Resolution No. 85491 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 8549 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF VERNON APPROVING AND AUTHORIZING THE EXECUTION OF A FOURTH AMENDMENT TO CONTRACT FOR PROCUREMENT, CONSTRUCTION AND STARTUP BY AND BETWEEN THE CITY OF VERNON AND MARELICH MECHANICAL CO., INC., DBA UNIVERSITY MARELICH MECHANICAL & GALLIERA, INC., DBA TRICO CONSTRUCTION FOR THE MALBURG GENERATING STATION PROJECT WHEREAS, on January 22, 2003, the City Council of the City of Vernon adopted Resolution No. 8115 approving a Contract for Procurement, Construction and Startup (the "Contract") with Marelich Mechanical Co., Inc., dba University Marelich Mechanical & Galliera, Inc., dba Trico Construction, a Joint Venture, ("Marelich"); and WHEREAS, on April 21, 2004, the City Council of the City of Vernon adopted Resolution No. 8435 ratifying the approval of a First Amendment to the Contract for additional services in the sum of $3,009,756 and a Second Amendment to the Contract for additional services in the sum of $1,891,491; and WHEREAS, on August 4, 2004, the City Council of the City of Vernon adopted Resolution No. 8510 approving a Third Amendment to the Contract for additional services; and WHEREAS, on October 6, 2004, the Finance Committee considered the recommendation of Bruce V. Malkenhorst, the Director of Finance, dated September 30, 2004, that an amendment to the Contract with Marelich for additional services in the sum of $1,521,619.00 be approved and executed; and WHEREAS, the City Council of the City of Vernon has determined that, pursuant to the provisions of subsection (a) of Section 2.27 of the Vernon City Code, it is in the public interest and 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 necessity to enter into an amendment to the Contract with Marelich. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF VERNON AS FOLLOWS: SECTION 1: The City Council of the City of Vernon hereby finds and determines that the recitals contained hereinabove are true and correct. SECTION 2: The City Council of the City of Vernon hereby approves the Fourth Amendment to Contract for Procurement, Construction, and Startup with Marelich, in substantially the same form as the copy which is attached hereto as Exhibit A and incorporated by reference. SECTION 3: The City Council of the City of Vernon hereby authorizes the Mayor and the City Clerk to execute said Amendment for, and on behalf of, the City of Vernon. SECTION 4: The City Council of the City of Vernon hereby directs the City Clerk, or his designee, to send one fully executed Amendment to: University Marelich Mechanical Attn. Jay W. McEntire, Sr. Vice President & General Manager 1000 N. Kraemer Place Anaheim, CA 92806-2610 SECTION 5: The City Clerk of the City of Vernon shall certify to the passage of this resolution, and thereupon and thereafter the same shall be in full force and effect. APPROVED AND ADOPTED this 6th day of October, 2004. 7LEONIS C. MALBURG,""Mayor ATTEST: BRUCE V. MALKENHORST, City Clerk - 2 - 1 STATE OF CALIFORNIA ) 2 ) ss COUNTY OF LOS ANGELES ) 3 4 I, BRUCE V. MALKENHORST, City Clerk of the City of Vernon, do 5 hereby certify that the foregoing Resolution, being Resolution No. 6 8549, was duly adopted by the City Council of the City of Vernon at a 7 regular meeting of the City Council duly held on Wednesday, October 6, 8 2004, and thereafter was duly signed by the Mayor of the City of 9 Vernon. 10 11 BRUCE V. MALKENHORST, City Clerk 12 13 (SEAL) 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 3 - EXHIBIT VA& FOURTH AMENDMENT TO CONTRACT FOR PROCUREMENT, CONSTRUCTION, AND STARTUP This Fourth Amendment to Contract for Procurement, Construction, and Startup for the Malburg Generating Station Project, Vernon, California (this "Amendment") is made as of October 6, 2004 by and between The City of Vernon, a municipal corporation (the "City") and Marelich Mechanical Co., Inc. dba University Marelich Mechanical & Galliera, Inc. dba Trico Construction, a Joint Venture (the "Contractor"), and is made with reference to the following: A. The City and the Contractor entered into that certain Contract for Procurement, Construction, and Startup for the Malburg Generating Station Project dated February 3, 2003, as amended on September 10, 2003, March 17, 2004 and August 4, 2004 (collectively, the "Agreement"), pursuant to which the parties agreed that the Contractor would provide for the procurement, construction and.start-up services for the City's development of a Combined Cycle Power Plant (the "Project"), on the terms and conditions described in the Agreement. B. The City and the Contractor have agreed that it would be in the best interest of the Project for the Contractor to perform additional work and provide additional materials and services in connection with the Project under the terms of the Agreement. C. Paragraph 6 of the Agreement requires that changes to the Project requiring expenditures in excess of $20,000 be accomplished by an Amendment to the Agreement. The additional labor and materials required in connection with the Project will exceed $20,000. Therefore, to comply with the terms of the Agreement, the City and the Contractor desire to enter into this Amendment to amend the terms of the Agreement as set forth below. Each initially capitalized term used in this Amendment without definition shall have the meaning ascribed to such term in the Agreement.' THEREFORE, for valuable consideration, the parties agree as follows: 1. Additional Services Required. The City and the Contractor acknowledge and agree that the additional services described in Exhibit "A" to this Agreement, a copy of which is attached hereto and incorporated herein by this reference (collectively, the "Additional Services"), are required in connection with the Project. The Additional Services constitute work that was not originally contemplated by the parties, and is now determined by the parties to be necessary to the Project. This Amendment is entered into solely for the purpose of evidencing the City's approval of the cost components of the items listed in Exhibit "A". The parties specifically acknowledge and agree that this Amendment is not intended to and does not evidence the City's approval or the Contractor's waiver or settlement of any reference to or description of or claim in regard to a time delay or schedule impact that may be set forth in any of the Contractor's cost estimates, whether or not listed in Exhibit "A", all of which are subject to review and evaluation by the City. Contractor hereby waives any claim that the City's execution of this Amendment or payment of the Additional Cost (as described below) constitutes the City's express or implied agreement to any reference in any of the Contractor's cost estimates related to time delays or schedule impacts. 2. Cost of Additional Services. The City and the Contractor agree that the total cost for all labor and materials for the Additional Services is $1,521,619.00 (the "Additional Cost"). The Additional Cost is payable on the terms of the Agreement, following submission and approval of documentation as required by the Agreement. 3. Terms of Additional Services. All Additional Services are to be provided in accordance with the terms of the Agreement, are to meet the standards and specifications and quality of work provisions set forth in the Agreement, and are to be covered by the same warranties or guarantees, if any, that are set forth in the Agreement. 4. Approval by the City_. This Amendment shall be executed by a duly authorized representative of the City following approval of the terms of this Amendment by the City in accordance with City policies and procedures. Oil 5. Remainder of Agreement. Except as specifically modified herein, all terms and conditions of the Agreement are unmodified and remain in full force and effect, and apply to the Additional Work and Additional Costs as if those services and costs were originally included in the Agreement. Executed as of the date first above written. ATTEST: Bruce V. Malkenhorst, City Clerk APPROVED AS TO FORM , Eric T. Fresch, City Attorney Bv: CITY OF VERNON Leonis C. Malburg, Mayor CONTRACTOR Marelich Mechanical Co., Inc. dba University Marelich Mechanical & Galliera, Inc. dba Trico Construction, a Joint Venture By: Signature Date: Name: Title: By: Signature Date: Name: Title: 3 EXHIBIT 0 EXHIBIT A ADDITIONAL WORK CE# Description of Work Amount A IPurchase of COV Gas Equipment $55,735 9E Isaies Tax February 1 - February 29 $5,449 9F ISales Tax March 1 - March 31 $7,892 26 R1 Transportation of Gas Skid and Condenser from Soto Street to jobsite $12,037 34A Added Switch Gear vaults $28,347 34B Change to roadway profile $292,230 35K Provide Hach Panel System $4,648 35L Added Control Valve Cable $14,432 36 Changes to Oily Water Separator Size $5,536 51 Inventory of COV-supplied equipment July 03 - October 03 $336,607 52 Invento of COV-supplied equipment February 04 $8,492 52B Inventory of COV-supplied equipment March 16, 2004 to March 18, 2004 $3,306 52C Inventory of COV-supplied equipment March 2, 2004 to March 12, 2004 $18,829 68 Graqding to remove unforseen duct bank and foundation $28,715 75 Stoppage of work by CBO/Stop Notice #2 9/15/03/NE Corner of Site $43,835 77 Change of Compaction Requirements at HRSG pads $21,381 80 Change of Compaction Requirements for balance of site (90% - 95%) $33,111 82C Survey of Remediation Trench $2,875 91 Change to Piping Material Specification C10 & C11 $17,466 96D Installation of Temporary Grading and Drainage Plan $21,961 106 Change to Tubing Size from .049 to .065 per DCN 037 $10,415 109 Change to Structural Drawing per DCN 038/Civil Only $14,222 112 Change to slope at PDCM $g 972 123 Revise rebar details for the construction joints in the CTG and STG Foundation per DCN 032 $551 128 Alstom Inlet Duct Banks delivered as Knock Down, not Modular Sections as per bid docs $250,000 130 Removal of Overflow Piping per DCN 066 $30,339 131 Additional Block Valves at Pump P1430 A/B Discharge $3,517 132 lInstall PWR to Internal Battery Chargers $11,942 135 IShipping of Alstom-Supplied Handrails for Repair $13,269 A- I EXHWi r A ' ADDITIONAL WORK CE# Description of Work Amount 136 Additional Reinforcement @ HRSG Mat Foundation per DCN 019 $9,606 138 ITrench Plates at 50th Street Storage $12,960 140 Change minimum concrete cover from 3" to 4" for duct banks $12,870 148 Revise thickness of Concrete Grade Rings per DCN 026 $3,293 154 Raise Rebar Mat on Pad # 8 per DCNs 43, 51,63 $345 167 Changes to Raw Water Tank Foundation per DCN 065 1 $19,308 177 Change to Water Stop Location on Pads #68 & 74 $3,677 182A R1 Erection of HRSG Pedestals $3,794 185 B Base for Access Road at Station A / Site Watering $3,855 185C Maintain Access Road $3,676 186 Extra Survey for Pad Certifications $5,713 186A jAdded Survey for Pad Certifications $2,007 186E dded Survey at Blowdown Pits - $931 186C[Added Survey for Pad Certifications $2,229 188 Rebar cost escalation for December 2003 and January 2004 $7,512 189 Recompact and Retest Condensate Pad and Ammonia Sump $1,824 200 Repair to various HRSG Welds $10,191 201 Repair to various HRSG Welds $882 202 IRepair to various HRSG Welds $7,750 202A R1 IRepair to various HRSG Welds $24,992 203 R1 lWeld Repairs to HRSG Inlet Duct $26,582 203A Weld Repairs to HRSG Inlet Duct $18,266 203E Weld Repairs to HRSG Inlet Duct $6,553 256 Dewatering of HRSG Mats $1,542 259 Change to Switch Gear Foundation Pad Per DCN 076 $4,248 270 Move Drainage Swale and add 4 direction changes $1,517 276 Connect Temp Power to CTG for Charges and Heaters $12,152 285 Extended Warranty of Alfa Heat Exchangers $3,149 286 As -Built HRSG Pads $1,474 292 Re -Detail Rebar Clearance on Hairpins per DCN 072 - $146 293 Extend HRSG Pad per DCN 081 $2,464 $1,521,619 A-2 SUPPORTING DOCUMENTS FOURTH AMENDMENT TO CONTRACT FOR PROCUREMENT CONSTRUCTION AND STARTUP This Fourth Amendment to Contract for Procurement, Construction, and Startup for the Malburg Generating Station Project, Vernon, California (this "Amendment") is made as of October 6, 2004 by and between The City of Vernon, a municipal corporation (the "City") and Marelich Mechanical Co., Inc. dba University Marelich Mechanical & Galliera, Inc. dba Trico Construction, a Joint Venture (the "Contractor"), and is made with reference to the following: A. The City and the Contractor entered into that certain Contract for Procurement, Construction, and Startup for the Malburg Generating Station Project dated February 3, 2003, as amended on September 10, 2003, March 17, 2004 and August 4, 2004 (collectively, the "Agreement"), pursuant to which the parties agreed that the Contractor would provide for the procurement, construction and,start-up services for the City's development of a Combined Cycle Power Plant (the "Project"), on the terms and conditions described in the Agreement. B. The City and the Contractor have agreed that it would be in the best interest of the Project for the Contractor to perform additional work and provide additional materials and services in connection with the Project under the terms of the Agreement. C. Paragraph 6 of the Agreement requires that changes to the Project requiring expenditures in excess of $20,000 be accomplished by an Amendment to the Agreement. The additional labor and materials required in connection with the Project will exceed $20,000. Therefore, to comply with the terms of the Agreement, the City and the Contractor desire to enter into this Amendment to amend the terms of the Agreement as set forth below. Each initially capitalized term used in this Amendment without definition shall have the meaning ascribed to such term in the Agreement. THEREFORE, for valuable consideration, the parties agree as follows: 1. Additional Services Required The City and the Contractor acknowledge and agree that the additional services described in Exhibit "A" to this Agreement, a copy of which is attached hereto and incorporated herein by this reference (collectively, the "Additional Services"), are required in connection with the Project. The Additional Services constitute work that was not originally contemplated by the parties, and is now determined by the parties to be necessary to the Project. This Amendment is entered into solely for the purpose of evidencing the City's approval of the cost components of the items listed in Exhibit "A". The parties specifically acknowledge and agree that this Amendment is not intended to and does not evidence the City's approval or the Contractor's waiver or settlement of any reference to or description of or claim in regard to a time delay or schedule impact that may be set forth in any of the Contractor's cost estimates, whether or not listed in Exhibit "A", all of which are subject to review and evaluation by the City. Contractor hereby waives any claim that the City's execution of this Amendment or payment of the Additional Cost (as described below) constitutes the City's express or implied agreement to any reference in any of the Contractor's cost estimates related to time delays or schedule impacts. 2. Cost of Additional Services. The City and the Contractor agree that the total cost for all labor and materials for the Additional Services is $1,521,619.00 (the "Additional Cost"). The Additional Cost is payable on the terms of the Agreement, following submission and approval of documentation as required by the Agreement. 3. Terms of Additional Services. All Additional Services are to be provided in accordance with the terms of the Agreement, are to meet the standards and specifications and quality of work provisions set forth in the Agreement, and are to be covered by the same warranties or guarantees, if any, that are set forth in the Agreement. 4. Approval by the City. This Amendment shall be executed by a duly authorized representative of the City following approval of the terms of this Amendment by the City in accordance with City policies and procedures. 2 5 Remainder of A cement. Except as specifically modified herein, all terms and conditions of the Agreement are unmodified and remain in full force and effect, and apply to the Additional Work and Additional Costs as if those services and costs were originally included in the Agreement. Executed as of the date first above written. CITY OF VERNON By: ATTEST: Leonis C. Malburg, Mayor Bntce .'MalkenhOrst, City Clerk APPROVED 4S TO FORM Eric T. Fresch, City Attorney CONTRACTOR Marehoh Mechanical Co., Inc. dba University Mamlich Mechanical & Galliera, Inc, dba Trico Consttuctio a Joint By; signs Date: -Name-, V A Sid t� St-t�l-En{ Title: &eka — tAckr By: Signature Date: - Name:-.. Title. 3 ' 'n 5. Remainder of Agreement. Except as specifically modified herein, all terms and conditions of the Agreement are unmodified and remain in full force and effect, and apply to the Additional Work and Additional Costs as if those services and costs were originally included in the Agreement. Executed as of the date first above written. ATTEST: Bruce V. Malkenhorst, City Clerk APPROVED AS TO FORM Eric T. Fresc , City Attorney CITY OF VERNON By: J—ep nis C. Malburg, ayor CONTRACTOR Marelich Mechanical Co., Inc. dba University Marelich Mechanical & Galliera, Inc. dba Trico Constru on, a Joint Venture By: i e Date:.. p Name: Title: By: Sure — `� Date: !" o - & . ® T Name:j ID v.& C.aejcA- Title: `rn �9 3 • EXHIBIT A EXHIBIT A ADDITIONAL WORK CE# Description of Work Amount A IPurchase of COV Gas Equipment $55,735 9E Sales Tax February 1 - February 29 $5,449 9F Sales Tax March 1 - March 31 $7,892 Transportation of Gas Skid and Condenser from Soto Street to jobsite 26 R1 $12,037 34A dded Switch Gear vaults $28,347 34B Change to roadway profile $292,230 35K Provide Hach Panel System $4,648 35L Added Control Valve Cable $14,432 36 Changes to Oily Water Separator Size $5,536 Inventory of COV-supplied equipment July 03 - October 03 51 $336,607 52 Inventory of COV-supplied equipment February 04 $8,492 Inventory of COV-supplied equipment March 16, 2004 to March 18, 2004 526 $3,306 Inventory of COV-supplied equipment March 2, 2004 to March 12, 2004 52C $18,829 Graqding to remove unforseen duct bank and foundation 68 $28,715 Stoppage of work by CBO/Stop Notice #2 9/15/03/NE Comer of Site 75 $43,835 Change of Compaction Requirements at HRSG pads 77 $21,381 Change of Compaction Requirements for balance of site (90% - 95%) 80 $33,111 82C Survey of Remediation Trench $2,875 91 Change to Piping Material Specification C10 & C11 $17,466 96D Installation of Temporary Grading and Drainage Plan $21,961 Change to Tubing Size from .049 to .065 per DCN 037 106 $10,415 Change to Structural Drawing per DCN 038/Civil Only 109 $14,222 112 Change to slope at PDCM $8,972 Revise rebar details for the construction joints in the CTG and STG 123 Foundation per DCN 032 $551 Alstom Inlet Duct Banks delivered as Knock Down, not Modular Sections as 128 per bid docs $250,000 130 Removal of Overflow Piping per DCN 066 $30,339 Additional Block Valves at Pump P1430 A/B Discharge 131 $3,517 132 Install PWR to Internal Battery Chargers $11,942 135 Shipping of Alstom-Supplied Handrails for Repair $13.269 A-1