RESOLUTION NO.9040
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF VERNON ACCEPTING THE BID OF AA-1 SERVICES,
INC. FOR THE ELEVATED TANK SEISMIC UPGRADE
AND EXTERIOR PAINT IN ACCORDANCE WITH
CONTRACT NO. 598 OF THE CITY OF VERNON AND
APPROVING THE EXECUTION OF SAID CONTRACT
WHEREAS, Contract No. 598 of the City of Vernon was approved by the City
Council of the City of Vernon pursuant to Resolution No. 8997, and sealed bids were opened on
May 2, 2006; and
WHEREAS, said bids were referred to Samuel Kevin Wilson, Director of
Community Services & Water, who has reported to the City Council under the date of May 10,
2006, recommending that Contract No. 598 for the Elevated Tank Seismic Upgrade and Exterior
Paint be executed with AA-1 Services, Inc. on the basis of its bid in the sum of Five Hundred
Thirty Five Thousand Dollars and no cents ($535,000.00), being the lowest responsible bid
meeting the contract requirements.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF VERNON AS FOLLOWS:
SECTION 1: The City Council of the City of Vernon hereby finds and
determines that the recitals contained hereinabove are true and correct.
SECTION 2: The City Council of the City of Vernon does hereby award
Contract No. 598 to AA-1 Services, Inc. in accordance with the recommendation of Samuel
Kevin Wilson, Director of Community Services & Water, and authorizes the Mayor and Acting
City Clerk to execute said Contract on behalf of the City.
SECTION 3: All other bids are rejected subject to execution of the contract and
the City Treasurer is hereby directed to return unsuccessful bidders any cashier or certified
checks deposited with said bids upon the receipt of an executed contract from AA-1 Services,
Inc. accompanied by all required bonds and certificates.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
SECTION 4: The Acting City Clerk of the City of Vernon shall certify to the
passage of this resolution and thereupon and thereafter the same shall be in full force and effect.
ATTEST:
V.
APPROVED AND ADOPTED this 24 h day of May 2006.
, Acting City Clerk
-2-
LEONIS C. MAL URG, yor
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
STATE OF CALIFORNIA )
)ss
COUNTY OF LOS ANGELES )
I, BRUCE V. MALKENHORST, JR., Acting City Clerk of the City of Vernon,
do hereby certify that the foregoing Resolution, being Resolution No. 9040, was duly adopted by
the City Council of the City of Vernon at an adjourned regular meeting of the City Council duly
held on Wednesday, May 24, 2006 and thereafter duly signed by the Mayor of the City of
Vernon. zn
(SEAL)
BRUC
Acting
-3-
us
quw
CITY OF VERNON (_�
COMMLiITY SERVICES & WATER D'hYARTMENT
CONTRACT CHANGE ORDER NO. 1 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS
PROJECT: Elevated Tank Seismic Upgrade and Exterior Paint CONTRACT NO. 598
TO: AA-1 Services, Inc. CONTRACTOR
REQUESTED BY: City
You are hereby directed to make the herein described changes from the plans and specifications or do the following described
worx not incractea m the
on this contract.
CHANGE ORDER
Instead of performing the Contract within 80 calendar days as required in the specifications, you are
hereby authorized to perform the Contract within 140 calendar days as requested in the attached
correspondence.
No adjustment of compensation will be allowed for this change.
Contract Amount (Base Bid) ............................................... $ 535,000.00
Amount of This Change Order ............................................. $ 0.00
Amount of Previous Change Order .................................. ... $ 0.00
Total Change Orders ..................................................... $ 0.00
Amount of Previous Extra Work Order ........................................ $ 0.00
Modified Contract Amount ... ..... ... .. .. ... $ 535,000.00
By reason of this order the time of 60 Calendar Days.
completion will be adiusted as follows:
Approved: 20n! fM Date: A T.,f Jig,
Director o o unity�Ser ices & Water
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
Accepted: Date: Contractor:
By: Title: -�I-eyla /'1 C! � J,—
xc. riiiancciiccsiucnt nngineerirro]ect rite/uonrracioi
RECEVEO
I OT vER
SEP 2`
Community
Selves?
�A�i 6 @ r`O��acr tN9��Re
COMMUNITY SERVICES & WATER DEPARTMENT
OFFICE MEMORANDUM
TO: Bruce V. Malkenhorst Jr., Acting City Clerk
/OvPP-V�D
FROM: Samuel Kevin Wilson, Director of Community Services & Water
DATE: September 19, 2006
SUBJECT: Contract Number 598 — Change Order No.1
AA-1 Services, Inc., the primary contractor for the Elevated Tank Seismic Upgrade and
Exterior Paint, Contract No. 598, has submitted a request to increase the number of days to complete
the contract from 80 calendar days as specified in the contract to 140 calendar days.
Harper & Associates Engineering, Inc. was contracted by the City to write the contract
specifications and perform the welding and coating inspection for this project. Harper & Associates
believes that their original estimate of 80 calendar days to complete the contract may have only
included the seismic upgrade and exterior painting portion and did not allow any time for scaffolding
installation/removal and painting of the logo. Harper & Associates reviewed the request and agree that
140 calendar days to complete the contract is a justifiable request.
There is no additional cost for this Change Order. .Staff has reviewed the request and found it
acceptable. It is recommended that you authorize the Department to proceed with the Change Order,
SKW/md
Enclosures
C'eq of VE8
Lys
COMMUNITY SERVICES & WATER DEPARTMENT
OFFICE MEMORANDUM
TO: Bruce V. Malkenhorst Jr., Acting City Clerk
/vPP�Vn
FROM: Samuel Kevin Wilson, Director of Community Services & Water
DATE: September 19, 2006
SUBJECT: Contract Number 598 — Change Order No.1
AA-1 Services, Inc., the primary contractor for the Elevated Tank Seismic Upgrade and
Exterior Paint, Contract No. 598, has submitted a request to increase the number of days to complete
the contract from 80 calendar days as specified in the contract to 140 calendar days.
Harper & Associates Engineering, Inc. was contracted by the City to write the contract
specifications and perform the welding and coating inspection for this project. Harper & Associates
believes that their original estimate of 80 calendar days to complete the contract may have only
included the seismic upgrade and exterior painting portion and did not allow any time for scaffolding
installation/removal and painting of the logo. Harper & Associates reviewed the request and agree that
140 calendar days to complete the contract is a justifiable request.
There is no additional cost for this Change Order. Staff has reviewed the request and found it
acceptable. It is recommended that you authorize the Department to proceed with the Change Order.
SKW/md
Enclosures
CITY OF VERNON
COMMUNITY SERVICES & WATER DEPARTMENT
CONTRACT CHANGE ORDER NO. 1 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS
PROJECT: Elevated Tank Seismic Upgrade and Exterior Paint CONTRACT NO. 598
TO: AA-1 Services, Inc. CONTRACTOR
REQUESTED BY: C
You are hereby directed to make the herein described changes from the plans and specifications or do the following described
work not included m the plans and specifications on this contract.
CHANGE ORDER
Instead of performing the Contract within 80 calendar days as required in the specifications, you are
hereby authorized to perform the Contract within 140 calendar days as requested in the attached
correspondence.
No adjustment of compensation will be allowed for this change.
Contract Amount (Base Bid) ............................................... $ 535,000.00
Amount of This Change Order ............................................. $ 0.00
Amount of Previous Change Order .................................. .... $ 0.00
Total Change Orders ....................... $ 0.00
Amount of Previous Extra Work Order ........................................ $ 0.00
Modified Contract Amount .. ... .. .. ... .. . $ 535,000.00
... .. ... .. .. ... .... .... ... ...
By reason of this order the time of S 60 Calendar Da
completion will be adjusted as follows: y
Approved: Date:
Director of Community Services & Water
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
Accepted: Date: Contractor:
By: Title:
11- i 1VJ-L 111G\.V11ll[LL:LVl
no V
001 CITY OF VERNON �G� D
1
ICeS COMMUNITY SERVICES & WATER DEPARTMENT Zwte
COMMOPIC NTRACT CHANGE ORDER NO. 2 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS
PROJECT: Elevated Tank Seismic Upgrade and Exterior Paint CONTRACT NO. 598
TO: AA-1 Services, Inc. CONTRACTOR
REQUESTED BY: City
You are hereby directed to make the herein described changes from the plans and specifications or do the following described
worx not included in the plans and specifications on this contract.
CHANGE ORDER
In lieu of performing a sweep -blast and overcoat of the existing coating system on the Elevated
Tank as required in the specifications, you are hereby directed to perform a commercial -blast (SP-
6) to the entire tank and structure completely removing the existing coating system for an additional
sum of $124,690. The final coating system shall be in accordance with the system specified in the
contract.
Contract Amount (Base Bid) ....................... $ 535,000.00
Amount of This Change Order ............................................. $ 124,690.00
Amount of Previous Change Order .................................. .... $ 0.00
Total Change Orders ..................................................... $ 124,690.00
Amount of Previous Extra Work Order ........................................ $ 0.00
Modified Contract Amount $ 659,690.00
By reason of this order the time of $CJ Calendar Da
completion will be adjusted as follows: ys a
Approved: Date: I Z 07
Director of unity Serv' es & Water
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
Accepted: Dater Contractor: A4 Jai"yt
BY Title: ./ " / -7e s u re
"___�, .�........,.... .....b...vvarai vJ....�i uan wuuaV Wl
RECEIVED A .
FEB 2 0 2001
Community Services
s
r4sYEGY .NOVSC .
COMMUNITY SERVICES & WATER DEPARTMENT
OFFICE MEMORANDUM
TO: Eric Fresh, Acting City Administrator E co M M (5tj b 15p
rr .'
FROM: Samuel Kevin Wilson; Drector of Community Services and Water �C �1►�1��
DATE: February 8, 2007 Wga v Eb
SUBJECT: CONTRACT NO.598 — REQUEST FOR CHANGE ORDER NO.2
CC 2-11-0f Q1
After making a closer evaluation of the existing coating system and observing several sweep -blast tests
performed on the tank structure the Community Services Staff believes that performing a sweep blast and
coating over the existing coating system as required in the specifications may ngtnbe in the City's best interest.
Due to the configuration and height of the tank, the cost associated with recoating or repairing a failed coating
system would be very high. Under the given circumstances completely removing the existing coating will
eliminate the chance of failure between the coating systems and leave the City with a more reliable and longer
lasting coating system.
AA-1 Services, Inc., the primary contractor for the Elevated Tank Seismic Upgrade and Exterior Paint,
Contract No. 598, Inc. is very concerned with the new coating system failing because it has been applied over a
forty-six year old coating system that is brittle and has been fractured or damaged by the sweep -blast process.
The configuration of the scaffolding and shrink-wrap make it very difficult and in some places. almost
impossible to perform a consistent sweep -blast without partially removing and/or fracturing the existing coating
system. The concern is that the tension created when the new coating system cures will cause the existing
coating to lift or separate from the steel or undercoat in the areas that have been fractured or damaged. Due to
the great expense to access and coat a structure of this size AA-1 Services, Inc. believes it is in the City's best
interest to completely remove the existing coating at this time eliminating any chance of a failure between the
two coating systems.
Tnemec Company, Inc. is the coating manufacture providing the coating materials for this project.
After visiting the site and observing the existing coating Tnemec feels that there is a high risk of failure in .
performing an overcoat on the existing coating and do not recommend it on this elevated tank. Considering the
age and type. of coating on the tank, Tnemec recommends performing a commercial -blast and. completely
remove the existing coating system before applying the new coating.
Harper & Associates Engineering, Inc. was contracted by the City to write the contract specifications
and perform full time welding and coating inspection for this project. They feel that under normal circumstances
a sweep -blast would be adequate however with the confined work area of the scaffolding it will be very difficult
to perform a consistent sweep -blast without partially removing and/or fracturing the existing coating system.
Harper agrees that the areas, which have been damaged and not properly prepped, are prone to failure. They also
agree that applying a new coating system directly to properly prepared steel is superior to a coating system
applied over an existing coating.
After careful review and considering the high cost to recoat the elevated tank I believe that it is in the
City's best interest to approve Change Order No. 2 for an additional sum of $124,690 to perform a commercial -
blast and completely remove the existing coating system. In addition, the number days to complete the
contract should be increased from 140 calendar days as specified in the contract to 225 calendar days.
Please advise if you concur with the Department's recommendation to approve Change Order No. 2.
Thank you.
SKW/md
Enclosure
of E'ER
S1VELT -INOJ
ILI 1-
COMMUNITY SERVICES & WATER DEPARTMENT
OFFICE MEMORANDUM
TO: Eric Fresh, Acting City Administrator CC.dH156
FROM: Samuel Kevin Wilson Director of Community Services and Water rG
►1��
DATE: February 8, 2007 A i Pgav ED
SUBJECT: CONTRACT NO.598 — REQUEST FOR CHANGE ORDER NO.2 C C 2-11-0/0
1
After making a closer evaluation of the existing coating system and observing several sweep -blast tests
performed on the tank structure the Community Services Staff believes that performing a sweep -blast and
coating over the existing coating system as required in the specifications may not be in the City's best interest.
Due to the configuration and height of the tank, the cost associated with recoating or repairing a failed coating
system would be very high. Under the given circumstances completely removing the existing coating will
eliminate the chance of failure between the coating systems and leave the City with a more reliable and longer
lasting coating system.
AA-1 Services, Inc., the primary contractor for the Elevated Tank Seismic Upgrade and Exterior Paint,
Contract No. 598, Inc. is very concerned with the new coating system failing because it has been applied over a
forty-six year old coating system that is brittle and has been fractured or damaged by the sweep -blast process.
The configuration of the scaffolding and shrink-wrap make it very difficult and in some places almost
impossible to perform a consistent sweep -blast without partially removing and/or fracturing the existing coating
system. The concern is that the tension created when the new coating system cures will cause the existing
coating to lift or separate from the steel or undercoat in the areas that have been fractured or damaged. Due to
the great expense to access and coat a structure of this size AA-1 Services, Inc. believes it is in the City's best
interest to completely remove the existing coating at this time eliminating any chance of a failure between the
two coating systems.
Tnemec Company, Inc. is the coating manufacture providing the coating materials for this project.
After visiting the site and observing the existing coating Tnemec feels that there is a high risk of failure in
performing an overcoat on the existing coating and do not recommend it on this elevated tank. Considering the
age and type of coating on the tank, Tnemec recommends performing a commercial -blast and completely
remove the existing coating system before applying the new coating.
Harper & Associates Engineering, Inc. was contracted by the City to write the contract specifications
and perform full time welding and coating inspection for this project. They feel that under normal circumstances
a sweep -blast would be adequate however with the confined work area of the scaffolding it will be very difficult
to perform a consistent sweep -blast without partially removing and/or fracturing the existing coating system.
Harper agrees that the areas, which have been damaged and not properly prepped, are prone to failure. They also
agree that applying a new coating system directly to properly prepared steel is superior to a coating system
applied over an existing coating.
1
After careful review and considering the high cost to recoat the elevated tank I believe that it is in the
City's best interest to approve Change Order No. 2 for an additional sum of $124,690 to perform a commercial -
blast and completely remove the existing coating system. In addition, the number days to complete the
contract should be increased from 140 calendar days as specified in the contract to 225 calendar days.
Please advise if you concur with the Department's recommendation to approve Change Order No. 2.
Thank you.
SKW/md
Enclosure
CITY OF VERNON
COMMUNITY SERVICES & WATER DEPARTMENT
CONTRACT CHANGE ORDER NO. 2 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS
PROJECT: Elevated Tank Seismic Upgrade and Exterior Paint CONTRACT NO. 598
TO: AA-1 Services, Inc. CONTRACTOR
REQUESTED BY: Ci
You are hereby directed to make the herein described changes from the plans and specifications or do the followine described
worK not included in the plans and
on this contract.
CHANGE ORDER
In lieu of performing a sweep -blast and overcoat of the existing coating system on the Elevated
Tank as required in the specifications, you are hereby directed to perform a commercial -blast (SP-
6) to the entire tank and structure completely removing the existing coating system for an additional
sum of $124,690. The final coating system shall be in accordance with the system specified in the
contract.
Contract Amount (Base Bid) ............................................... $ 535,000.00
Amount of This. Change Order ............................................. $ 124,690.00
Amount of Previous Change Order .................................. .... $ 0.00
Total Change Orders ........................................ $ 124,690.00
Amount of Previous Extra Work Order ........................................ $ 0.00
Modified Contract' Amount ... .. ... $ 659,690.00
By reason of this order the time of S 85 Calendar Da
completion will be adjusted as follows: y
Approved:
Date:
Director of Community Services & Water
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
Accepted: Date:
Contractor:
Title:
nn 1 OLn V.LULO IIYL..
10 002/004
/11
Feb ru a.ry 8, 2007
,�M--1 Services, Inc.
"A COMPLETE PAINTING & COATING SERVICE"
Sirice 1946
City of Vernon
Department of Community Services
4305 Santa Fe Ave.,
Vernon, CA, 90058
Reference: Contract #598 Elevated Tank Seismic Upgrade & Exterior Painting
Subject: Change in scope of Painting Specifications
Attention: Mr. Mike DaFIank
Gentlemen,
f3eeaLiSC dour (Treat concern regarding the present specification requiring a sweep blast surf ice
preparation to the existing coating, it is AA-1 Services determination to provide the City an, lternatc
scope and price for this project that will be more attractive to the City.
This alternate proposal is to blast the entire tank and s1ruoturc to SP-6 fully removing and ab iting the
exiting coating, and apply 2 coats of epoxy and a urethane finish.
TI1c benefits of this system when compared to the current scope are:
1) A longer life guectancy for the coating.
An epoxy/urethane syste(nn coated over SP-6 blasted steel has a life expectancy rated it 20 years
by coating; manufacturers, which is what the existing codling would Have been rated < s when
'first applied 30 plus years ago. So if applied properly it is undeniable the City WQL1ld le getting
a far superior product than any kind of overcoat system_
The weakest link in the ovcrcoaling systerrt currently specified, is the bond between t ie top
coat of the existing coating and the primer of the existing coating, which after 30 yea -s can it1
noway be considered preferable to any part ofan epoxy/urethane system over blaster I steel.
This is without even taking into account the uundeniable, damage done to the existing I:oating/
substrate by sweep -blasting, and the spot damage to the primer where the swcep-blas ing is
inevitably perlonxled too aggressively, and the weak bond between the new and exist ng
coating that the sweep -blast doesn't touch due to the speed we must move the nozzle to keep
fi-om tearing up the coating.
Simply put it's inconceivable for the coating specified currently could give you a life
expectancy close to this altorrlativc, and has exponentially higher chance of'tna'or 1ai Lire in the
short t crni.
tiieflM6
15117 ILLINOIS AVENUE - PARAMOUNT. CALIFORNIA 90723-4187
3e�eeiiUlMv
(5f�2) �3- �71 a - (323) 9'Y9-0671 • Fax (562) F338-4903 - NV (702) 643-S225 GORTR�TO\�
•� ►W rca
CA LICENSE NO, 202848 C-33 - NV LICENSE NO. 00409a9 - AZ LICENSE NO. 10873-3
v �,! von cvv i io. v i rnn U0400040VO KH 1 S;EHVlUES 1NU.
003/004
2) Removal of Lead J, <<bility —
By removing the coating by SP-6 blasting we are relinquishing the eity's cradle to grv.ve
liability for lead.
3) Aesthetic Appeal -
After a sweep -blast the excessively prepared surfaces where the coating has been rcrr oved to
the primer or steel, the uneven and rough appearance will be readily visible, after the new
coating has been applied. With our proposed system the finish coating will be as smo )th and
shizuiy.
The additional cost to the contract to perform this system is $IZ4,690
Considering the cost to scaffold and contain.the tank ofmore than $300,000 this option may ultimately
be more cost effective_
Please consider this proposal and let us know what you think. We enjoy talking to you to dis.,-uss this
or other optioxns. Also, if our proposal is accepted we wi l I need until April 30 to complete thi - project.
Enclosed is our proposed schedule.
Respectful ly,
tt r on,
Project Manager
Painting Service .Tne.
CITY OF VERNON
COMMUNITY SERVICES & WATER DEPARTMENT
CONTRACT CHANGE ORDER NO. 3 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS
PROJECT: Elevated Tank Seismic Upgrade and Exterior Paint CONTRACT NO. 598
TO: AA-1 Services, Inc. CONTRACTOR
REQUESTED BY: City
You are hereby directed to make the herein described changes from the plans and specifications or do the following described
wortc not tncivaea in the plans ana specifications on this contract.
CHANGE ORDER
Replace all vertical uprights, all nuts and bolts and all screen materials on the center vent per
Harper & Associates Engineering, Inc. recommendations contained in their letter dated February
28, 2007 for an additional sum of $7,900.
Contract Amount (Base Bid) ............................................... $ 535,000.00
Amount of This Change Order ............................................. $ 7,900.00
Amount of Previous Change Order .................................. .... $ 124,690.00
Total Change Orders ..................................................... $ 132,590.00
Amount of Previous Extra Work Order ........................................ $ 0.00
Modified Contract Amount $ 667,590.00
By reason of this order the time of 0 Cale�td Days
completion will be adjusted as follows:
Approved:
Date: =i Zd'G7
"Plr(5cWt-CoffimufPity'Services & Water
We, the undersigned Contractor, Have given careful consideration to the change proposed and hereby agree, if this proposal is approved that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perfonn all services necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
•( � n _
Accepted: Date: ���� Contractor: -5nrK(S 7!^Lc ,
Title: AT-elolra"10-"'
xc:
File/Contractor
COMMUNITY SERVICES & WATER DEPARTMENT
OFFICE MEMORANDUM
TO: Eric Fresh, Acting City Administrator
FROM: Samuel Kevin Wilson, Director of Community Services and Water
DATE: March 21, 2007
SUBJECT: CONTRACT NO.598 — CHANGE ORDER NO. 3
While preparing to blast and coat the center vent and roof portion of the elevated tank AA-1 Services,
Inc., the primary contractor for the Elevated Tank Seismic Upgrade and Exterior Paint, Contract No. 598,
noticed excessive corrosion on the center vent and screening.
Harper & Associates Engineering, Inc., the consultant contracted by the City to write the contract
specifications and perform welding and coating inspection for this project, was asked to evaluate the condition
of the center vent and submit a recommendation for repair. Harper & Associates Engineering, Inc. recommends
replacing all of the vertical uprights, all nuts and bolts and all screen materials on the center vent.
AA-1 Services, Inc, has agreed to repair the center vent per Harper & Associates Engineering, Inc.
recommendations for and additional sum of $7,900.
After evaluating the condition of the center vent the Community Services & Water Department staff
agrees that the above -mentioned repairs are necessary. Enclosed herewith is an executed original of Change
Order No. 3 for your file.
SKW/md/ca
Enclosure
CITY OF VERNON
COMMUNITY ®Ol\ UN Y SERVICES & WATER DEPARTMENT
N\S TRA IANGE ORDER NO. 4 SUPPLEMENT NO. SHEET 1 OF 1 SHEETS
� Sep
® CT: Elevated Tank Seismic Upgrade and Exterior Paint CONTRACT NO. 598
TO: AA-1 Services, Inc.
REQUESTED BY:
CONTRACTOR
You are hereby directed to make the herein described changes from the plans and specifications or do the following described
worx not mcluaea in the plans ana specitcations on this contract.
CHANGE ORDER
Due to the additional time required to individually shrink-wrap each leg and the support structure
between them, an additional 57 calendar days will be added to the Contract. All work shall be
completed no later than July 4, 2007. Any costs for additional coating inspection over forty hours
per week shall be paid by AA-1 Services, Inc. and deducted from the total Contract costs.
No other adjustment of compensation will be allowed for this change.
Contract Amount (Base Bid) ............................................... $ 535,000.00
Amount of This Change Order .............................. . .............. $ 0.00
Amount of Previous Change Order .................................. .... $ 132,590.00
Total Change Orders ..................................................... $ 132,590.00
Amount of Previous Extra Work Order .......... $ 0.00
Modified Contract Amount $ 667,590.00
.................... ....... ....... ...........
By reason of this order the time of 57 Calendar D S
completion will be adjusted as follows:
Approved: "//ZDate: 2-5 07
Directo 'nit S rvices &Water
We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved that we will provide all
equipment, furnish all materials, except as may otherwise be noted above, and perform all set -vices necessary for the work above specified, and will accept as full
payment therefor the prices shown above.
Accepted: Date: / J 67 Contractor: �' / �eyV f zz'r Zh C
By: Title: ete'4r '— T -CG' S'u��P�"
xa Finance/Reside Engineer/Project File/Contractor
/11
,Jg1- 1 Serrices, Inc.
'A COMPLETE PAINTINGS COATING SERVICE"
Vince 1946
City of Vernon
Department of Community Services & Water
4305 Santa Fe Ave.
Vernon, CA. 90058
Attention: Mr. Michael De Frank, Project Engineer.
R.efe_rence: Contract #598 Elevated Tank Seismic upgrade and Exterior Paint.
Subject: Job Completion Schedule.
Gentlemen;
RECEIVED
MAY A 7 2007
Community Services
As you are aware of the difficulty in the containment of the structural members and legs
on reference job. AA-1 assumes that the City and Harper Engineering approve of the
process that was established this last week and that we can continue until the job is
complete.
Because of the additional time it takes to piece meal the,wrapping of each leg and the
structural members the time for completion has to be extended. Per our discussion on the
job site, I would give you the date that we would be 100% complete including the two
weeks of scaffold removal, that date is July 4, 2007.
Please confirm the above date for completion.
Sincerely;
PAINTING
15117 ILLINOIS AVENUE • PARAMOUNT, CALIFORNIA 90723-4187 DECORATING
(5623 633-5718 • (323) 979-0671 • Fax (562) 633-4903 • NV (702) 643-6995 CONTRACTORS
of AMERKA
CA LICENSE NO. 202648 C-33 • NV LICENSE NO. 0040969 • AZ LICENSE NO. 109733 m
of VER
0*",EXY IN"J�
COMMUNITY SERVICES & WATER DEPARTMENT
OFFICE MEMORANDUM
TO: Eric Fresh, City Administrator
FROM: Samuel Kevin Wilson"; Director of Community Services and Water
DATE: June 25, 2007
SUBJECT: CONTRACT NO.598 — CHANGE ORDER NO. 4
AA-1 Services, Inc., the primary contractor for the Elevated Tank Seismic Upgrade and
Exterior Paint, Contract No. 598, has submitted a request to extend the completion date of the contract
to July 4, 2007. This extension will add an additional 57 calendar days to the contract.
Due to the configuration of the elevated tank's support structure and legs, the scaffolding
engineer for AA-1 Services, Inc. is unable to meet wind load calculations if the entire support structure
is encapsulated with shrink-wrap as originally planned when bidding the project. This means that each
leg and the support structure between them must be wrapped individually. Unfortunately, wrapping
each leg and the sections between the legs individually has proven to be a very slow and time-
consuming process.
City staff has reviewed the encapsulation process and feels that AA-1 Services, Inc. is working
diligently to complete the project in a timely manner and agrees that a time extension is justified. AA-1
Services, Inc. is not requesting additional funds for this Change Order however there will be additional
costs associated with the added time required for the coating inspection performed by Harper and
Associates Engineering, Inc. The City shall pay for required coating inspection up to forty hours per
week and any costs for additional coating inspection shall be paid by AA-1 Services, Inc. and deducted
from the total Contract costs.
SKW/md