0 0 0 0 4-1 I O O O O O O O O O O - r- I 10 0 0 0 0 0 0 0 0 0 1j I I~ I .--I lD LO M -A lD .--f O lD N ro 1 lD M lD 1- � I � � I •r-I I w I i I 1 0 H a a x O U x Ca U z Uw H w z a Q aH �a a UN wwa a aaoa, al �D >0U a E-Axz O`4FCC] �o Q W >w+U F::� aa�i:_ Ln zx= a a a, UkDwH.ia m a= u) - Ln N O CO >+ Ln Q0 LO r-I r-1 ri 'T w .-i lD (') M .--I H W W W La O W W W W Lt5 4444rX4CM4XG44444 4444 a E1 O Ei Q H C[1 04 w W wxo r-i N M I�v LO lD I` 00 m o y M O M r1 LO N [� � v+ O O ri r--1 r I N N N tP 4-1 IE! M (a .r-I PA A E-H E+ z w w U a a w a z(a > 0 x o 0o o a �1 zw wax m -ri LO rn kD LO H U w h a a a 0 E-H H H z w 0 124 z0 a H >w w O N y+ E a H a�x H > W IYl wx0 rn [� n Cl O O O O O O O O O O O O O O O O O O O 0 0 0 0 0 0 0 0 0 0 I—mO01101000lO;Zp r-iNIONI— OID�CMIO Mtnmr- LOr- r1I—O 0lMM(Y)l)r-10)r4(nm OD r-I (Y) -4 LO -A O O O O O O O o 0 0 0 0 0 0 0 0 0 0 0 0 00000000(D0 I— mlOMlOriO ml0N mmE—LO Or-1mM r-I to M O LO m r` I— LO r-i M ri 0) -W r-I 1 -P 1 E- HEyxxxxHEx zzzQ U44 DW oaz� I a a a W W W W w a W 10 0 0 0 0 0 0 0 0 0 -PIoo00000000 -.-I 10000000000 4-1 I . S~ 1 r-I 114 m M r-I to r-1 O tD N f� I k-0 1 0) al •ri 1 m I a a z 0 U x A U z 0 w w-1 cn a E H w a A aH �a ON a wwza 04 040uz a4 Nx Ox4A A w4?W+O �I r-o a tma3= Ln 0 waw c»wH,-Ia LO LONOm �HLO lOLO r-1 r-1 r-1 V' Csa —1 lO M M —4 H H H H H A H H H H H 44 Ga 44 44 Z Ga r24 C+r Gu Gu r-ANMd'IO r-mmCD O 0 O ri m d+ M M License CodV Engineering, Inc. PO Box 341 Norwalk, CA 90651 Ph: 562/868-2252 Fx: 562/868-2552 e-mail: codyengrinc@earthlink.net August 25, 2003 Sent via Facsimile City of Vernon Mr. Woody Natsuhara 4305 S. Santa Fe Avenue Vernon, CA 90058 RE: Seville Avenue Sewer Main Replacement — Contract #565 Dear Mr. Natsuhara: Cody Engineering was the low bidder on the above referenced project. The bid date was October 1, 2002 with an anticipated start date of January 3, 2003. There have been no less than 5 changes in the start date. We are now at the end of August and have September 8 as the target to begin the project. Since the original bid date, all of our insurances from General Liability to Workers Comp have seen an increase of no less than 25 percent, in addition to the increase in the prevailing wage. Furthermorg, most supplier quotes are valid for 30 to 45 days from the quote date. As it stands today, the boring company we listed is declining the project for the reasons previously mentioned, they can't afford to complete the project as shown on their quote dated October 1, 2002. In the past 10 months since the original bid opening, we have had a change order proposal request from Mr. Pin Chan for Concrete Blankets and most recently (last week) were told our crew would have to watch a 45-minute safety video prior to Cody Engineering starting the project. These items were not on the original bid. Therefore, due to the lengthy delays and other bid modifications, we feel we are entitled to adjust our bid to absorb the various increases in cost. Another suggestion would be to release us from the project and send it out for rebid when the City is ready to move forward. We await your comments. Respectfully submitted, CODY ENGINEERING, INC. Bob Kratz President Cc: Mr. Pin Chan