Resolution No. 90753
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 9075
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
VERNON APPROVING AND RATIFYING THE EXECUTION OF AN
INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT BY
AND BETWEEN THE CITY OF VERNON AND SOUTHERN
CALIFORNIA EDISON COMPANY REGARDING THE VERNON
POWER PLANT
WHEREAS, the City of Vernon is in the process of developing
a natural gas -fired combined cycle power plant located within City
limits and interconnected to Southern California Edison Company's
("SCE") Laguna Bell Substation 230 kV bus officially named the Vernon
Power Plant (the "Vernon Power Plant Project") for the purpose of
installing additional generating capacity that will yield an
efficient, cost-effective, and reliable source of electric generation
to the City of Vernon; and
WHEREAS, the City is in the process of obtaining all the
necessary certifications and licenses associated with the building of
the Vernon Power Plant Project; and
WHEREAS, both the City of Vernon and SCE are Participating
Transmission Owners ("PTO") with the California Independent System
Operator ("ISO"); and
WHEREAS, on October 12, 2005, the City Council of the City
of Vernon adopted Resolution No. 8873 approving an Interconnection
System Impact Study with SCE to assess the impact of interconnecting
the Vernon Power Plant Project to the ISO Controlled Grid at an output
of 610 mW (net); and
WHEREAS, the City of Vernon desires to interconnect an
additional 304 mW to the proposed 610 mW Vernon Power Plant, resulting
in a total maximum net output of 914 mW (the "VPP Expansion Project");
1
2
3
4
5
6
7
8
9
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Hand
and
WHEREAS, the Vernon Power Plant Project is considered a
Large Generating Facility and in accordance with the Cal -ISO Large
Generator Interconnection Procedure, SCE must perform an additional
Interconnection System Impact Study to assess the impact of the VPP
Expansion Project; and
WHEREAS, the City's Light & Power Department desires to
engage the services of SCE to perform the necessary impact study in
accordance with the terms and conditions of an Interconnection System
Impact Study Agreement (the "Agreement"); and
WHEREAS, in order to maintain the demanding licensing and
certification schedule and avoid the delay of SCE's completion of the
study which could potentially impact the City's data adequacy
responses to the California Energy Commission, the Acting City Clerk
executed the Agreement with SCE on June 15, 2006, and paid the deposit
of costs of $50,000.00, subject to ratification by the City Council.
WHEREAS, the City Council of the City of Vernon has
determined that, pursuant to the provisions of subsection (a) of
Section 2.27 of the Vernon City Code, it is in the public interest and
necessity to enter into an agreement with SCE.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF VERNON AS FOLLOWS:
SECTION 1: The City Council of the City of Vernon hereby
finds and determines that the recitals contained hereinabove are true
and correct.
SECTION 2: The City Council of the City of Vernon hereby
approves and ratifies the execution of the Interconnection System
Impact Study Agreement with Southern California Edison Company by the
- 2 -
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Acting City Clerk on June 15, 2006, a copy of which is attached hereto
as Exhibit A and incorporated by reference, and approves the payment
of costs in advance in the sum of $50,000.00.
SECTION 3: The City Council of the City of Vernon hereby
approves and ratifies the payment of costs in advance in the sum of
$50,000.00.
SECTION 4: The Acting City Clerk of the City of Vernon
shall certify to the passage of this resolution, and thereupon and
thereafter the same shall be in full force and effect.
APPROVED AND ADOPTED this.218t day of June, 2006.
ATTES
BRUCEf. MMLKENHORST, JR.
Actin C' v Clerk
- 3 -
a2,Z6tr�
THOMAS A. IBARRA, Mayor Pro Tem
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
STATE OF CALIFORNIA )
) ss
COUNTY OF LOS ANGELES )
I, BRUCE V. MALKENHORST, JR., Acting City Clerk of the City of
Vernon, do hereby certify that the foregoing Resolution, being
Resolution No. 9075, was duly adopted by the City Council of the City
of Vernon at a regular meeting of the City Council duly held on
Wednesday, June 21, 2006, and thereafter was duly signed by the Mayor
Pro Tem of the City of Vernon. ll
(SEAL)
- 4 -
BRUq,,,V. MALKENHORST, JR.
Acting City Clerk
EXHIBIT
&I-
CITY OF VERNON —
SOUTHERN CALIFORNIA EDISON COMPANY
INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT
(Vernon Power Plant Expansion)
THIS AGREEMENT is made and entered into this]"ay of 5�, 2006
by and between the City of Vernon, a municipal corporation organized and existing
under the laws of the State of California, ("Interconnection Customer") and Southern
California Edison Company, a corporation existing under the laws of the State of
California, ("Participating TO"). The Interconnection Customer and the Participating TO
each may be referred to as a "Party," or collectively as the "Parties."
RECITALS
WHEREAS, the Interconnection Customer is proposing to develop a Large
Generating Facility or generating capacity addition to an existing Generating Facility
consistent with the Interconnection Request submitted by the Interconnection Customer
dated April 12, 2006; and
WHEREAS, the Interconnection Customer desires to interconnect the Large
Generating Facility with the ISO Controlled Grid; and
WHEREAS, the Interconnection Customer has requested the Participating TO to
perform an Interconnection System Impact Study to assess the impact of
interconnecting the Large Generating Facility;
NOW, THEREFORE, in consideration of and subject to the mutual covenants
contained herein the Parties agree as follows:
1.0 When used in this Agreement, with initial capitalization, the terms
specified shall have the meanings indicated in the ISO's FERC-approved
Standard Large Generation Interconnection Procedures ("LGIP")°or the
Master Definitions Supplement, Appendix A to the ISO Tariff, as
applicable.
2.0 The Interconnection Customer elects and the Participating TO shall cause
to be performed an Interconnection System Impact Study consistent with
Section 7 of the LGIP in accordance with the ISO Tariff.
3.0 The scope of the Interconnection System Impact Study shall be subject to
the assumptions set forth in Attachment A to this Agreement.
4.0 The Interconnection System Impact Study will be based upon the
technical information provided by the Interconnection Customer in the
Interconnection Request, .subject to any modifications in accordance with
Section 4.4 of the LGIP. The Participating TO reserves the right to
request additional technical information from the Interconnection
Customer as may reasonably become necessary consistent with Good
Utility Practice during the course of the Interconnection System Impact
Study. If the Interconnection Customer modifies its designated Point of
Interconnection, Interconnection Request, or the technical information
provided therein is modified, the time to complete the Interconnection
System Impact Study may be extended.
5.0 The Interconnection System Impact Study report shall provide the
following information:
identification of any circuit breaker short circuit capability limits
exceeded on the Participating TO's electric system as a result of
the interconnection;
identification of any thermal overload or voltage limit violations on
the Participating TO's electric system resulting from the
interconnection;
identification of any instability or inadequately damped response to
system disturbances on the Participating TO's electric system
resulting from the interconnection;
a description and.non-binding, good faith estimated cost of facilities
on the Participating TO's electric system required to interconnect
the Large Generating Facility to the Participating TO's portion of
the ISO Controlled Grid and to address the identified short circuit,
instability, and power flow issues on the Participating TO's portion
of the ISO Controlled Grid; and
if the Participating TO is an interconnecting Participating TO for the
Large Generating Facility, a Deliverability Assessment on the ISO
Controlled Grid pursuant to Section 3.3 of the LGIP.
6.0 The Interconnection Customer shall provide a deposit of $50,000 for the
performance of the Interconnection System Impact Study. The
Participating TO's good faith estimate for the time of completion of the
Interconnection System Impact Study is one hundred twenty (120)
Calendar Days after the receipt of the executed Agreement, $50,000
study payment and technical data in accordance with Attachment A to
Appendix 1 of the LGIP.
Following the issuance of the Interconnection System Impact Study, the
Participating TO shall charge and the Interconnection Customer shall pay
the actual costs of the Interconnection System Impact Study, inclusive of
2
any re -studies and amendments to the Interconnection System Impact
Study, pursuant to Section 9 of this Agreement.
Any difference between the deposit made toward the Interconnection
System Impact Study, amendments and re -studies to the Interconnection
System Impact Study, and the actual cost of the study shall be paid by or
refunded to the Interconnection Customer, as appropriate in accordance
with Section 13.3 of the LGIP.
7.0 Pursuant to Section 3.7 of the LGIP, the ISO will coordinate the conduct
of .any studies required to determine the impact of the Interconnection
Request on Affected Systems. The Participating TO may provide a copy
of the Interconnection System Impact Study results to an Affected System
Operator and the Western Electricity Coordinating Council. Requests for
review and input from Affected System Operators. or the Western
Electricity Coordinating Council may arrive at any time prior to
interconnection, and a revision of the Interconnection System Impact
Study or re -study may be required in such event.
8.0 Substantial portions of technical data and assumptions used to perform
the Interconnection System Impact Study, such as system conditions,
existing and planned generation, and unit modeling, may change after the
Participating TO provides the Interconnection System Impact Study
results to the Interconnection Customer. Study results will reflect
available data at the time the Participating TO provides the
Interconnection System Impact Study to the Interconnection Customer.
The Participating TO shall not be responsible for any additional costs,
including, without limitation, costs of new or additional facilities, system
upgrades, or schedule changes, that may be incurred by the
Interconnection Customer as a result of changes in such data and
assumptions.
9.0 In the event that a re -study or amendment of the Interconnection System
Impact Study, is required, the Participating TO shall provide notification of
the need for such re -study or amendment, and the Interconnection
Customer shall provide direction as to whether to proceed with the re-
study or amendment and any associated deposit payment pursuant to
Section 7.6 or Section 12.2.4 of the LGIP, as applicable.
10.0 The Participating TO shall maintain records and accounts of all costs
incurred in performing the Interconnection System Impact Study, inclusive
of any re -studies or amendments thereto, in sufficient detail to allow
verification of all costs incurred, including associated overheads. The
Interconnection Customer shall have the right, upon reasonable notice,
within a reasonable time at the Participating TO's offices and at its own
expense, to audit the Participating TO's records as necessary and as
appropriate in order to verify costs incurred by the Participating TO. Any
audit requested by the Interconnection Customer shall be completed, and
written notice of any audit dispute provided to the Participating TO
representative, within one hundred eighty (180) Calendar Days following
receipt by the Interconnection. Customer of the Participating TO's
notification of the final costs of the Interconnection System Impact Study,
inclusive of any re -study or amendment thereto.
11.0 In accordance with Section 3.8 of the LGIP, the Interconnection Customer
may withdraw its Interconnection Request at any time by written notice to
the ISO. Upon receipt of such notice, this Agreement shall terminate.
12.0 Pursuant to Section 7.2 of the LGIP, this Agreement shall become
effective upon the date the fully executed Agreement and deposit
specified in Section 6 of this Agreement are received by the Participating
TO. If the Participating TO does not receive the fully executed Agreement
and payment pursuant to Section 7.2 of the LGIP, then the
Interconnection Request will be deemed withdrawn upon the
Interconnection Customer's receipt of written notice by the ISO pursuant
to Section 3.8 of the LGIP.
13.0 Miscellaneous.
13.1 Dispute Resolution. Any dispute, or assertion of a claim, arising out of or
in connection with this Interconnection System Impact Study Agreement,
shall be resolved in accordance with Section 13.5 of the LGIP.
13.2 Confidentiality. Confidential Information shall be treated in accordance
with Section 13.1 of the LGIP.
13.3 Binding Effect. This Interconnection System Impact Study Agreement and
the rights and obligations hereof, shall be binding upon and shall inure to
the benefit of the successors and assigns of the Parties hereto.
13.4 Conflicts. In the event of a conflict between the body of this
Interconnection System Impact Study Agreement and any attachment,
appendices or exhibits hereto, the terms and provisions of the body of this
Interconnection System Impact Study Agreement shall prevail and be
deemed the final intent of the Parties.
13.5 Rules of Interpretation. This Interconnection System Impact Study
Agreement; unless a clear contrary intention appears, shall be construed
and interpreted as follows: (1) the singular number includes the plural
number and vice versa; (2) reference to any person includes such
4
person's successors and assigns but, in the case of a Parry, only if such
successors and assigns are permitted by this Interconnection System
Impact Study Agreement, and reference to a person in a particular
capacity excludes such person in any other capacity or individually; (3)
reference to any agreement (including this Interconnection System Impact
Study Agreement), document, instrument or tariff means such agreement,
document, instrument, or tariff as amended or modified and in effect from
time to time in accordance with the terms thereof and, if applicable, the
terms hereof; (4) reference to any applicable laws and regulations means
such applicable laws and regulations as amended, modified, codified, or
reenacted, in whole or in part, and in effect from time to time, including, if
applicable, rules and regulations promulgated thereunder; (5) unless
expressly stated otherwise, reference to any Article, Section or Appendix
means such Article or Section of this Interconnection System Impact
Study Agreement or such Appendix to this Interconnection System Impact
Study Agreement, or such Section to the LGIP or such Appendix to the
LGIP, as the case may be; (6) "hereunder", "hereof, "herein", "hereto" and
words of similar import shall be deemed references to this Interconnection
System Impact Study Agreement as a whole and not to any particular
Article, Section, or other provision hereof or thereof; (7) "including" (and
with correlative meaning "include") means including without limiting the
generality of any description preceding such term; and (8) relative to the
determination of any period of time, "from" means "from and including",
"to" means "to but excluding" and "through" means "through and
including".
13.6 Entire Agreement. This Interconnection System impact Study Agreement,
including all Appendices and Schedules attached .hereto, constitutes the
entire agreement between the Parties with reference to the subject matter
hereof, and supersedes all prior and contemporaneous understandings or
agreements, oral or written, between the Parties with respect to the
subject matter of this Interconnection System Impact Study Agreoment
There are no other agreements, representations, warranties, or covenants
which constitute any part of the consideration for, or any condition to, any
Party's compliance with its obligations under this Interconnection System
Impact Study Agreement.
13.7 No Third Party Beneficiaries. This Interconnection System Impact Study
Agreement is not intended to and does not create rights, remedies, or
benefits of any character whatsoever in favor of any persons,
corporations, associations, or entities other than the Parties, and the
obligations herein assumed are solely for the use and benefit of the
Parties, their successors in interest and, where permitted, their assigns.
13.8 Waiver. The failure of a Party to this Interconnection System Impact
Study Agreement to insist, on any occasion, upon strict performance of
any provision of this Interconnection System Impact Study Agreement will
not be considered a waiver of any obligation, right, or duty of, or imposed
upon, such Party.
Any waiver at any time by either Party of its rights with respect to this
Interconnection System Impact Study Agreement shall not be deemed a
continuing waiver or a waiver with respect to any other failure to comply
with any other obligation, right, duty of this Interconnection System Impact
Study Agreement. Termination or default of this Interconnection System
Impact Study Agreement for any reason by the Interconnection Customer
shall not constitute a waiver of the Interconnection Customer's legal rights
to obtain an interconnection from the Participating TO. Any waiver of this
Interconnection System Impact Study Agreement shall, if requested, be
provided in writing.
Any waivers at any time by any Party of its rights with respect to any
default under this Interconnection System Impact Study Agreement, or
with respect to any other matter arising in connection with this
Interconnection System Impact Study Agreement, shall not constitute or
be deemed a waiver with respect to any subsequent default or other
matter arising in connection with this Interconnection System Impact
Study Agreement. Any delay, short of the statutory period of limitations, in
asserting or enforcing any right under this Interconnection System Impact
Study Agreement shall not constitute or be deemed a waiver of such right.
13.9 Headings. The descriptive headings of the various Articles and Sections
of this Interconnection System Impact Study Agreement have been
inserted for convenience of reference only and are of no significance in
the interpretation or construction of this Interconnection System Impact
Study Agreement.
13.10 Multiple Counterparts. This Interconnection System Impact Study
Agreement may be executed in two or more counterparts, each of which
is deemed an original but all constitute one and the same instrument.
13.11 Amendment. The Parties may by mutual agreement amend this
Interconnection System Impact Study Agreement by a written instrument
duly executed by both of the Parties.
13.12 Modification by the Parties. The Parties may by mutual agreement amend
the Appendices to this Interconnection System Impact Study Agreement
by a written instrument duly executed by both of the Parties. Such
amendment shall become effective and a part of this Interconnection
System Impact Study Agreement upon satisfaction of all applicable laws
and regulations.
13.13 Reservation of Rights. The Participating TO shall have the right to make
a unilateral filing with FERC to modify this Interconnection System Impact
Study Agreement with respect to any rates, terms and conditions,
charges, classifications of service, rule or regulation under section 205 or
any other applicable provision of the Federal Power Act and FERC's rules
and regulations thereunder, and Interconnection Customer shall have the
right to make a unilateral filing with FERC to modify this Interconnection
System Impact Study Agreement pursuant to section 206 or any other
applicable provision of the Federal Power Act and FERC's rules and
regulations thereunder; provided that each Party shall have the right to
protest any such filing by another Party and to participate fully in any
proceeding before FERC in which such modifications may be considered.
Nothing in this Interconnection System Impact Study Agreement shall
limit the rights of the Parties or of FERC under sections 205 or 206 of the
Federal Power Act and FERC's rules and regulations thereunder, except
to the extent that the Parties otherwise_ mutually agree as provided herein.
13.14 No Partnership. This Interconnection System Impact Study Agreement
shall not be interpreted or construed to create an association, joint
venture, agency relationship, or partnership between the Parties or to
impose any partnership obligation or partnership liability upon any Party.
No Party shall have any right, power or authority to enter into any
agreement or undertaking for, or act on behalf of, or to act as or be an
agent or representative of, or to otherwise bind, another Party.
13.15 Assignment. This Interconnection System Impact Study Agreement may
be assigned by a Party only with the written consent of the other Party;
provided that a Party may assign this Interconnection System Impact
Study Agreement without the consent of the other Party to any Affiliate of
the assigning Party with an equal or greater credit rating and with the legal
authority and operational ability to satisfy the obligations of the assigning
Party under this Interconnection System Impact Study Agreement; and
provided further that the Interconnection Customer shall have the right to
assign this Interconnection System Impact Study Agreement, without the
consent of the other Party, for collateral security purposes to aid in
providing financing for the Large Generating Unit,. provided that the
Interconnection Customer will require any secured party, trustee or
mortgagee to notify the other Party of any such assignment. Any
financing arrangement entered into by the Interconnection Customer
pursuant to this Article will provide that prior to or upon the exercise of the
secured party's, trustee's or mortgagee's assignment rights pursuant to
said arrangement, the secured creditor, the trustee or mortgagee will
notify the other Party of the date and particulars of any such exercise of
assignment right(s). Any attempted assignment that violates this Article is
void and ineffective. Any assignment under this Interconnection System
Impact Study Agreement shall not relieve a Parry of its obligations, nor
shall a Party's obligations be enlarged, in whole or in part, by reason
thereof. Where required, consent to assignment will not be unreasonably
withheld, conditioned or delayed.
IN WITNESS THEREOF, the Parties have caused this Agreement to be duly
executed by their duly authorized officers or agents on the day and year first above
written.
SOUTHERN CALIFO NIA EDISON COMPANY
By: `
1;AerVH1E. Tam
Title: Director of Grid Contracts
Date:
CITY OF VERNON
By:
Title: W4*
Date: June 15, 2006
XATEsTY
By. I_ M
B ce Y Malkenhorst, Jr., Acting
Ci lerk
APPROVED AS —TO FORM:
Willard C(- lY,dmagucftl, Chief Deputy City8 Attorney
APPROVED
STEPHEN E. PICKETT
Sr. Vice President and
neral unsel
Attachment A
Interconnection System Impact
Study Agreement
ASSUMPTIONS USED IN CONDUCTING THE
INTERCONNECTION SYSTEM IMPACT STUDY
The Interconnection Customer, Participating TO and ISO have agreed to forego
the Interconnection Feasibility Study. The Interconnection System Impact Study will be
based upon the information set forth in the Interconnection Request and agreed upon in
the Scoping Meeting held on May 24, 2006, and will include the following assumptions:
1. Designation of Point of Interconnection and configuration to be studied.
a. Point of Interconnection: The Participating TO's Laguna Bell Substation
230 kV bus via a double circuit 230 kV transmission line.
b. Configuration: The proposed project is a 304 MW incremental increase to the
proposed 610 MW Vernon Power Plant (the "Vernon Power Plant
Expansion"). The full configuration of the natural gas fired combined cycle
plant will consist of three gas turbines and one steam turbine with a total net
output of 914 MW; transformation equipment; meters and metering
equipment; and appurtenant equipment at the Large Generating Facility site
to be located at 3200 Fruitland Avenue, in Vernon, California as specified in
the Interconnection Customer's Interconnection Request.
2. Designation of alternative Point(s) of Interconnection and configuration.
a. Point of Interconnection: The Mesa-Lighthipe and Mesa -Redondo 230 kV
transmission lines via a new switchyard near Laguna Bell Substation.
b. Configuration: Same as above.
3. An Interconnection Customer requested in-service date of March 31, 2009, Trial
Operation date of May 31, 2009, and Commercial Operation date of July 31,
2009; however, such assumptions shall be subject to change after study results,
permitting requirements, design, land issues and material lead times are known,
so that a more accurate determination can be made.
4. The technical data supplied by Interconnection Customer are accurate and
complete.
5. Interconnection Customer will install and maintain necessary equipment to meet
Participating TO's criteria for power factor correction at the Point of
Interconnection.
6. The maximum interconnection capacity requested by Interconnection Customer
is 304 MW at 230 kV for the Vernon Power Plant Expansion.
7. Interconnection System Impact Study results will reflect the ISO Tariff, rules and
protocols, and the Participating TO's Interconnection Handbook in effect at the
time the Participating TO provides the Interconnection System Impact Study to
Interconnection Customer.
8. The Interconnection System Impact Study will be performed in accordance with
the study plan agreed to by the Participating TO, the Interconnection Customer
and the ISO.
Pursuant to Section 7.1 of the LGIP, the estimated cost to complete the
Interconnection System Impact Study is $60,000.
The Deliverability Assessment mentioned in Section 5 of the Interconnection
System Impact Study Agreement is not yet being performed by the ISO and will not be
included in the scope of work.
SUPPORTING
Do.CUMENTS
CITY OF VERNON —
SOUTHERN CALIFORNIA EDISON COMPANY
INTERCONNECTION SYSTEM IMPACT STUDY AGREEMENT
(Vernon Power Plant Expansion)
THIS AGREEMENT is made and entered into thi&day of , 2006
by and between the City of Vernon, a municipal corporation organized nd existing
under the laws of the State of California, ("Interconnection Customer") and Southern
California Edison Company, a corporation existing under the laws of the State of
California, ("Participating TO"). The Interconnection Customer and the Participating TO
each may be referred to as a "Party," or collectively as the "Parties."
RECITALS
WHEREAS, the Interconnection Customer is proposing to develop a Large
Generating Facility or generating capacity addition to an existing Generating Facility
consistent with the Interconnection Request submitted by the Interconnection Customer
dated April 12, 2006; and
WHEREAS, the Interconnection Customer desires to interconnect the Large
Generating Facility with the ISO Controlled Grid; and
WHEREAS, the Interconnection Customer has requested the Participating TO to
perform an interconnection System Impact Study to assess the impact of
interconnecting the Large Generating, Facility;
NOW, THEREFORE, in consideration of and subject to the mutual covenants
contained herein the Parties agree as follows:
1.0 When used in this Agreement, with initial capitalization, the terms
specified shall have'the meanings indicated in the ISO's FERC-approved
Standard .Large Generation Interconnection 'Procedures ("LGIP") or the
Master Definitions Supplement, Appendix Ato the ISO Tariff, as
applicable.
2.0 The Interconnection Customer elects and the 'Participating TO shall cause
to be performed an Interconnection System Impact Study consistent with
Section 7 of the LGIP in accordance with the ISO Tariff.
3.0 The scope of the Interconnection System Impact Study shall be subject to
the assumptions set forth in Attachment .A to this Agreement.
4.0 The Interconnection System Impact Study will be based upon the
technical information provided by the Interconnection Customer in the
Interconnection Request, subject to any modifications in accordance with
Section 4.4 of the LGIP. The Participating TO reserves the right to
request additional technical information from the Interconnection
Customer as may reasonably become necessary consistent with Good
Utility Practice during the course of the Interconnection System Impact
Study. if the Interconnection Customer modifies its designated Point of
Interconnection, Interconnection Request, or the technical information
provided therein is modified, the time to complete the Interconnection
System Impact Study may be extended.
5.0 The Interconnection System Impact Study report shall provide the
following information:
identification of any circuit breaker short circuit capability limits
exceeded on the Participating TO's electric system as a result of
the interconnection;
identification of any thermal. overload or voltage limit violations on
the Participating TO's electric system resulting from the
interconnection;
identification of any instability or inadequately damped response to
system disturbances on the Participating TO's electric system
resulting from the interconnection;
a description and non -binding, good faith estimated cost of facilities
on the Participating TO's electric system required to interconnect
the .Large Generating Facility to the Participating TO's portion of
the ISO Controlled Grid and to address the identified short circuit,
instability, and powerflow issues on the Participating TO's portion
of the ISO Controlled Grid; and
if the :Participating TO is an interconnecting Participating TO for the
Large Generating Facility, a Deliverability Assessment on the ISO
Controlled Grid pursuant -to Section 3.3 of the LGIP.
6.0 The Interconnection Customer shall provide a deposit of $50,000 for the
performance of the Interconnection System Impact Study. The
Participating TO's good faith estimate for the time of completion of the
Interconnection System Impact Study is one hundred twenty (120)
Calendar Days after the receipt of the executed Agreement, $50,000
study payment and technical data in accordance with Attachment A to
:Appendix 1 of the LGIP.
Following the issuance of the Interconnection System Impact Study, the
'Participating TO shall charge and the Interconnection Customer shall pay
the actual costs of the Interconnection System Impact Study, inclusive of
2
any re -studies and amendments to the Interconnection System Impact
Study, pursuant to Section 9 of this Agreement.
Any difference between the deposit made toward the Interconnection
System Impact Study, amendments and re -studies to the Interconnection
System Impact Study, and the actual cost of the study shall be paid by or
refunded to the Interconnection Customer, as appropriate in accordance
with Section 13.3 of the LGIP.
7.0 Pursuant to Section 3.7 of the LGIP, the ISO will coordinate the conduct
of any studies required to determine the impact of the Interconnection
Request on Affected Systems. The Participating TO may provide a copy
of the Interconnection System Impact Study results to an Affected System
Operator and the Western Electricity Coordinating Council. Requests for
review and input from Affected System Operators or the Western
Electricity Coordinating Council may arrive at any time prior to
interconnection, and a revision of the Interconnection System Impact
Study or re -study may be required in such event.
8.0 Substantial portions of technical data and assumptions used to perform
the Interconnection System Impact Study, such as system conditions,
existing and planned generation, and unit modeling, may change after the
Participating TO provides the Interconnection System Impact Study
results to the Interconnection Customer. Study results will reflect
available data at the time the Participating TO provides the
Interconnection System Impact Study to the Interconnection Customer.
The Participating TO .shall not be responsible for any additional costs,
including, without limitation, costs of new or additional facilities, system
.upgrades, orzchedule changes, that may be incurred .by -the
Interconnection Customer.as a result of changes in such data and
assumptions.
9.0 In the event that a re -study or amendment ofthe Interconnection System
Impact Study is required, the Participating TO shall provide notification of
the need for such re -study or amendment, and the Interconnection
Customer shall provide, direction as to whether to proceed with the re-
study or amendment and any associated deposit payment pursuant to
Section '7.6 or, Section 12.2.4 of the LGIP, as applicable.
10.0 The Participating TO shall maintain records and accounts of all costs
incurred in :performing the Interconnection System Impact Study, inclusive
of any re-studles or amendments thereto, in sufficient detail to allow
verification of all costs incurred, including associated overheads. The
Interconnection Customer shall have the right, upon reasonable notice,
Within a reasonable time at the Participating TO's offices and at its own
3
expense, to audit the Participating TO's records as necessary and as
appropriate in order to verify costs incurred by the Participating TO. Any
audit requested by the Interconnection Customer shall be completed, and
written notice of any audit dispute provided to the Participating TO
representative, within one hundred eighty (180) Calendar Days following
receipt by the Interconnection Customer of the Participating TO's
notification of the final costs of the Interconnection System Impact Study,
inclusive of any re -study or amendment thereto.
11.0 In accordance with Section 3.8 of the LGIP, the Interconnection Customer
may withdraw its Interconnection Request at any time by written notice to
the ISO. Upon receipt of such notice, this Agreement shall terminate.
12.0 Pursuant to Section 7.2 of the LGIP, this Agreement shall become
effective upon the date the fully executed Agreement and deposit
specified in Section 6 of this Agreement are received by the Participating
TO. If the Participating TO does not receive the fully executed Agreement
and payment pursuant to Section 7.2 of the LGIP, then the
Interconnection Request will be deemed withdrawn upon the
Interconnection Customer's receipt of written notice by the ISO pursuant
to Section 3.8 of the LGIP.
13.0 Miscellaneous.
13.1 Dispute Resolution. Any dispute, or assertion of a claim, arising out of or
in connection with this Interconnection System Impact Study Agreement,
shall be resolved in. accordance with Section 13.5 of the LGIP.
13.2 Confidentiality. Confidential Information shall be treated in accordance
with Section 13.1 of the LGIP.
13.3 Binding Effect. This Interconnection System Impact Study Agreement and
the rights and obligations hereof, shall be binding upon and shall inure to
the benefit of the successors and assigns of the Parties hereto.
13.4 Conflicts. in the event of a conflict between the body of this
Interconnection System Impact Study Agreement and any attachment,
appendices or exhibits hereto, the terms and provisions of the body of this
Interconnection System Impact Study Agreement shall prevail and be
deemed the final intent of the Parties.
13.5 "Rules of interpretation. This interconnection System Impact Study
Agreement, unless a clear contrary intention appears, shall be construed
and interpreted as follows: (1) the singular number includes the plural
number and vice versa; (2) reference to any person includes such
person's successors and assigns but, in the case of a Party, only if such
successors and assigns are permitted by this Interconnection System
Impact Study Agreement, and reference to a person in a particular
capacity excludes such person in any other capacity or individually; (3)
reference to any agreement (including this Interconnection System Impact
Study Agreement), document, instrument or tariff means such agreement,
document, instrument, or tariff as amended or modified and in effect from
time to time in accordance with the terms thereof and, if applicable, the
terms hereof; (4) reference to any applicable laws and regulations means
such applicable laws and regulations as amended, modified, codified, or
reenacted, in whole or in part, and in effect from time to time, including, if
applicable, rules and regulations promulgated thereunder; (5) unless
expressly stated otherwise, reference to any Article, Section or Appendix
means such Article or Section of this Interconnection System Impact
Study Agreement or such Appendix to this. Interconnection System Impact
Study Agreement, or such Section to the LGIP or such Appendix to the
LGIP, as the case may be; (6) "hereunder", "hereof", "herein", "hereto" and
words of similar import shall be deemed references to this Interconnection
System Impact Study Agreement as a whole and not to any particular
Article, Section, or other provision hereof or thereof; (7) "including" (and
with correlative meaning "include") means including without limiting the
generality of any description preceding such term; and (8) relative to the
determination of any period of time, "from" means "from and including",
"to" means "to but excluding" and "through" means "through and
including".
13.6 Entire Agreement. 'This Interconnection System Impact Study Agreement,
including all Appendices and Schedules attached hereto, constitutes the
entire agreement between the Parties with reference to the subject matter
hereof, and :supersedes all prior and contemporaneous understandings or
agreements, oral or written, between the "Parties with respect to the
subject matter of this Interconnection System Impact Study Agreement.
There are no other agreements, representations, warranties, or covenants
which constitute any part of the consideration for, or any condition to, any
Party's compliance with its obligations under this Interconnection System
Impact Study Agreement.
13.7 No Third Party Beneficiaries. This Interconnection System Impact Study
Agreement is not intended to and does not create rights, remedies, or
benefits of any character whatsoever in favor of any persons,
corporations, associations, or entities otherrthan the Parties, and the
obligations herein assumed are solely for the use and benefit of the
Parties, their successors in interest and, where permitted, their assigns.
13.8 Waiver. The failure of a Party to this Interconnection System Impact
Study Agreement to insist, on any occasion, upon strict performance of
any provision of this Interconnection System Impact Study Agreement will
not be considered a waiver of any obligation, right, or duty of, or imposed
upon, such Parry.
Any waiver at any time by either Party of its rights with respect to this
Interconnection System Impact Study Agreement shall not be deemed a
continuing waiver or a waiver with respect to any other failure to comply
with any other obligation, right, duty of this Interconnection System Impact
Study Agreement. Termination or default of this Interconnection System
Impact Study Agreement for any reason by the Interconnection Customer
shall not constitute a waiver of the Interconnection Customer's legal rights
to obtain an interconnection from the Participating TO. Any waiver of this
Interconnection System Impact Study Agreement shall, if requested, be
provided In writing.
Any waivers at any time by any Party of its rights with respect to any
default under this Interconnection System Impact Study Agreement, or
with respect to any other matter arising in connection with this
Interconnection System Impact Study Agreement, shall not constitute or
be deemed a waiver with respect to any subsequent default or other
matter arising in connection with this Interconnection System Impact
Study Agreement. Any delay, short of the statutory period of limitations, in
asserting or enforcing any right under this Interconnection System Impact
Study Agreement shall not constitute or be deemed a waiver of such right.
'13.9 Headings. The'descriptive headings of the various Articles and Sections
of this Interconnection System impact Study Agreement have been
inserted for convenience of reference only and are of no significance in
the interpretation or construction of this Interconnection System Impact
Study Agreement.
13.10 Multiple Counterparts. 'This Interconnection System Impact Study
Agreement may be executed in two or more counterparts, each of which
is deemed an original but all constitute one and the same instrument.
13.11 Amendment. The Parties may by mutual agreement amend this
Interconnection. System Impact Study Agreement by a written instrument
duly executed by both of the Parties.
13.12 Modification by the Parties. The Parties may by mutual agreement amend
the Appendices to this Interconnection System Impact Study Agreement
by a written instrument duly executed by both of the Parties. Such
amendment shall become effective and a part of this Interconnection
System impact Study Agreement upon satisfaction of all applicable laws
and regulations.
13.13 Reservation of Rights. The Participating TO shall have the right to make
a unilateral filing with FERC to modify this Interconnection System Impact
Study Agreement with respect to any rates, terms and conditions,
charges, classifications of service, rule or regulation under section 205 or
any other applicable provision of the Federal Power Act and FERC's rules
and regulations thereunder, and Interconnection Customer shall have the
right to make a unilateral filing with FERC to modify this Interconnection
System Impact Study Agreement pursuant to section 206 or any other
applicable provision of the Federal Power Act and FERC's rules and
regulations thereunder; provided that each Party shall have the right to
protest any such filing by another Party and to participate fully in any
proceeding before FERC in which such modifications may be considered.
Nothing in this Interconnection System Impact Study Agreement shall
limit the rights of the Parties or of FERC under sections 205 or 206 of the
Federal Power Act and FERC's rules and regulations thereunder, except
to the extent that the Parties otherwise mutually agree as provided herein.
13.14 No Partnership. This Interconnection System Impact Study Agreement
shall not be Interpreted or construed to create an association, joint
venture, agency relationship, or partnership between the Parties or to
impose any partnership obligation or partnership liability upon any Party.
No Party shall have any right, power or authority to enter into any
agreement or undertaking for, or act on behalf of, or to act as or be an
agent or representative of, or to otherwise bind, another Party. ,
13.15 Assignment. This Interconnection System Impact Study Agreement may
be assigned .by a Party only with the written consent of the other Party;
provided that a Party may assign this Interconnection System Impact
Study Agreement without the consent of the other Party to any Affiliate of
the assigning Party with an equal or greater credit rating and with the legal
authority and operational ability to satisfy the obligations of the assigning
Party under this Interconnection System Impact Study Agreement; and
provided further that the Interconnection Customer shall have the right to
assign this interconnection System Impact Study Agreement, without the
consent of the other Party, for collateral security purposes to aid in
providing financing for the Large Generating Unit, provided that the
Interconnection Customer will require any secured party; trustee or
mortgagee to notify the other Party of any such assignment. Any
financing arrangement entered into by the Interconnection Customer
pursuant to this Article will provide that prior to or upon the exercise of the
secured party's, trustee's or mortgagee's assignment rights pursuant to
said arrangement, the secured creditor, the trustee or mortgagee will
notify the other Party of the date and particulars of any such exercise of
assignment right(s). Any attempted assignment that violates this Article is
void and ineffective. Any assignment under this Interconnection System
Impact Study Agreement shall not relieve a Party of its obligations, nor
shall a Party's obligations be enlarged, in whole or in part, by reason
thereof. Where required, consent to assignment will not be unreasonably
withheld, conditioned or delayed.
IN WITNESS THEREOF, the Parties have caused this Agreement to be duly
executed by their duly authorized officers or agents on the day and year first above
written.
SOUTHERN 4La
NIA EDISON COMPANY
By:
ilb
Title: Director of Grid Contracts
Date:
CITY OF VERNON
By:
7tx
Title:
Date: June 15, 2006
x
By:
u �Valkenhorst�, Jr., Acting City Clerk
APPR ED AS TO FO .
X �
Willard G. Yamaifucift, C of Deputy City Attorney,
8
STEPHEN E. PICKETT
Sr. Vice President and
Attachment A
Interconnection System Impact
Study Agreement
ASSUMPTIONS USED IN CONDUCTING THE
INTERCONNECTION SYSTEM IMPACT STUDY
The Interconnection Customer, Participating TO and ISO have agreed to forego
the Interconnection Feasibility Study. The Interconnection System Impact Study will be
based upon the information set forth in the Interconnection Request and agreed upon in
the Scoping Meeting held on May 24, 2006, and will include the following assumptions:
1. Designation of Point of Interconnection and configuration to be studied.
a. Point of Interconnection: The Participating TO's Laguna Bell Substation
230 kV bus via a double circuit 230 kV transmission line.
b. Configuration: The proposed project is a 304 MW incremental increase to the
proposed 610 MW Vernon Power Plant (the "Vernon Power Plant
Expansion"). The full configuration of the natural gas fired combined cycle
plant will consist of three gas turbines and one steam turbine with a total net
output of 914 MW; transformation equipment; meters and metering
equipment; and appurtenant equipment at the Large Generating Facility site
to be located at 3200 Fruitland Avenue, in Vernon, California as specified in
the Interconnection Customer's Interconnection Request.
2. Designation of alternative Point(s) of Interconnection and configuration.
a. Point of Interconnection: The Mesa-Lighthipe and Mesa -Redondo 230 kV
'transmission lines via a new switchyard near Laguna Bell Substation.
b. Configuration: Same as above.
3. An Interconnection Customer requested in-service date of March 31, 2009, Trial
Operation date of May 31, 2009, and Commercial Operation date of July 31,
2009; however, such assumptions shall be subject to change after study results,
permitting requirements, design, land issues and material lead times are known,
so that a more accurate determination can be made.
4. The technical data supplied by Interconnection Customer are accurate and
complete.
5. Interconnection Customer will install and maintain necessary equipment to meet
Participating TO's criteria for power factor correction at the Point of
Interconnection.
6. The maximum interconnection capacity requested by Interconnection Customer
is 304 MW at 230 kV for the Vernon Power Plant Expansion.
7. Interconnection System Impact Study results will reflect the ISO Tariff, rules and
protocols, and the Participating TO's Interconnection Handbook in effect at the
time the Participating TO provides the Interconnection System Impact Study to
Interconnection Customer.
8. The Interconnection System Impact Study will be performed in accordance with
the study plan agreed to by the Participating TO, the Interconnection Customer
and the ISO.
Pursuant to Section 7.1 of the LGIP, the estimated cost to complete the
Interconnection System Impact Study is $60,000:
The Deliverability Assessment mentioned in Section 5 of the Interconnection
System Impact Study Agreement is not yet being performed by the ISO and will not be
included in the scope of work.