Resolution No. 91140
1
2
3
4
5
M
7
8
$,I
10
11
12
13
14
15
16
17
18
19
20
21
22
23
PILI!
25
26
27
28
RESOLUTION NO. 9114
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
VERNON APPROVING AND AUTHORIZING THE EXECUTION OF
AN INTERCONNECTION FACILITIES STUDY AGREEMENT BY
AND BETWEEN THE CITY OF VERNON AND THE CALIFORNIA
INDEPENDENT SYSTEM OPERATOR CORPORATION REGARDING
THE VERNON POWER PLANT
WHEREAS, the City of Vernon (the "City") owns and operates
its own electric system which services the City's constituents; and
WHEREAS, the City is a Participating Transmission Owner with
the California Independent System Operator Corporation ("ISO"); and
WHEREAS, the City is in the process of developing a natural
gas -fired combined cycle power plant located within City limits
officially named the Vernon Power Plant (the "VPP Project") for the
purpose of installing additional generating capacity that will yield an
efficient, cost-effective, and reliable source of electric generation
to the City; and
WHEREAS, the Vernon Power Plant will be interconnected to
Southern California Edison Company's ("SCE") Laguna Bell Substation 230,
kV bus via a double circuit 230 kV transmission line; and
WHEREAS, on October 12, 2005, the City Council of the City of
Vernon adopted Resolution No. 8873 approving an Interconnection System
Impact Study with SCE to assess the impact of interconnecting the VPP
Project to the ISO Controlled Grid at an output of 610 mW (net); and
WHEREAS, the City desires to interconnect an additional 304
mW to the proposed 610 mW Vernon Power Plant, resulting in a total
maximum net output of 914 mW; and
WHEREAS, the VPP Project is considered a Large Generating
Facility and in accordance with the Cal -ISO Large Generator
1 a
r
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Interconnection Procedure, the ISO has completed an Interconnection
System Impact Study to assess the impact of the VPP Project; and
WHEREAS, the City's Light & Power Department has determined
I1that an Interconnection Facilities Study needs to be performed to
specify and estimate the cost of the equipment, engineering,
procurement and construction work needed on the City's electric system
to implement the conclusions of the Interconnection System Impact Study
to physically and electrically connect the Large Generating Facility to
the ISO Controlled Grid; and
WHEREAS, the City desires to engage the services of the ISO
to perform the necessary study (i) to identify the City's
interconnection facilities, distribution upgrades and network upgrades
necessary to interconnect the Vernon Power Plant; (ii) to estimate the
cost of such required facilities and upgrades; (iii) to estimate the
time to complete the required facilities and upgrades; (iv) to evaluate
the impacts to the SCE Distribution System; (v) to evaluate the
feasibility and associated cost with interconnecting the 230 kV double
circuit gen-tie line at the northwest side of Laguna Bell Substation,
in accordance with the terms and conditions of an Interconnection
Facilities Study (the "Agreement"); and
WHEREAS, in order to perform the study, the ISO is requiring
the City to pay a deposit for costs in an estimated amount of
$100,000.00; and
WHEREAS, the Director of Light & Power has recommended that
the Agreement with the ISO be approved and a check issued for the
estimated study costs; and
WHEREAS, the City Council of the City of Vernon has
determined that, pursuant to the provisions of subsection (a) of
- 2 -
0
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Section 2.27 of the Vernon City Code, it is in the public interest and
necessity to enter into an agreement with the ISO.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF VERNON AS FOLLOWS:
SECTION 1: The City Council of the City of Vernon hereby
finds and determines that the recitals contained hereinabove are true
and correct.
SECTION 2: The City Council of the City of Vernon hereby
approves the Interconnection Facilities Study Agreement with the ISO,
a copy of which is attached hereto as Exhibit A and incorporated by
reference, and approves the payment of a deposit for costs in the sum
of $100,000.00.
SECTION 3: The City Council of the City of Vernon hereby
authorizes the Mayor to execute said Agreement for, and on behalf of,
the City of Vernon and the Acting City Clerk is hereby authorized to
attest thereto.
SECTION 4: The City Council of the City of Vernon hereby
authorizes and empowers the Acting City Clerk to execute such other
agreements and documents and to take such actions as may be necessary
or convenient to carry out the City's obligations hereunder and to
effect the purposes of the Agreement and the transactions therein
authorized.
SECTION 5: The City Council of the City of Vernon hereby
directs the Acting City Clerk, or his designee, to send one fully
executed Agreement, together with the deposit of $100,000.00, to the
ISO.
- 3 -
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
SECTION 6: The Acting City Clerk of the City of Vernon
shall certify to the passage of this resolution, and thereupon and
thereafter the same shall be in full force and effect.
APPROVED AND ADOPTED this 16th day of August, 2006.
ATTEST:
BRUCE VMMALKENHORST, JR.
Acting City Clerk
�LEqONIES C. M LBURG, Mayor
- 4 -
E
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
STATE OF CALIFORNIA )
) ss
COUNTY OF LOS ANGELES )
I, BRUCE V. MALKENHORST, JR., Acting City Clerk of the City of
Vernon, do hereby certify that the foregoing Resolution, being
Resolution No. 9114, was duly adopted by the City Council of the City
of Vernon at a regular meeting of the City Council duly held on
Wednesday, August 16, 2006, and thereafter was duly signed by the Mayor
of the City of Vernon.
BRUCE MALKENHORST, JR.
Acting City Clerk
(SEAL)
- 5 -
s
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
INTERCONNECTION FACILITIES STUDY AGREEMENT
THIS AGREEMENT is made and entered into this day of , 20 by
and between City of Vernon, a municipal corporation organized and existing under the
laws of the State of California, ("Interconnection Customer,") and the California
Independent System Operator Corporation, a California nonprofit public benefit
corporation. existing under the laws of the State of California, ("ISO"). The
Interconnection Customer and the ISO each may be referred to as a "Party," or
collectively as the "Parties."
RECITALS
WHEREAS, the Interconnection Customer is proposing to develop a Large
Generating Facility or generating capacity addition to an existing Generating Facility
consistent with the Interconnection Request submitted by the Interconnection Customer
dated September 9, '2005; and
WHEREAS, the Interconnection Customer desires to interconnect the Large
Generating Facility with the ISO Controlled Grid;
WHEREAS, the ISO has completed an Interconnection System Impact Study
(the "System Impact Study") and provided the results of. said study to the
Interconnection Customer; and
WHEREAS, the Interconnection Customer has requested the ISO to conduct or
cause to be performed an Interconnection Facilities Study to specify and estimate the
cost of the equipment, engineering, procurement and construction work needed on the
Participating TO's electric system to implement the conclusions of the Interconnection
System Impact Study in accordance with Good Utility Practice to physically and
electrically connect the Large Generating Facility to the ISO Controlled Grid.
NOW, THEREFORE, in consideration of and subject to the mutual covenants
contained herein the Parties agreed as follows:
1.0 When used in this Agreement, with initial capitalization, the terms
specified shall have the meanings indicated in the ISO's FERC-approved
Standard Large Generation Interconnection Procedures ("LGIP") or the
Master Definitions Supplement, Appendix A to the ISO Tariff, as
applicable.
2.0 The Interconnection Customer elects and the ISO shall conduct or cause
to be performed an Interconnection Facilities Study consistent with the
LGIP in accordance with the ISO Tariff.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
3.0 The scope of the Interconnection Facilities Study shall be subject to the
assumptions set forth in Attachment A and the data provided in
Attachment B to this Agreement.
4.0 The Interconnection Facilities Study report (i) shall provide a description,
estimated cost, including, if applicable, the cost of remedial measures that
address the financial impacts, if any, on Local Furnishing Bonds, of
(consistent with Attachment A), and schedule for required facilities or for
effecting remedial measures that address the financial impacts, if any, on
Local Furnishing Bonds within each Participating TO's electric system to
interconnect the Large Generating Facility to the ISO Controlled Grid and
(ii) shall address the short circuit, instability, and power flow issues
identified in the Interconnection System Impact Study.
5.0 The Interconnection Customer shall provide a deposit of the greater of
$100,000 or the Interconnection Customer's portion of the estimated
monthly cost for the performance of the Interconnection Facilities Study.
The time for completion of the Interconnection Facilities Study is specified
in Attachment A. For studies where the estimated cost exceed $100,000,
the ISO may invoice Interconnection Customer on a monthly basis for the
work to be conducted on the Interconnection Facilities Study for the
remaining balance of the estimated Interconnection Facilities Study cost.
The Interconnection Customer shall pay invoiced amounts within thirty
(30) Calendar Days of receipt of invoice. The ISO shall continue to hold
the amounts on deposit until settlement of the final in
Following the issuance of the Interconnection Facilities Study, the ISO
shall charge and the Interconnection Customer shall pay the actual costs
of the Interconnection Facilities Study, inclusive of any re -studies and
amendments to the Interconnection Facilities Study, pursuant to Section 9
of this Agreement.
Any difference between the deposit made toward the Interconnection
Facilities Study and the actual cost of the study, inclusive of any re -studies
and amendments thereto, shall be paid by or refunded to the
Interconnection Customer, as appropriate in accordance with Section 13.3
of the LGIP.
6.0 The Interconnection Facilities Study will be based upon the results of the
Interconnection System Impact Study and the technical information
provided by the Interconnection Customer in the Interconnection Request,
subject to any modifications in accordance with Section 4.4 of the LGIP.
The ISO reserves the right to request additional technical information from
the Interconnection Customer as may reasonably become necessary
consistent with Good Utility Practice during the course of the
Interconnection Facilities Study.
F
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
If the Interconnection Customer modifies its Interconnection Request or
the technical information provided therein is modified, the time to complete
the Interconnection Facilities Study may be extended.
7.0 Pursuant to Section 3.7 of the LGIP, the ISO will coordinate the conduct of
any studies required to determine the impact of the Interconnection
Request on Affected Systems. The ISO may provide a copy of the
Interconnection Facilities Study results to an Affected System Operator
and the Western Electricity Coordinating Council Requests for review
and input from Affected System Operators or the Western Electricity
Coordinating Council may arrive at any time prior to interconnection, and a
revision of the Interconnection Facilities Study or re -study may be required
in such event.
8.0 Substantial portions of technical data and assumptions used to perform
the Interconnection Facilities Study, such as system conditions, existing
and planned generation, and unit modeling, may change after the ISO
provides the Interconnection Facilities Study results to the Interconnection
Customer. Study results will reflect available data at the time the ISO
provides the Interconnection Facilities Study to the Interconnection
Customer. The ISO shall not be responsible for any additional costs,
including, without limitation, costs of new or additional facilities, system
upgrades, or schedule changes, that may be incurred by the
Interconnection Customer as a result of changes in such data and
assumptions.
9.0 In the event that a re -study or amendment of the Interconnection Facilities
Study is required, the ISO shall provide notification of the need for such
re -study or amendment, and the Interconnection Customer shall provide
direction as to whether to proceed with the re -study or amendment and
any associated deposit payment pursuant to Section 8.5 or Section 12.2.4
of the LGIP, as applicable.
10.0 The ISO shall maintain records and accounts of all costs incurred in
performing the Interconnection Facilities Study, inclusive of any re -studies
or amendments thereto, in sufficient detail to allow verification of all costs
incurred, including associated overhead. The Interconnection Customer
shall have the right, upon reasonable notice, within a reasonable time at
the ISO offices and at its own expense, to audit the ISO's records as
necessary and as appropriate in order to verify costs incurred by the ISO.
Any audit requested by the Interconnection Customer shall be completed,
and written notice of any audit dispute provided to the ISO within one
hundred eighty (180) Calendar Days following receipt by the
Interconnection Customer of the ISO's notification of the final costs of the
3
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Interconnection Facilities Study, inclusive of any re -study or amendment
thereto.
11.0 In accordance with Section 3.8 of the LGIP, the Interconnection Customer
may withdraw its Interconnection Request at any time by written notice to
the ISO. Upon receipt of such notice, this Agreement shall terminate.
12.0 Pursuant to Section 8.1 of the LGIP, this Agreement shall become
effective upon the date the fully executed Agreement and deposit
specified in Section 6 of this Agreement are received by the ISO. If the
ISO does not receive the fully executed Agreement and payment pursuant
to Section 8.1 of the LGIP, then the Interconnection Request will be
deemed withdrawn upon the Interconnection Customer's receipt of written
notice by the ISO pursuant to Section 3.8 of the LGIP.
13.0 Miscellaneous.
13.1 Dispute Resolution. Any dispute, or assertion of a claim, arising out of or
in connection with this Interconnection Facilities Study Agreement, shall
be resolved in accordance with Section 13.5 of the LGIP.
13.2 Confidentiality. Confidential Information shall be treated in accordance
with Section 13.1 of the LGIP.
13.3 Binding Effect. This Interconnection Facilities Study Agreement and the
rights and obligations hereof, shall be binding upon and shall inure to the
benefit of the successors and assigns of the Parties hereto.
13.4 Conflicts. In the event of a conflict between the body of this
Interconnection Facilities Study Agreement and any attachment,
appendices or exhibits hereto, the terms and provisions of the body of this
Interconnection Facilities Study Agreement shall prevail and be deemed
the final intent of the Parties.
13.5 Rules of Interpretation. This Interconnection Facilities Study Agreement,
unless a clear contrary intention appears, shall be construed and
interpreted as follows: (1) the singular number includes the plural number
and vice versa; (2) reference to any person includes such person's
successors and assigns but, in the case of a Party, only if such
successors and assigns are permitted by this Interconnection Facilities
Study Agreement, and reference to a person in a particular capacity
excludes such person in any other capacity or individually; (3) reference to
any agreement (including this Interconnection Facilities Study Agreement),
document, instrument or tariff means such agreement, document,
instrument, or tariff as amended or modified and in effect from time to time
in accordance with the terms thereof and, if applicable, the terms hereof;
CI
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
(4) reference to any applicable laws and regulations means such
applicable laws and regulations as amended, modified, codified, or
reenacted, in whole or in part, and in effect from time to time, including, if
applicable, rules and regulations promulgated thereunder; (5) unless
expressly stated otherwise, reference to any Article, Section or Appendix
means such Article or Section of this Interconnection Facilities Study
Agreement or such Appendix to this Interconnection Facilities Study
Agreement, or such Section to the LGIP or such Appendix to the LGIP, as
the case may be; (6) "hereunder", "hereof", "herein", "hereto" and words of
similar import shall be deemed references to this Interconnection Facilities
Study Agreement as a whole and not to any particular Article, Section, or
other provision hereof or thereof; (7) "including" (and with correlative
meaning "include") means including without limiting the generality of any
description preceding such term; and (8) relative to the determination of
any period of time, "from" means "from and including", "to" means "to but
excluding" and "through" means "through and including".
13.6 Entire Agreement. This Interconnection Facilities Study Agreement,
including all Appendices and Schedules attached hereto, constitutes the
entire agreement between the Parties with reference to the subject matter
hereof, and supersedes all prior and contemporaneous understandings or
agreements, oral or written, between the Parties with respect to the
subject matter of this Interconnection Facilities Study Agreement. There
are no other agreements, representations, warranties, or covenants which
constitute any part of the consideration for, or any condition to, any Party's
compliance with its obligations under this Interconnection Facilities Study
Agreement.
13.7 No Third Party Beneficiaries. This Interconnection Facilities Study
Agreement is not intended to and does not create rights, remedies, or
benefits of any character whatsoever in favor of any persons,
corporations, associations, or entities other than the Parties, and the
obligations herein assumed are solely for the use and benefit of the
Parties, their successors in interest and, where permitted, their assigns.
13.8 Waiver. The failure of a Party to this Interconnection Facilities Study
Agreement to insist, on any occasion, upon strict performance of any
provision of this Interconnection Facilities Study Agreement will not be
considered a waiver of any obligation, right, or duty of, or imposed upon,
such Party.
Any waiver at any time by either Party of its rights with respect to this
Interconnection Facilities Study Agreement shall not be deemed a
continuing waiver or a waiver with respect to any other failure to comply
with any other obligation, right, duty of this Interconnection Facilities Study
Agreement. Termination or default of this Interconnection Facilities Study
5
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Agreement for any reason by the Interconnection Customer shall not
constitute a waiver of the Interconnection Customer's legal rights to obtain
an interconnection from the Participating TO or ISO. Any waiver of this
Interconnection Facilities Study Agreement shall, if requested, be provided
in writing.
Any waivers at any time by any Party of its rights with respect to any
default under this Interconnection Facilities Study Agreement, or with
respect to any other matter arising in connection with this Interconnection
Facilities Study Agreement, shall not constitute or be deemed a waiver
with respect to any subsequent default or other matter arising in
connection with this Interconnection Facilities Study Agreement. Any
delay, short of the statutory period of limitations, in asserting or enforcing
any right under this Interconnection Facilities Study Agreement shall not.
constitute or be deemed a waiver of such right.
13.9 Headings. The descriptive headings of the various Articles and Sections
of this Interconnection Facilities Study Agreement have been inserted for
convenience of reference only and are of no significance in the
interpretation or construction of this Interconnection Facilities Study
Agreement.
13.10 Multiple Counterparts. This Interconnection Facilities Study Agreement
may be executed in two or more counterparts, each of which is deemed
an original but all constitute one and the same instrument.
13.11 Amendment. The Parties may by mutual agreement amend this
Interconnection Facilities Study Agreement by a written instrument duly
executed by both of the Parties.
13.12 Modification by the Parties. The Parties may by mutual agreement amend
the Appendices to this Interconnection Facilities Study Agreement by a
written instrument duly executed by both of the Parties. Such amendment
shall become effective and a part of this Interconnection Facilities Study
Agreement upon satisfaction of all applicable laws and regulations.
13.13 Reservation of Rights. The ISO shall have the right to make a unilateral
filing with FERC to modify this Interconnection Facilities Study Agreement
with respect to any rates, terms and conditions, charges, classifications of
service, rule or regulation under section 205 or any other applicable
provision of the Federal Power Act and FERC's rules and regulations
thereunder, and Interconnection Customer shall have the right to make a
unilateral filing with FERC to modify this Interconnection Facilities Study
Agreement pursuant to section 206 or any other applicable provision of
the Federal Power Act and FERC's rules and regulations thereunder;
provided that each Party shall have the right to protest any such filing by
0
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
another Party and to participate fully in any proceeding before FERC in
which such modifications may be considered. Nothing in this
Interconnection Facilities Study Agreement shall limit the rights of the
Parties or of FERC under sections 205 or 206 of the Federal Power Act
and FERC's rules and regulations thereunder, except to the extent that the
Parties otherwise mutually agree as provided herein.
13.14 No Partnership. This Interconnection Facilities Study Agreement shall not
be interpreted or construed to create an association, joint venture, agency
relationship, or partnership between the Parties or to impose any
partnership obligation or partnership liability upon any Party. No Party
shall have any right, power or authority to enter into any agreement or
undertaking for, or act on behalf of, or to act as or be an agent or
representative of, or to otherwise bind, another Party.
13.15 Assignment. This Interconnection Facilities Study Agreement may be
assigned by a Party only with the written consent of the other Party;
provided that a Party may assign this Interconnection Facilities Study
Agreement without the consent of the other Party to any Affiliate of the
assigning Party with an equal or greater credit rating and with the legal
authority and operational ability to satisfy the obligations of the assigning
Party under this Interconnection Facilities Study Agreement; and provided
further that the Interconnection Customer shall have the right to assign
this Interconnection Facilities Study Agreement, without the consent of the
other Party, for collateral security purposes to aid in providing financing for
the Large Generating Unit, provided that the Interconnection Customer will
require any secured party, trustee or mortgagee to notify the other Party of
any such assignment.. Any financing arrangement entered into by the
Interconnection Customer pursuant to this Article will provide that prior to
or upon the exercise of the secured party's, trustee's or mortgagee's
assignment rights pursuant to said arrangement, the secured creditor, the
trustee or mortgagee will notify the other Party of the date and particulars
of any such exercise of assignment right(s). Any attempted assignment
that violates this Article is void and ineffective. Any assignment under this
Interconnection Facilities Study Agreement shall not relieve a Party of its
obligations, nor shall a Party's obligations be enlarged, in whole or in part,
by reason thereof. Where required, consent to assignment will not be
unreasonably withheld, conditioned or delayed.
7
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
IN WITNESS WHEREOF, the Parties agenve caused ts on thethis day anreement to be d d year first above
executed by their duly authorized officers
written.
California Independent System Operator Corporation
By: ? y
Title: V'I « PreS d
Date: 7% l you b
City of Vernon
By:
Title:
Date:
INTERCONNECTION FACILITIES STUDY AGREEMENT
Attachment A
Interconnection Facilities
Study Agreement
INTERCONNECTION CUSTOMER SCHEDULE ELECTION FOR CONDUCTING THE
INTERCONNECTION FACILITIES STUDY
The ISO shall use Reasonable Efforts to complete the study and issue a draft
Interconnection Facilities Study report to the Interconnection Customer. Prior to issuing
draft study results to the Interconnection Customer, the Participating TO and ISO shall
share results for review and incorporate comments within the following number of days
after of receipt of an executed copy of this Interconnection Facilities Study Agreement:
one hundred twenty (120) Calendar Days with no more than a +/- 20
percent cost estimate contained in the report, or
two hundred ten (210) Calendar Days with no more than a +/- 10 percent
cost estimate contained in the report.
9
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Attachment B
Interconnection Facilities
Study Agreement
DATA FORM TO BE PROVIDED BY THE INTERCONNECTION CUSTOMER
WITH THE INTERCONNECTION FACILITIES STUDY AGREEMENT
Provide two copies of this completed form and other required plans and diagrams in
accordance with Section 8.1 of the LGIP.
Provide location plan and one -line diagram of the plant and station facilities. For staged
projects, please indicate future generation, transmission circuits, etc.
One set of metering is required for each generation connection to the new bus or
existing ISO Controlled Grid station. Number of generation connections:
On the one line indicate the generation capacity attached at each metering location.
(Maximum load on CT/PT)
On the one line indicate the location of auxiliary power. (Minimum load on CT/PT)
Will an alternate source of auxiliary power be available during CT/PT maintenance?
Yes No
Will a transfer bus on the generation side of the metering require that each meter set be
designed for the total plant generation? Yes No
(Please indicate on one line).
What type of control system or PLC will be located at the Interconnection Customer's
Large Generating Facility?
What protocol does the control system or PLC use?
Please provide a 7.5-minute quadrangle of the site. Sketch the plant, station,
transmission line, and property line.
10
r
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Physical dimensions of the proposed interconnection station:
Bus length from generation to interconnection station:
Line length from interconnection station to the Participating TO's transmission line.
Tower number observed in the field. (Painted on tower leg)*
Number of third party easements required for transmission lines*:
* To be completed in coordination with the Participating TO or ISO.
Is the Large Generating Facility in the Participating TO's service area?
Yes No
Local service provider for auziliary and other power:
Please provide proposed schedule dates:
Begin Construction Date:
Generator step-up transformer Date:
receives back feed power
Generation Testing
Commercial Operation
Level of Deliverability: Choose one of the following:
Deliverability with no Network Upgrades
100% Deliverability
Date:
Date:
11
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
ATTACHMENT C
Study Plan
12
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Facilities Study
Study Plan
City of Vemon
Vernon Power Plant (610 MV1)
July 27, 2006
California ISO
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Table of Contents
Project Summary ............................ :...............................................................................
..............................................1
Summary of Facilities Study Scope................................................................................................2
FacilitiesStudy Schedule..............................................................................................................................3
CostEstimates Summary .........................................................................................................................4
SiteVicinity Map...........................................................................................................................................................5
ConceptualOne -Line Diagram ................................ ....................................................:.........................6
Facilities Study Assumptions................................................................................7
Summary of the SIS Results & Mitigation Plan..........................................................................................................8
Summary of Deliverability Study Results ................. . .................................................................................................9
Detailed Facilities Study Work Scope & Cost Estimates..........................................................................................10
Estimated Time to Construct (Construction Schedule)...........................................................................................11
Reasonsa. Re -Study May Be Needed .............................. .......................................................................................12
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 1 PROJECT SUMMARY
The Vernon Power Plant to be studied is a 610 MW (net) plant. An incremental 304 MW
(net) increase to the Vernon Power Plant has been requested in a separate
Interconnection Request. The full configuration of the natural gas fired combined cycle
plant will consist of three gas turbines and one steam turbine with a total net output of 914
MW. The Vernon Power Plant will be located at 3200 Fruitland Avenue in Vernon,
California, and will be interconnected to Southern California Edison Company's ("SCE")
Laguna Bell Substation 230 kV bus via a double circuit 230 kV transmission line. The
City of Vernon (the "Interconnection Customer") has requested a March 31, 2009 in-
service date, a May 31, 2009 Trial Operation date, and a July 31, 2009 Commercial
Operation date.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 2 SUMMARY OF FACILITIES STUDY SCOPE
The Interconnection Facilities Study ("Facilities Study") shall include the following
scope of work: (i) the identification of the Participating TO'S Interconnection Facilities,
Distribution Upgrades and Network Upgrades necessary to interconnect the Vernon
Power Plant, (ii) the, estimated cost of such required facilities and upgrades, and (iii) the
estimated time to complete the required facilities and upgrades.
In addition, the Interconnection System Impact Study report dated June 23, 2006
did not include an evaluation of SCE's Distribution System. The impacts to the
Distribution System will be evaluated as part of the Facilities Study.
Vernon has also requested that the Facilities Study include an evaluation of the
feasibility and associated cost with interconnecting the gen-tie line at the northwest side
of Laguna Bell Substation. The estimated cost and time to perform such study will be
evaluated after Vernon provides the details of such request. As a result, the estimated
time to complete the study as specified below may need to be revised.
2
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 3 FACILITIES STUDY SCHEDULE
The study is scheduled to be completed as follows:
one hundred twenty (120) Calendar Days, with no more than a +/- 20
percent cost estimate
two hundred ten (210) Calendar Days, with no more than a +/- 10 percent
cost estimate
3
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 4 COST ESTIMATES SUMMARY
The estimated costs for the Participating TO's Interconnection Facilities will
include the costs associated with sole use facilities between the Vernon Power Plant
and the Point of Interconnection at Laguna Bell Substation, which do not include
Distribution Upgrades or Network Upgrades, to accommodate the Vernon Power
Project. Such facilities include those required to terminate the 230 kV double circuit
gen-tie line at Laguna Bell Substation and any protection equipment, communication
equipment, controls and other facilities associated with such termination.
The estimated costs for Network Upgrades will include the facilities and upgrades
required at or beyond the Point of Interconnection, including substation facilities at
Laguna Bell Substation; transmission facilities, protection equipment, communication
equipment, and controls at Laguna Bell Substation;- and facilities required beyond
Laguna Bell Substation, such as at other substations and on other transmission lines in
the ISO Controlled Grid to accommodate the interconnection of the Vernon Power
Plant.
The estimated costs for Distribution Upgrades will include the facilities and
upgrades, including substations and subtransmission and distribution lines, required on
SCE's Distribution System to accommodate the interconnection of the Vernon Power
Plant.
4
INTERCONNECTION FACILITIES STUDY AGREEMENT .
VERNON POWER PLANT
CHAPTER 5 SITE VICINITY MAP
The site vicinity map showing the project location and the proposed Point of
Interconnection will be provided in the Facilities Study.
5
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 6 CONCEPTUAL ONE -LINE DIAGRAM
The conceptual one -line diagram showing the proposed Point of Interconnection
will be provided in the Facilities Study.
1.1
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 7 FACILITIES STUDY ASSUMPTIONS
The Facilities Study will be based on the results of the Interconnection System
Impact Study ("SIS") and upon the following assumptions:
1) An Interconnection Customer requested in-service date of March 31, 2009, a Trial
Operation date of May 31, 2009, and a Commercial Operation date of July 31, 2009;
however, such assumptions shall be subject to change after study results, permitting
requirements, design, land issues and material lead times are known, so that a more
accurate determination can be made.
2) The technical data supplied by the Interconnection Customer for this Large
Generating Facilities are accurate and complete.
3) The maximum interconnection capacity requested by the Interconnection Customer is
610 MW.
4) The Interconnection Customer will install, own, operate and maintain all ISO metering
equipment. The ISO metering equipment will be located on the Interconnection
Customer's side of the Point of Interconnection.
5) The Interconnection Customer shall design the Large Generating Facility to maintain
a composite power delivery at continuous rated power output at the terminals of the
Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90
lagging, unless the ISO has established different requirements that apply to all
generators in the Control Area on a comparable basis.
6) The Facilities Study results will reflect the ISO Tariff, rules and protocols and SCE's
Interconnection Handbook in effect at the time SCE provides the Facilities Study
results to the Interconnection Customer.
7) Unless otherwise agreed to by SCE, it is assumed that Vernon will design, build, and
own the double circuit 230 kV generation tie line that will connect the plant switchyard
to the Laguna Bell 230kV Bus.
7
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 8 SUMMARY OF THE SIS RESULTS & MITIGATION PLAN
The results and mitigation plan identified in the SIS for the bulk power system are as follows:
1) Interconnection of Vernon Power Plant into Laauna Bell Substation:
The non -binding cost estimate to terminate the 230kV double circuit gen-tie line
into Laguna Bell Substation, including the work required to reconfigure the
substation in order to accommodate the line, is $30 million.
2) Power Flow Analysis:
Studies identified that with addition of the Vernon Power Plant, the Lighthipe-
Mesa 230 kV line was overloaded from 2424Amps/101 % to 2671 Amps/111 %
under the outages of Laguna Bell -Rio Hondo 230 kV No.1 line and Mesa -
Redondo 230 kV No.1 line. Such overload was triggered in the base case and
will be the responsibility of SCE to mitigate. Such mitigation will be performed by
removing or upgrading wave traps on the Lighthipe-Mesa No. 1 23Q kV line and
modifying the protection for such line.
3) Post -Transient Power Flow Analysis:
There were no post -transient power flow impacts identified with addition of the
Vernon Power Plant.
4) Transient Stability Analysis:
The transmission system remained in operating equilibrium throughout all
transmission contingencies with inclusion of the Project. Also the Vernon Power
Plant met the Low Voltage Ride -Through criterion. None of the Vernon Power
Plant generators tripped due to the adverse contingencies that were simulated.
Phase -to -ground faults were not simulated in the SIS since previously studied
projects that had a larger output did not reveal any problems.
5) Short -Circuit Analysis:
Preliminary three -phase -to -ground SCD analysis indicated that the Vernon
Power Plant contributed short circuit duties on several SCE owned circuit
breakers, but did not trigger any upgrades or replacement. However, studies
indicated that prior projects in the queue triggered upgrade and replacement of
62 SCE owned circuit breakers at a non -binding estimated cost of $17.123
million. Single -Line -to -Ground (SLG) circuit breaker evaluation will be performed
in the Facilities Study.
As specified in the "Summary of Facilities Study Scope" section, the impacts to SCE's
Distribution System will be evaluated as part of the Facilities Study.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 9 SUMMARY OF DELIVERABILITY STUDY RESULTS
A deliverability study has not yet been performed by the ISO. Such study will be performed in a
separate ISO study process at this time.
9
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 10 DETAILED FACILITIES STUDY WORK SCOPE & COST ESTIMATES
The detailed facilities study work scope and cost estimates will be provided in the Facilities Study
and will include the following items.
- Impacts to SCE's 66 kV systemTransmission, subtransmission and distribution line
evaluation
- Substation evaluation
- Land and right-of-way evaluation (Note Only the estimated cost to perform such
evaluation will be included in the study. The actual land and right-of-way evaluations
will be performed as part of the engineering and design work.)
- System protection evaluation
- Cost estimates (total costs) for the Participating TO'S Interconnection Facilities,
Distribution Upgrades and Netwok Upgrades
- The feasibility and associated estimated cost for interconnecting the gen-tie line at
the northwest side of Laguna Bell Substation.
10
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 11 ESTIMATED TIME TO CONSTRUCT (CONSTRUCTION SCHEDULE)
The estimated time to construct the required Participating TO's Interconnection Facilities,
Distribution Upgrades and Network Upgrades will be provided in the Facilities Study.
11
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 12 REASONS A RE -STUDY MAY BE NEEDED
Pursuant to Section 8.5 of the Large Generator Interconnection Procedures
(LGIP), a re -study of the Facilities Study may be needed due to a higher queued project
dropping out of the queue or a modification of a higher queued project pursuant to LGIP
Section 4.4, or any other effective change in information which necessitates a re -study.
12
CITY OF VERNON FOLIO NUMBER
LIGHT & POWER 503278
4305 SANTA FE AVENUE
VERNON, CALIFORNIA 90058-0805
(323) 583-8811
THE SUM OF D 10 0,0 0 Odols 0 Octs
California ISO
PAY TO 151 Blue Ravine Road
THE
ORDER OF Folsom, CA. 95630
Market & Product Development Div.
Attn: Roni Reese
Bank of America CHECK
16/66 NUMBER
usSo327811' 1:12200066 W L4S94-OS9S811-
.n�uico - nsnc CAKITA FC A\/F . VFRNnN CAI IFnRNIA 9(NISR-0805
CHECK DATE
08 22 1.
06
CHECK AMOUNT
100,000.00
VOID AFTER
90 DAYS
VENDOR NO.
VENDOR NAME
DATE CHECK ISSUED
CHECK NO.
000205
California ISO
08/22/06
503278
CITY ACCOUNT NUMBER
YOUR INV. NO.
YOUR INV. DATE
PAYMENT DESCRIPTION
DISC. TAKEN
NET AMT. PAID
055 100 9192 5962
OOAFCSCE
Deposit For Estimated Inter-
100,000.00
Connection Facilities Study
Cost For Interconnection Of V.P.
.
File Dated 09/05/06 LG
100,000.00
CITY CLERK'S OFFICE
INTEROFFICE MEMORANDUM
DATE: August 30, 2006
TO: Donal O'Callaghan, Director of Light & Power
FROM,4 Nelly Giron, Deputy City Clerk
RE: Resolution No. 9114 - A Resolution of the City Council of
the City of Vernon Approving and Authorizing the Execution
of an Interconnection Facilities Study Agreement By and
Between the City of Vernon and the California Independent
System Operator Corporation Regarding the Vernon Power Plant
Transmitted herewith is a copy of the fully executed agreement and
Resolution No. 9114, referenced above, which was approved by City
Council on August 16, 2006.
Thank you.
NG:dr
c: Resolution File No. 9114
Agreement File No. 06-096
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
INTERCONNECTION FACILITIES STUDY AGREEMENT
THIS AGREEMENT is made and entered into this211Tday of WWII', 20 o 6 by
and between City of Vernon, a municipal corporation organized and existing under the
laws of the State of California, ("Interconnection Customer,") and the California
Independent System Operator Corporation, a California nonprofit public benefit
corporation existing under the laws of the State of California, ("ISO"). The
Interconnection Customer and the ISO each may referred to as a "Party," or
collectively as the "Parties."
RECITALS
WHEREAS, the Interconnection Customer is proposing to develop a Large
Generating Facility or generating capacity addition to an existing Generating Facility
consistent with the Interconnection Request submitted by the Interconnection ,Customer
dated September 9, 2005 and
WHEREAS, the Interconnection Customer desires to interconnect the Large
Generating Facility with the ISO Controlled Grid;
WHEREAS, the ISO has completed an Interconnection System Impact Study
(the "System Impact Study") and provided the results of said study to the
Interconnection Customer; and
WHEREAS, the Interconnection Customer has requested the ISO to conduct or
cause to be performed an Interconnection Facilities Study to specify and estimate the
cost of the equipment, engineering, procurement and construction work needed on the
Participating TO's electric system to implement the conclusions of the Interconnection
System Impact Study in accordance with Good Utility Practice to physically and
electrically connect the Large Generating Facility to the ISO Controlled Grid.
NOW, THEREFORE, in consideration of and subject to the mutual covenants
contained herein the Parties agreed as follows:
1.0 When used in this Agreement, with initial capitalization, the terms
specified shall have4he meanings indicated in the LSO's FERC-approved
Standard Large Generation Interconnection Procedures ("LGIP") or the,
Master Definitions Supplement, Appendix A to the ISO Tariff, as
applicable.
2.0 The Interconnection Customer elects and the ISO shall conduct or cause
to be performed an Interconnection Facilities Study consistent with the
LGIP in accordance with the ISO Tariff.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
3.0 The scope of the Interconnection Facilities Study shall be subject to the
assumptions set forth in Attachment A and the data provided in
Attachment B to this Agreement.
4.0 The Interconnection Facilities Study report (i) shall provide a description,
estimated cost, including, if applicable, the cost of remedial measures that
address the financial impacts, if any; on Local Furnishing Bonds, of
(consistent with Attachment A), and schedule for required facilities or for
effecting remedial measures that address the financial impacts, if any, on
Local Furnishing Bonds within each Participating TO's electric system to
interconnect the Large Generating Facility to the ISO Controlled Grid and
(ii) shall address the short circuit, instability, and power flow issues
identified in the Interconnection System Impact Study.
5.0 The Interconnection Customer shall provide a deposit of the greater of
$100,000 or the Interconnection Customer's portion of the estimated
monthly cost for the performance of the Interconnection Facilities Study.
The time for completion of the Interconnection Facilities Study is specified
in Attachment A. For studies where the estimated cost exceed $100,000,
the ISO may invoice Interconnection Customer on a monthly basis for the
work to be conducted on the Interconnection Facilities Study for the
remaining balance of the estimated Interconnection Facilities Study cost.
The Interconnection Customer shall pay invoiced amounts within thirty
(30) Calendar Days of receipt of invoice. The ISO shall continue to hold
the amounts on deposit until settlement of the final invoice.
Following the issuance of the Interconnection Facilities. Study, the ISO
shall charge and the Interconnection Customer shall pay the actual costs
of the Interconnection Facilities Study, inclusive of any re -studies and
amendments. to the Interconnection Facilities Study, pursuant to Section 9
of this Agreement.
Any difference between the deposit made toward the Interconnection
Facilities Study and the actual cost of the study, inclusive of any re -studies
and amendments thereto, shall be paid by or refunded to the
Interconnection Customer, as appropriate in accordance with Section 13.3
of the LGIP.
6.0 The Interconnection Facilities Study will be based upon the results of the
Interconnection System Impact Study and the technical information
provided by the Interconnection Customer in the Interconnection Request,
subject to any modifications in accordance with Section 4.4 of the LGIP.
The ISO reserves the right to request additional technical information from
the Interconnection Customer as may reasonably become necessary
consistent with Good Utility Practice during the course of the
Interconnection Facilities Study.
4
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
If the Interconnection Customer modifies its Interconnection Request or
the technical information provided therein is modified, the time to complete
the Interconnection Facilities Study may be extended.
7.0 Pursuant to Section 3.7 of the LGIP, the ISO will coordinate the conduct of
any studies required to determine the impact of the Interconnection
Request on Affected Systems. The ISO may provide a copy of the
Interconnection Facilities Study results to an Affected System Operator
and the Western Electricity Coordinating Council. Requests for review
and input from Affected System Operators or the Western Electricity
Coordinating Council may arrive at any time prior to interconnection, and a
revision of the Interconnection Facilities Study or re -study may be required
in such event.
8.0 Substantial portions of technical data and assumptions used to perform
the Interconnection Facilities Study, such as system conditions, existing
and planned generation, and unit modeling, may change after the ISO
provides the Interconnection Facilities Study results to the Interconnection
Customer. Study results will reflect available data at the time the ISO
provides the'Interconnection Facilities Study to the Interconnection
Customer. The ISO shall not be responsible for any additional costs,
including, without limitation, costs of new or additional facilities, system
upgrades, or schedule changes, that may be incurred by the
Interconnection Customer as a result of changes in such data and
assumptions.
9.0 In the event that a re -study or amendment of the Interconnection Facilities
Study is required, the ISO shall provide notification of the need for such
re -study or amendment, and the Interconnection Customer shall provide
direction as to whether to proceed with the re -study or amendment and
any associated deposit payment pursuant to Section 8.5 or Section 12.2.4
of the LGIP, as applicable.
10.0 The ISO shall maintain records and accounts of all costs incurred in
performing the Interconnection Facilities Study, inclusive of any re -studies
or amendments thereto, in sufficient detail to allow verification of all costs
incurred, including associated overhead. The Interconnection Customer
shall have the right, upon reasonable notice, within a reasonable time at
the ISO offices and at its own expense, to audit the ISO's records as
necessary and as appropriate in order to verify costs incurred by the ISO.
Any audit requested by the Interconnection Customer shall be completed,
and written notice of any audit dispute provided to the ISO within one
hundred eighty (180) Calendar Days following receipt by the
Interconnection Customer of the ISO's notification of the final costs of the
3
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Interconnection Facilities Study, inclusive of any re -study or amendment
thereto.
11.0 In accordance with Section 3.8 of the LGIP, the Interconnection Customer
may withdraw its Interconnection Request at any time by written notice to
the ISO. Upon receipt of such notice, this Agreement shall terminate.
12.0 Pursuant to Section 8.1 of the LGIP, this Agreement shall become
effective upon the date the fully executed Agreement and deposit
specified in Section 6 of this Agreement are received by the ISO. If the
ISO does not receive the fully executed Agreement and payment pursuant
to Section 8.1 of the LGIP, then the Interconnection Request will be
deemed withdrawn upon the Interconnection Customer's receipt of written
notice by the ISO pursuant to Section 3.8 of the LGIP.
13.0 Miscellaneous.
13.1 Dispute Resolution. Any dispute, or assertion of a claim, arising out of or
in connection with this Interconnection Facilities Study Agreement, shall
be resolved in accordance with Section 13.5 of the LGIP.
13.2 Confidentiality. Confidential Information shall be treated in accordance
with Section 13.1 of the LGIP.
13.3 Binding Effect. This Interconnection Facilities Study Agreement and the
rights and obligations hereof, shall be binding upon and shall inure to the
benefit of the successors and assigns of the Parties hereto.
13.4 Conflicts. In the event of a conflict between the body of this .
Interconnection Facilities Study Agreement and any attachment,
appendices or exhibits hereto, the terms and provisions of the body of this
Interconnection Facilities Study Agreement shall prevail and be deemed
the final intent of the Parties.
13.5 Rules of Interpretation. This Interconnection Facilities Study Agreement,
unless a clear contrary intention appears, shall be construed and
interpreted as follows: (1) the singular number includes the plural number
and vice versa; (2) reference to any person includes such person's
successors and assigns but, in the case of a Party, only if such
successors and assigns are permitted by this Interconnection Facilities
Study Agreement, and reference to a person in a particular capacity
excludes such person in any other capacity or individually; (3) reference to
any agreement (including this Interconnection Facilities Study Agreement),
document, instrument or tariff means such agreement, document,
instrument, or tariff as amended or modified and in effect from time to time
in accordance with the terms thereof and, if applicable, the terms hereof;
4
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
(4) reference to any applicable laws and regulations means such
applicable laws and regulations as amended, modified, codified, or
reenacted, in whole or in part, and in effect from time to time, including, if
applicable, rules and regulations promulgated thereunder; (5) unless
expressly stated otherwise, reference to any Article, Section or Appendix
means such Article or Section of this Interconnection Facilities Study
Agreement or such Appendix to this Interconnection Facilities Study
Agreement, or such Section to the LGIP or such Appendix to the LGIP, as
the case may be; (6) "hereunder", "hereof", "herein", "hereto" and words of
similar import shall be deemed references to this Interconnection Facilities
Study Agreement as a whole and not to any particular Article, Section, or
other provision hereof or thereof; (7) "including" (and with correlative
meaning "include") means including without limiting the generality of any
description preceding such term; and (8) relative to the determination of
any period of time, "from" means "from and including", "to"means "to but
excluding" and "through" means "through and including".
13.6 Entire Agreement. This Interconnection Facilities Study Agreement,
including all Appendices and Schedules attached hereto, constitutes the
entire agreement between the Parties with reference to the subject matter
hereof, and supersedes all prior and contemporaneous understandings or
agreements, oral or written, between the Parties with respect to the
subject matter of this Interconnection Facilities Study Agreement. There
are no other agreements, representations, warranties, or covenants which
constitute any part of the consideration for, or any condition to; any Party's
compliance with its obligations under this Interconnection Facilities Study
Agreement.
13.7 No Third Party Beneficiaries. This Interconnection Facilities Study
Agreement is not intended to and does not create rights, remedies, or
benefits of any character whatsoever in favor of any persons,
corporations, associations, or entities other than the Parties, and the
obligations herein assumed, are solely for the use and benefit of the
Parties, their successors in interest and, where permitted, their. assigns
13.8 Waiver. The failure of a Party to this Interconnection Facilities Study
Agreement to insist, on any occasion, upon strict performance of any
provision of this Interconnection Facilities Study Agreement will not be
considered a waiver of any obligation, right, or duty of, or imposed upon,
such Party.
Any waiver at any time by either Party of its rights with respect to this
Interconnection Facilities Study Agreement shall not be deemed a
continuing waiver or a waiver with respect to any other failure to comply
with any other obligation, right, duty of this Interconnection Facilities Study
Agreement. Termination or default of this Interconnection Facilities Study
5
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Agreement for any reason by the Interconnection Customer shall not
constitute a waiver of the Interconnection Customer's legal rights to obtain
an interconnection from the Participating TO or ISO. Any waiver of this
Interconnection Facilities Study Agreement shall, if requested, be provided
in writing.
Any waivers at any time by any Party of its rights with respect to any
default under this Interconnection Facilities Study Agreement, or with
respect to any other matter arising in connection with this Interconnection
Facilities Study Agreement, shall not constitute or be deemed a waiver
with respect to any subsequent default or other matter arising in
connection with this Interconnection Facilities Study Agreement. Any
delay, short of the statutory period of limitations, in asserting or enforcing
any right under this Interconnection Facilities Study Agreement shall not
constitute or be deemed a waiver of such right.
13.9 Headings. The descriptive headings of the various Articles and Sections
of this Interconnection Facilities Study Agreement have been inserted for
convenience of reference only and are of no significance in the
interpretation or construction of this Interconnection Facilities Study
Agreement.
13.10 Multiple Counterparts. This Interconnection Facilities Study Agreement
may be executed in two or more counterparts, each of which is deemed
an original but all constitute one and the same instrument.
13.11 Amendment. The Parties may by mutual agreement amend this
Interconnection Facilities Study Agreement by a written instrument duly
executed by both of the Parties.
13.12 Modification by the Parties. The Parties may by mutual agreement. amend
the Appendices to this Interconnection Facilities Study Agreement by a
written instrument duly executed by both of the Parties. Such amendment
.shall become effective and a part of this Interconnection Facilities Study
Agreement upon satisfaction of all applicable laws and regulations.
13.13 Reservation of Rights. The ISO shall have the right to make a unilateral
filing with FERC to modify this Interconnection Facilities Study Agreement
with respect to any rates, terms and conditions, charges, classifications of
service, rule or regulation under section 205 or any other applicable
provision of the Federal Power Act and FERC's rules and regulations
thereunder, and Interconnection Customer shall have the right to make a
unilateral filing with FERC to modify this Interconnection Facilities Study
Agreement pursuant to section 206 or any other applicable provision of
the Federal Power Act and FERC's rules and regulations thereunder;
provided that each Party shall have the right to protest any such filing by
A
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
another Party and to participate fully in any proceeding before FERC in
which such modifications may considered. Nothing in this
Interconnection Facilities Study'Agreement shall limit the rights of the
Parties or of FERC under sections 205 or 206 of the Federal Power Act
and FERC's rules and regulations thereunder, except to the extent that the
Parties otherwise mutually agree as provided herein.
13.14 No Partnership. This Interconnection Facilities Study Agreement shall not
be interpreted or construed to create an association, joint venture, agency
relationship, or partnership between the Parties or to impose any
partnership obligation or partnership liability upon any. Party. No, Party.
shall have any right, power or authority to enter into any agreement or
undertaking for, or act on behalf of, or to act as or be an agent or
representative of, or to otherwise bind, another Party.
13.15 Assignment. This Interconnection Facilities Study Agreement may be
assigned by a Party only with the written consent of the other Party;
provided that a Party may assign this Interconnection Facilities Study
Agreement without the consent of the other Party to any Affiliate of the
assigning Party with an equal or greater credit rating and with the legal
authority and operational ability to satisfy the obligations of the assigning
Party under this Interconnection Facilities Study Agreement; -and provided
further that the Interconnection Customer shall have the right to assign
this Interconnection Facilities Study Agreement, without the consent of the
other Party, for collateral security purposes to aid in providing financing for
the Large Generating Unit, provided that the Interconnection Customer will
require any secured party, trustee or mortgagee to notify the other Party of
any such assignment. Any financing arrangement entered into by the
Interconnection Customer pursuant to this Article will provide that prior to
or upon the exercise of the secured party's, trustee's or mortgagee's
assignment rights pursuant to said arrangement, the secured creditor, the
trustee or mortgagee will notify the other Party of the date and particulars
of any such exercise of assignment right(s). Any attempted assignment
that violates this Article is void and ineffective. Any assignment under this
Interconnection. Facilities Study Agreement shall not relieve a Party of its
obligations, nor shall a Party's obligations be enlarged, in whole or in part,
by reason thereof. Where required, consent to assignment will not be
unreasonably withheld, conditioned or delayed.
7
l
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly
executed by their duly authorized officers or agents on the day and year first above
written.
California Independent System Operator Corporation
By:�
Title: V I P r'e 5 i d.e-�I-A-
Date: -7 ) a 6. / e:.00 V
City of Vernon
Title: Mayor
Date: August 21, 2006
ATTEST:
Bruce V. Malkenhorst, Jr.
Acting City Clerk
APPROVES AS TO FORM:
Hhrrison
f Assistant City Attorney
INTERCONNECTION FACILITIES STUDY AGREEMENT
Attachment A
Interconnection Facilities
Study Agreement
INTERCONNECTION CUSTOMER SCHEDULE ELECTION FOR CONDUCTING THE
INTERCONNECTION FACILITIES STUDY
The ISO shall use Reasonable Efforts to complete the study and issue a draft
Interconnection Facilities Study report to the Interconnection Customer. Prior to issuing
draft study results to the Interconnection Customer, the Participating TO and ISO shall
share results for review and incorporate comments within, the following number of days
after of receipt of an executed copy of this Interconnection Facilities Study Agreement:
one hundred twenty (120) Calendar Days with no more than a +/- 20
percent cost estimate contained in the report, or
two hundred ten (210) Calendar Days with no more than a +/- 10 percent
cost estimate contained in the report.
9
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Attachment B
Interconnection Facilities
Study Agreement
DATA FORM TO BE PROVIDED BY THE INTERCONNECTION CUSTOMER
WITH THE INTERCONNECTION FACILITIES STUDY AGREEMENT
Provide two copies of this completed form and other required plans and diagrams in
accordance with Section 8.1 of the LGIP.
Provide location plan and one -line diagram of the plant and station facilities. For staged
projects, please indicate future generation, transmission circuits, etc.
One set of metering is required for each generation connection to the new bus or
existing ISO Controlled Grid station. Number of generation connections:
On the one line indicate the generation capacity attached at each metering location.
(Maximum load on CT/PT)
On the one line indicate the location of auxiliary power. (Minimum load on CT/PT)
Will an alternate source of auxiliary power be available during CT/PT maintenance?
Yes No
Will a transfer bus on the generation side of the metering require that each meter set be
designed for the total plant generation? Yes No
(Please indicate on one line).
What type of control system or PLC will be located at the Interconnection Customer's
Large Generating Facility?
What protocol does the control system or PLC use?
Please provide a 7.5-minute quadrangle of the site. Sketch the plant, station,
transmission line, and property line.
10
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Physical dimensions of the proposed interconnection station:
Bus length from generation to interconnection station:
Line length from interconnection station to the Participating TO's transmission line.
Tower number observed in the field. (Painted on tower leg)*
Number of third party easements required for transmission Iines*:
* To be completed in coordination with the Participating TO or ISO.
Is the Large Generating Facility in the Participating TO's service area?
Yes No
Local service provider for auziliary and other power:
Please provide proposed schedule dates:
Begin Construction Date:
Generator step-up transformer Date:
receives back feed power
Generation Testing Date:;
Commercial Operation Date:
Level of Deliverability: Choose one of the following:
Deliverability with no Network Upgrades
100% Deliverability
11
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
ATTACHMENT C
Study Plan
12
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 1 PROJECT SUMMARY
The Vernon Power Plant to be studied is a 610 MW (net) plant. An incremental 304 MW
(net) increase to the Vernon Power Plant has been requested in a separate
Interconnection Request. The full configuration of the natural gas fired combined cycle
plant will consist of three gas turbines and one steam turbine with a total net output of 914
MW. The Vernon Power Plant will be located at 3200 Fruitland Avenue in Vernon,
California, and will be interconnected to Southern California Edison Company's ("SCE")
Laguna Bell Substation 230kV bus via a double circuit 230 kV transmission line. The
City of Vernon (the "Interconnection Customer") has requested a March 31, 2009 in-
service date, a May 31,.2009 Trial Operation date, anda July 31, 2009 Commercial
Operation date.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Table of Contents
ProjectSummary ..........................................................................................................................................................1
Summaryof Facilities Study Scope.......................................'................................................................................:.:..2 0
FacilitiesStudy Schedule.............................................................................................................................................3
CostEstimates Summary ............................................................................................................................................4
SiteVicinity Map...........................................................................................................................................................5
ConceptualOne -Line Diagram...................................................................................................................................6
FacilitiesStudy Assumptions.......................................................................................................................................7
Summary of the SIS Results & Mitigation Plan..........................................................................................................8
Summaryof Deliverability Study Results...................................................................................................................9
Detailed Facilities Study Work Scope & Cost Estimates .................................. :...................................................... 10
Estimated Time to Construct (Construction Schedule)...........................................................................................11
Reasonsa Re -Study May Be Needed.....................................................................................................................12
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
Facilities Study
Study Plan
City of Vernon
Vernon Power Plant (610 MV1)
July 27, 2006
v California ISO
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 2 SUMMARY OF FACILITIES STUDY SCOPE
The Interconnection Facilities Study ("Facilities Study") shall include the following
scope of work: (i) the identification of the Participating TO's Interconnection Facilities,
Distribution Upgrades and Network Upgrades necessary to interconnect the' Vernon
Power Plant, (ii) the estimated cost of such required facilities and upgrades, and (iii) the
estimated time to complete the required facilities and upgrades.
In addition, the Interconnection System Impact Study report dated June 23, 2006
did not include an evaluation of SCE's Distribution System. The impacts to the
Distribution System will be evaluated as part of the Facilities Study.
Vernon has also requested that the Facilities Study include an evaluation of the
feasibility and associated cost with interconnecting the gen-tie line at the northwest side
of Laguna Bell Substation. The estimated cost and time to perform such study will be
evaluated after Vernon provides the details of such request. As a result, the estimated
time to complete the study as specified below may need to be revised.
2
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 3 FACILITIES STUDY SCHEDULE
The study is scheduled to be completed as follows:
- one hundred twenty (120) Calendar Days, with no more than a +/- 20
percent cost estimate
- two hundred ten (210) Calendar Days, with no more than a +/- 10 percent
cost estimate
3
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 4 COST ESTIMATES SUMMARY
The estimated costs for the Participating TO's Interconnection Facilities will
include the costs associated with sole use facilities between the Vernon Power Plant
and the Point of Interconnection at Laguna Bell Substation, which do ' not include
Distribution Upgrades or, Network Upgrades, to accommodate the Vernon. Power
Project. Such facilities include those required to terminate the 230 kV double circuit
gen-tie line at Laguna Bell Substation and any protection equipment, communication
equipment, controls and other facilities associated with such termination.
The estimated costs for Network Upgrades will include the facilities and upgrades
required at or beyond the Point of Interconnection, including substation facilities at
Laguna Bell Substation; transmission facilities, protection equipment, communication
equipment, and controls at Laguna Bell Substation; and facilities required beyond
Laguna Bell Substation, such as at other substations and on other transmission lines in.
the ISO Controlled Grid to accommodate the interconnection of the Vernon Power
Plant.
The estimated costs for Distribution Upgrades will include the facilities and
upgrades, including substations and subtransmission and distribution lines, required on
SCE's Distribution System to accommodate the interconnection of the Vernon Power
Plant.
4
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 5 SITE VICINITY MAP
The site vicinity map showing the project location and the proposed Point of
Interconnection will be provided in the Facilities Study.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 6 CONCEPTUAL ONE -LINE DIAGRAM
The conceptual one -line diagram, showing the proposed Point of Interconnection
will be provided in the Facilities Study.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 7 FACILITIES STUDY ASSUMPTIONS
The Facilities Study will be based on the results of the Interconnection System
Impact Study ("SIS") and upon the following assumptions:
1) An Interconnection Customer requested in-service date of March 31, 2009, a Trial
Operation date of May 31, 2009, and a Commercial Operation date of July 31, 2009;
however, such assumptions shall be subject to change. after study results, permitting
requirements, design, land issues and material lead times are known, so that a more
accurate determination can be made.
2) The technical data supplied by the Interconnection Customer for this Large
Generating Facilities are accurate and complete.
3) The maximum interconnection capacity requested by the Interconnection Customer is
610 MW.
4) The Interconnection Customer will install, own, operate and maintain all ISO metering
equipment. The ISO metering equipment will be located on the Interconnection
Customer's side of the Point of Interconnection.
5) The Interconnection Customer shall design the Large Generating Facility to maintain
a composite power delivery at continuous rated power output at the terminals of the
Electric Generating Unit at a power factor within the range of 0.95 leading to 0.90
lagging, unless the ISO has established different requirements that apply to all
generators in the Control Area on a comparable basis.
6) The Facilities Study results will reflect the ISO Tariff, rules and protocols and SCE's
Interconnection Handbook in effect at the time SCE provides the Facilities Study
results to the Interconnection Customer.
7) Unless otherwise agreed to by SCE, it is assumed that Vernon will design, build, and
own the double circuit 230 kV generation tie line that will connect the plant switchyard
to the Laguna Bell 230kV Bus
7
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 8 SUMMARY, OF THE SIS RESULTS & MITIGATION PLAN
The results and mitigation plan identified in the SIS for the bulk power system are as follows:
1) Interconnection of Vernon Power Plant into Laguna Bell Substation:
The non -binding cost estimate to terminate the 230kV double circuit gen-tie line
into Laguna Bell Substation, including the work required to reconfigure the
substation in order to accommodate the line, is $30 million.
2) Power Flow Analysis:
Studies identified that with addition of the Vernon Power Plant, the Lighthipe-
Mesa 230 kV line was overloaded from 2424Amps/101 % to 2671 Amps/111 %
under the outages of Laguna Bell -Rio Hondo 230 kV No.1 line and Mesa -
Redondo 230 kV No.1 line. Such overload was triggered in the base case and
will be the responsibility of SCE to mitigate. Such mitigation will be performed by
removing or upgrading wave traps on the Lighthipe-Mesa No. 1 230 kV line and
modifying the protection for such line.
3) Post -Transient Power Flow Analysis:
There were no post -transient power flow impacts identified with addition of the
Vernon Power Plant.
4) Transient Stability Analysis:
The transmission system remained in operating equilibrium throughout all
transmission contingencies with inclusion of the Project. Also the Vernon Power
Plant met the Low Voltage Ride -Through criterion. None of the Vernon Power
Plant generators tripped due to the adverse contingencies that were simulated.
Phase -to -ground faults were not simulated in the SIS since previously studied
projects that had a larger output did not reveal any problems.
5) Short -Circuit Analysis:
Preliminary three -phase -to -ground SCD analysis indicated that the Vernon
Power Plant contributed short circuit duties on several SCE owned circuit
breakers, but did not trigger any upgrades or replacement. However, studies
indicated that prior projects in the queue triggered upgrade and replacement of
62 SCE owned circuit breakers at a non -binding estimated cost of $17.123
million. Single -Line -to -Ground (SLG) circuit breaker evaluation will be performed
in the Facilities Study.
As specified in the "Summary of Facilities Study Scope" section, the impacts to SCE's
Distribution System will be evaluated as part of the Facilities Study.
f3
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 9 SUMMARY OF DELIVERABILITY STUDY RESULTS
A deliverability study has not yet been performed by the ISO. Such study will be performed in a
separate ISO study process at this time.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 10 DETAILED FACILITIES STUDY WORK SCOPE & COST ESTIMATES
The detailed facilities study work scope and cost estimates will be provided in the Facilities Study
and will include the following items. -
Impacts to SCE's 66 kV systemTransmission, subtransmission and distribution line
evaluation
Substation evaluation
Land and right-of-way evaluation (Note: Only the estimated cost to perform such
evaluation will be included in the study. The actual land and right-of-way evaluations
will be performed as part of the engineering and design work.)
- System protection evaluation
Cost estimates (total costs) for the Participating TO'S interconnection Facilities,
Distribution Upgrades and Netwok Upgrades
- The feasibility and associated estimated cost for interconnecting the gen-tie line at
the northwest side of Laguna Bell Substation.
10
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWER PLANT
CHAPTER 11 ESTIMATED TIME TO CONSTRUCT (CONSTRUCTION SCHEDULE)
The estimated time to construct the required Participating TO's Interconnection Facilities,
Distribution Upgrades and Network Upgrades will be provided in the Facilities Study.
INTERCONNECTION FACILITIES STUDY AGREEMENT
VERNON POWERPLANT
CHAPTER 12 REASONS A RE -STUDY MAY BE NEEDED
Pursuant to Section 8.5 of the Large Generator Interconnection Procedures
(LGIP), a re -study of the Facilities Study may be needed due to a higher queued project
dropping out of the queue or a modification of a higher queued project pursuant to LGIP
Section 4.4, or any other effective change in information which necessitates a re -study.